(1) GENERAL. All sampling, field work and development of plans for field activities for response actions being taken to satisfy the requirements of ss. NR 708.09 to 708.15 or chs. NR 716 to 754 shall be conducted by or under the supervision of a professional engineer, hydrogeologist or scientist, unless sub. (2) or an exemption in s. NR 712.11 is applicable.
(2)SAMPLING FOR IMMEDIATE AND INTERIM ACTIONS NOT INVOLVING TREATMENT OR ENGINEERING CONTROLS. For immediate actions and interim actions that do not involve treatment or engineering controls, samples of air, soil, water or other media for field measurement or analytical laboratory analysis are not required to be collected under the supervision of a professional engineer, hydrogeologist or scientist, but shall be collected by one of the following, unless the sampling is exempt under s. NR 712.11(2):
(3)SAMPLING FOR INTERIM ACTIONS INVOLVING TREATMENT OR ENGINEERING CONTROLS AND REMEDIAL ACTIONS. For remedial actions and interim actions that involve treatment or engineering controls, samples of air, soil, water or other media for field measurements or analytical laboratory analysis shall be collected by a professional engineer, hydrogeologist, scientist or any one of the following working under the supervision of a professional engineer, hydrogeologist or scientist, unless the sampling is exempt under s. NR 712.11(2):
(4)TRAINING AND EXPERIENCE.
(5)SOIL BORING LOGS.