Wisconsin Administrative Code
Department of Natural Resources
NR 600-699 - Environmental Protection - Hazardous Waste Management
Chapter NR 661 - Hazardous Waste Identification And Listing
Subchapter H - Financial Requirements for Management of Excluded azardous Secondary Material
Section NR 661.0142 - Cost estimate
Current through August 26, 2024
(1) The owner or operator shall have a detailed written estimate, in current dollars, of the cost of disposing of any hazardous secondary material as listed or characteristic hazardous waste, and the potential cost of closing the facility as a treatment, storage, and disposal facility. The estimate shall include all of the following:
(2) During the active life of the facility, the owner or operator shall adjust the cost estimate for inflation within 60 days prior to the anniversary date of the establishment of the financial instrument or instrument used to comply with s. NR 661.0143. For owners and operators using the financial test or corporate guarantee, the cost estimate shall be updated for inflation within 30 days after the close of the firm's fiscal year and before submission of updated information to the department as specified in s. NR 661.0143(5) (c). The adjustment may be made by recalculating the cost estimate in current dollars, or by using an inflation factor derived from the most recent Implicit Price Deflator for Gross National Product published by the U.S. department of commerce in its Survey of Current Business, as specified in pars. (a) and (b). The inflation factor is the result of dividing the latest published annual deflator by the deflator for the previous year. Adjustments shall be made as follows:
(3) During the active life of the facility, the owner or operator shall revise the cost estimate no later than 30 days after a change in a facility's operating plan or design that would increase the costs of conducting the activities described in sub. (1) or no later than 60 days after an unexpected event that increases the cost of conducting the activities described in sub. (1). The revised cost estimate shall be adjusted for inflation as specified in sub. (2).
(4) The owner or operator shall keep the following at the facility during the operating life of the facility: The latest cost estimate prepared in accordance with subs. (1) and (3) and, when this estimate has been adjusted in accordance with sub. (2), the latest adjusted cost estimate.