(1) WELL VENT. Each well shall be vented to the atmosphere in accordance with the following requirements:
(a) For wells without pitless units, a metal
vent pipe shall be installed that terminates in a 24-mesh corrosion resistant
screened "U" bend or mushroom cap at least 24 inches above the floor. The vent
pipe diameter shall be a minimum of 2 inches for well casings 10 inches in
diameter and larger. The department may, on a case-by-case basis, allow smaller
diameter well vents on existing installations if water drawdown has not
compromised the sanitary seal or require larger diameter well vents for wells
with significant water level drawdown. Vent piping shall be welded watertight
to the side of the well casing a minimum of 4 inches above the floor and may
extend through a concrete pump base or collar where one is present.
Alternatively, vent piping may project through a well seal or pump discharge
head if the well seal or discharge head is watertight and will facilitate the
installation of the vent pipe.
(b)
For wells with pitless units, a metal vent pipe shall be installed which
terminates in a 24-mesh corrosion resistant screened "U" bend or mushroom cap
at least 24 inches above the floor. The pitless unit vent area shall be equal
to or greater than the area provided by a 2-inch diameter vent pipe for pitless
units 10 inches in diameter or larger. Vent piping shall extend above or be
incorporated into the top of the pitless unit or be welded watertight to the
side of the pitless unit a minimum of 4 inches above the floor and may extend
through a concrete pump base or collar where one is present.
Note: It is recommended that vent installations for pitless units be factory installed to prevent damage to the integrity of factory units and paint systems.
(c) If the well is flowing, the vent shall
terminate above the artesian water level or a suitable automatic valve shall be
provided.
(2) WATER LEVEL MEASUREMENTS.
(a) Provisions shall be
made for measurement of static and pumping water levels in the completed well
by the use of an electric depth gauge, pressure transducer or an air line
attached to the pump column and an altitude gauge.
(b) The installation shall be constructed to
prevent entrance of foreign material.
(c) Air lines may not be installed through
vent pipes unless justified when modifications are being made to existing
installations, the minimum 2-inch diameter vent pipe area is maintained where
applicable, and the specific approval of the department is obtained.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.