Wisconsin Administrative Code
Department of Natural Resources
NR 700-799 - Environmental Protection - Investigation and Remediation of Environmental Contamination
Chapter NR 724 - Remedial and interim action design, implementation, operation, maintenance and monitoring requirements
Section NR 724.13 - Operation and maintenance
Current through August 26, 2024
(1) GENERAL.
(2)OPERATION AND MAINTENANCE PLAN. Unless otherwise directed by the department, responsible parties shall submit to the department an operation and maintenance plan when on-site maintenance activities are necessary to implement, monitor or ensure the effectiveness of a remedial or interim action. The plan shall outline all operation, monitoring, and maintenance activities, from design through case closure under ch. NR 726 or through post-closure under ch. NR 727, as appropriate, including all of the following information:
Note: Engineering controls may include a cover, barrier, or vapor mitigation system.
Note: More site-specific information may be found in the department's files.
(3)PROGRESS REPORTS. In addition to the general progress reporting requirements in s. NR 700.11, responsible parties shall submit semi-annual operation and maintenance progress reports to the department. Progress reports shall be sequentially numbered, starting with the first report which is due no later than 6 months after the remediation system begins operation. Information related to operation and maintenance shall be provided on a reporting form supplied by the department. The department may require progress reports be submitted at a different frequency than semi-annually.
Note: Operation and maintenance progress reports should be submitted for both active and passive remediation systems. Progress reports required under this subsection are not the same as post-closure maintenance inspection logs for remedies such as performance standard covers.
Note: Copies of remediation system operation and maintenance reporting forms may be obtained from any regional office of the department, or by writing to the Department of Natural Resources, Bureau for Remediation and Redevelopment, P.O. Box 7921, Madison, Wisconsin 53707, or at http://dnr.wi.gov/files/PDF/forms/4400/4400-194.pdf.
(4)OPERATION AND MAINTENANCE PLAN REVISIONS. When warranted by changes in the design, operation or maintenance of the interim or remedial action, or when requested by the department, responsible parties shall revise the appropriate section of the operation and maintenance plan. Plan revisions shall be submitted to the department and shall: