Section NR 724.15 - Documentation of construction and completion
Current through August 26, 2024
(1) Unless otherwise directed by the department, responsible parties shall submit to the department a construction documentation or as-built report within 60 days after the date that construction of a remedial action or any interim action specified in s. NR 724.02(1) is completed or determined to be essentially complete by the department.
(2) The report shall document that the completed final remedial or interim action meets or exceeds all design criteria and the plans and specifications developed in accordance with all of the requirements of this chapter.
(3) Unless otherwise directed by the department, the construction documentation report shall include all of the following information: