Wisconsin Administrative Code
Department of Natural Resources
NR 600-699 - Environmental Protection - Hazardous Waste Management
Chapter NR 665 - Interim License Hazardous Waste Treatment, Storage And Disposal Facility Standards
Subchapter H - Financial Requirements
Section NR 665.0142 - Cost estimate for closure
Current through August 26, 2024
(1) The owner or operator shall have a detailed written estimate, in current dollars, of the cost of closing the facility in accordance with the requirements in ss. NR 665.0111 to 665.0115 and applicable closure requirements in ss. NR 665.0197, 665.0228, 665.0258, 665.0310, 665.0351, 665.0381, 665.0404 and 665.1102.
(2) During the active life of the facility, the owner or operator shall adjust the closure cost estimate for inflation within 60 days prior to the anniversary date of the establishment of the financial instrument(s) used to comply with s. NR 665.0143. For owners and operators of disposal facilities using the net worth test, the closure cost estimate shall be updated for inflation as required under s. 289.41(5) (d), Stats. The adjustment may be made by recalculating the closure cost estimate in current dollars, or by using an inflation factor derived from the most recent implicit price deflator for gross domestic product published by the U.S. department of commerce in its Survey of Current Business, as specified in pars. (a) and (b). The inflation factor is the result of dividing the latest published annual deflator by the deflator for the previous year.
(3) During the active life of the facility, the owner or operator shall revise the closure cost estimate no later than 30 days after a revision has been made to the closure plan which increases the cost of closure. If the owner or operator has an approved closure plan, the closure cost estimate shall be revised no later than 30 days after the department has approved the request to modify the closure plan, if the change in the closure plan increases the cost of closure. The revised closure cost estimate shall be adjusted for inflation as specified in sub. (2).
(4) The owner or operator shall keep the following at the facility during the operating life of the facility: The latest closure cost estimate prepared in accordance with subs. (1) to (3) and, when this estimate has been adjusted in accordance with sub. (2), the latest adjusted closure cost estimate.