Wisconsin Administrative Code
Department of Natural Resources
NR 600-699 - Environmental Protection - Hazardous Waste Management
Chapter NR 665 - Interim License Hazardous Waste Treatment, Storage And Disposal Facility Standards
Subchapter K - Surface Impoundments
Section NR 665.0221 - Design and operating requirements
Current through August 26, 2024
(1) The owner or operator of each new surface impoundment unit, each lateral expansion of a surface impoundment unit, and each replacement of an existing surface impoundment unit shall install 2 or more liners and a leachate collection and removal system between the liners, and operate the leachate collection and removal system in accordance with s. NR 664.0221(3), unless exempted under s. NR 664.0221(4), (5), or (6).
(2) The owner or operator of each unit referred to in sub. (1) shall notify the department at least 60 days prior to receiving waste. The owner or operator of each facility submitting notice shall file a feasibility and plan of operation report within 6 months of the receipt of the notice.
(3) The owner or operator of any replacement surface impoundment unit is exempt from sub. (1) if both of the following apply:
(4) The double liner requirement in sub. (1) may be waived by the department for any monofill, if the requirements of pars. (a) and (b) 1. or 2. are met:
(5) In the case of any unit in which the liner and leachate collection system has been installed pursuant to the requirements of sub. (1) and in good faith compliance with sub. (1) and with guidance documents governing liners and leachate collection systems under sub. (1), no liner or leachate collection system which is different from that which was so installed pursuant to sub. (1) will be required for the unit by the department when issuing the first operating license to the facility, except that the department will not be precluded from requiring installation of a new liner when the department has reason to believe that any liner installed pursuant to the requirements of sub. (1) is leaking.
(6) A surface impoundment shall maintain enough freeboard to prevent any overtopping of the dike by overfilling, wave action or a storm. Except as provided in sub. (7), there shall be at least 60 centimeters (2 feet) of freeboard.
(7) A freeboard level less than 60 centimeters (2 feet) may be maintained if the owner or operator obtains certification by a qualified engineer that alternate design features or operating plans will, to the best of that person's knowledge and opinion, prevent overtopping of the dike. The certification, along with a written identification of alternate design features or operating plans preventing overtopping, shall be maintained at the facility.
(8) Surface impoundments that are newly subject to 42 USC 6925(j) (1) due to the promulgation of additional listings or characteristics for the identification of hazardous waste shall be in compliance with subs. (1), (3) and (4) not later than 48 months after the promulgation of the additional listing or characteristic. This compliance period may not be cut short as the result of the promulgation of land disposal prohibitions under ch. NR 668 or the granting of an extension to the effective date of a prohibition pursuant to s. NR 668.05, within this 48-month period.