(1) WHAT NOTIFICATIONS MUST I SUBMIT?
(a)
General. You shall submit the notifications in ss.
NR 460.06(2), 460.07(6)
(c) and to 460.08(2) (5) and (8) that apply
to you by the dates specified in those sections, except as provided in pars.
(b) and (c).
(b)
Initial
notification. You shall submit the initial notification required by s.
NR 460.08(2) for a new or reconstructed
affected source no later than 120 days after initial startup. For an existing
affected source, you shall submit the initial notification no later than one
year after January 2, 2004. If you are using compliance with the surface
coating of automobiles and light-duty trucks NESHAP in 40 CFR part 63, Subpart
IIII, as provided for under s.
NR 465.41(2)
(d) to constitute compliance with this
subchapter for any or all of your metal parts coating operations, then you
shall include a statement to this effect in your initial notification, and no
other notifications are required under this subchapter in regard to those metal
parts coating operations. If you are complying with another NESHAP that
constitutes the predominant activity at your facility under s.
NR 465.41(2) (e)
2. to constitute compliance with this
subchapter for your metal parts coating operations, then you shall include a
statement to this effect in your initial notification, and no other
notifications are required under this subchapter in regard to those metal parts
coating operations.
(c)
Notification of compliance status. You shall submit the
notification of compliance status required by s.
NR 460.08(8) no later than 30 calendar
days following the end of the initial compliance period described in s.
NR 465.46(1), 465.47(1) or 465.48(1) that
applies to your affected source. The notification of compliance status shall
contain the information specified in subds. 1. to 11. and in s.
NR 460.08(8).
1. Company name and address.
2. Statement by a responsible official with
that official's name, title and signature, certifying the truth, accuracy and
completeness of the content of the report.
3. Date of the report and beginning and
ending dates of the reporting period. The reporting period is the initial
compliance period described in s.
NR 465.46(1), 465.47(1) or 465.48(1) that
applies to your affected source.
4.
Identification of the compliance option or options specified in s.
NR 465.43(2) that you used on each
coating operation in the affected source during the initial compliance
period.
5. Statement of whether or
not the affected source achieved the emission limits in s.
NR 465.43(1) for the initial compliance
period.
6. If you had a deviation,
include the information in subd. 6. a. and b.
a. A description and statement of the cause
of the deviation.
b. If you failed
to meet the applicable emission limit in s.
NR 465.43(1), include all the
calculations you used to determine the kg (lb) of organic HAP emitted per liter
(gallon) of coating solids used. You do not need to submit information provided
by the materials' suppliers or manufacturers, or test reports.
7. For each of the data items
listed in subd. 7. a. to d. that is required by the compliance option you used
to demonstrate compliance with the emission limit in s.
NR 465.43(1), include an example of how
you determined the value, including calculations and supporting data.
Supporting data may include a copy of the information provided by the supplier
or manufacturer of the example coating or material, or a summary of the results
of testing conducted according to s.
NR 465.46(2) (a), (b) or (c). You do not
need to submit copies of any test reports.
a.
Mass fraction of organic HAP for one coating, for one thinner or other
additive, and for one cleaning material.
b. Volume fraction of coating solids for one
coating.
c. Density for one
coating, one thinner or other additive, and one cleaning material, except that
if you use the compliant material option in s.
NR 465.43(2) (a), only the example
coating density is required.
d. The
amount of waste materials and the mass of organic HAP contained in the waste
materials for which you are claiming an allowance in Equation 1 of s.
NR 465.47(2).
8. The calculation of kg (lb) of organic HAP
emitted per liter (gallon) of coating solids used for the compliance options
you used, as specified in subd. 8. a. to c.
a. For the compliant material option in s.
NR 465.43(2) (a), provide an example
calculation of the organic HAP content for one coating, using Equation 2 of s.
NR 465.46(2).
b. For the emission rate without add-on
controls option specified in s.
NR 465.43(2) (b), provide the
calculation of the total mass of organic HAP emissions for each month; the
calculation of the total volume of coating solids used each month; and the
calculation of the 12-month organic HAP emission rate using Equations 1 and 1A
to 1C, 2 and 3, respectively, of s.
NR 465.47(2).
c. For the emission rate with add-on controls
option specified in s.
NR 465.43(2) (c), provide the
calculation of the total mass of organic HAP emissions for the coatings,
thinners and other additives, and cleaning materials used each month, using
Equations 1 and 1A to 1C of s.
NR 465.47(2); the calculation of the
total volume of coating solids used each month using Equation 2 of s.
NR 465.47(2); the mass of organic HAP
emission reduction each month by emission capture systems and add-on control
devices using Equations 1 and 1A to 1D of s.
NR 465.48(2) and Equations 2, 3 and 3A
to 3C of s.
NR 465.48(2) as applicable; the
calculation of the total mass of organic HAP emissions each month using
Equation 4 of s.
NR 465.48(2); and the calculation of the
12-month organic HAP emission rate using Equation 5 of s.
NR 465.48(2).
9. For the emission rate with add-on controls
option specified in s.
NR 465.43(2) (c), you shall include the
information specified in subd. 9. a. to d., except that the requirements in
subd. 9. a. to c. do not apply to solvent recovery systems for which you
conduct liquid-liquid material balances according to s.
NR 465.48(2) (j).
a. For each emission capture system, a
summary of the data and copies of the calculations supporting the determination
that the emission capture system is a permanent total enclosure (PTE) or a
measurement of the emission capture system efficiency. Include a description of
the protocol followed for measuring capture efficiency, summaries of any
capture efficiency tests conducted and any calculations supporting the capture
efficiency determination. If you use the data quality objective (DQO) or lower
confidence limit (LCL) approach, you shall also include the statistical
calculations to show you meet the DQO or LCL criteria in 40 CFR part 63,
Subpart KK, Appendix A, incorporated by reference in s.
NR 484.04(24). You do not need to submit
complete test reports.
b. A summary
of the results of each add-on control device performance test. You do not need
to submit complete test reports.
c.
A list of each emission capture system's and add-on control device's operating
limits and a summary of the data used to calculate those limits.
d. A statement of whether or not you
developed and implemented the work practice plan required by s.
NR 465.43(4).
10. If you are complying with a single
emission limit representing the predominant activity under s.
NR 465.43(1) (c) 1., include the
calculations and supporting information used to demonstrate that this emission
limit represents the predominant activity as specified in s.
NR 465.43(1) (c) 1.
11. If you are complying with a
facility-specific emission limit under s.
NR 465.43(1) (c) 2., include the
calculation of the facility-specific emission limit and any supporting
information as specified in s.
NR 465.43(1) (c) 2.
(2) WHAT REPORTS MUST I SUBMIT?
(a)
Semiannual compliance
reports. You shall submit semiannual compliance reports for each
affected source according to the requirements of subds. 1. to 7. The semiannual
compliance reporting requirements may be satisfied by reports required under
other parts of the Clean Air Act, as specified in subd. 2.
1. `Dates'. Unless the department has
approved or agreed to a different schedule for submission of reports under s.
NR 460.09(1), you shall prepare and
submit each semiannual compliance report according to the dates specified in
subd. 1. a. to d. The information reported for each of the months in the
reporting period shall be based on the last 12 months of data prior to the date
of each monthly calculation.
a. The first
semiannual compliance report shall cover the first semiannual reporting period,
which begins the day after the end of the initial compliance period described
in s.
NR 465.46(1), 465.47(1) or 465.48(1) that
applies to your affected source and ends on June 30 or December 31, whichever
date is the first date following the end of the initial compliance
period.
b. Each subsequent
semiannual compliance report shall cover the subsequent semiannual reporting
period from January 1 to June 30 or the semiannual reporting period from July 1
to December 31.
c. Each semiannual
compliance report shall be postmarked or delivered no later than July 31 or
January 31, whichever date is the first date following the end of the
semiannual reporting period.
d. For
each affected source that is subject to permitting regulations pursuant to ch.
NR 407, and if the department has established dates for submitting semiannual
reports pursuant to s.
NR 407.09(1) (c) 3. a., you may submit
the first and subsequent compliance reports according to those dates instead of
according to the date specified in subd. 1. c.
2. `Inclusion with title V report'. Each
affected source that has obtained a title V operating permit pursuant to ch. NR
407 shall report all deviations in the semiannual monitoring report required by
s.
NR 407.09(1) (c) 3. a. If an affected
source submits a semiannual compliance report pursuant to this subsection along
with, or as part of, the semiannual monitoring report required by s.
NR 407.09(1) (c) 3. a., and the
semiannual compliance report includes all required information concerning
deviations from any emission limit in s.
NR 465.43(1), its submission will be
deemed to satisfy any obligation to report the same deviations in the
semiannual monitoring report. However, submission of a semiannual compliance
report may not otherwise affect any obligation the affected source may have to
report deviations from permit requirements to the department.
3. `General requirements'. The semiannual
compliance report shall contain the information specified in subd. 3. a. to g.,
and the information specified in subds. 4. to 7. and par. (c) 1. that is
applicable to your affected source.
a.
Company name and address.
b.
Statement by a responsible official with that official's name, title and
signature, certifying the truth, accuracy and completeness of the content of
the report.
c. Date of report and
beginning and ending dates of the reporting period. The reporting period is the
6-month period ending on June 30 or December 31. The information reported for
each of the 6 months in the reporting period will be based on the last 12
months of data prior to the date of each monthly calculation.
d. Identification of the compliance option or
options specified in s.
NR 465.43(2) that you used on each
coating operation during the reporting period. If you switched between
compliance options during the reporting period, you shall report the beginning
and ending dates for each option you used.
e. If you used the emission rate without
add-on controls option or the emission rate with add-on controls option in s.
NR 465.43(2) (b) or (c), the calculation
results for each rolling 12-month organic HAP emission rate during the 6-month
reporting period.
f. If you used
the predominant activity alternative in s.
NR 465.43(1) (c) 1., include the annual
determination of predominant activity if it was not included in the previous
semi-annual compliance report.
g.
If you used the facility-specific emission limit alternative in s.
NR 465.43(1) (c) 2., include the
calculation of the facility-specific emission limit for each 12-month
compliance period during the 6-month reporting period.
4. `No deviations'. If there were no
deviations from the emission limits in s.
NR 465.43(1), (3) and (4) that apply to
you, the semiannual compliance report shall include a statement that there were
no deviations from the emission limits during the reporting period. If you used
the emission rate with add-on controls option specified in s.
NR 465.43(2) (c) and there were no
periods during which the continuous parameter monitoring systems (CPMS) were
out-of-control as specified in s.
NR 460.07(3)
(g), the semiannual compliance report shall
include a statement that there were no periods during which the CPMS were
out-of-control during the reporting period.
5. `Deviations: compliant material option'.
If you used the compliant material option in s.
NR 465.43(2) (a) and there was a
deviation from the applicable organic HAP content requirements in s.
NR 465.43(1), the semiannual compliance
report shall contain the information in subd. 5. a. to d.
a. Identification of each coating used that
deviated from the applicable emission limit in s.
NR 465.43(1), and each thinner, other
additive and cleaning material used that contained organic HAP, and the dates
and time periods each was used.
b.
The calculation of the organic HAP content, using Equation 2 of s.
NR 465.46(2), for each coating
identified in subd. 5. a. You do not need to submit background data supporting
this calculation, such as information provided by coating suppliers or
manufacturers, or test reports.
c.
The determination of mass fraction of organic HAP for each thinner, other
additive and cleaning material identified in subd. 5. a. You do not need to
submit background data supporting this calculation, such as information
provided by material suppliers or manufacturers, or test reports.
d. A statement of the cause of each
deviation.
6.
`Deviations: emission rate without add-on controls option'. If you used the
emission rate without add-on controls option in s.
NR 465.43(2) (b) and there was a
deviation from the applicable emission limit in s.
NR 465.43(1), the semiannual compliance
report shall contain the information in subd. 6. a. to c.
a. The beginning and ending dates of each
compliance period during which the 12-month organic HAP emission rate exceeded
the applicable emission limit in s.
NR 465.43(1).
b. The calculations used to determine the
12-month organic HAP emission rate for the compliance period in which the
deviation occurred. You shall submit the calculations for Equations 1, 1A to
1C, 2, and 3 of s.
NR 465.47(2); and if applicable, the
calculation used to determine mass of organic HAP in waste materials according
to s.
NR 465.47(2) (e) 2. You do not need to
submit background data supporting these calculations, such as information
provided by materials suppliers or manufacturers, or test reports.
c. A statement of the cause of each
deviation.
7.
`Deviations: emission rate with add-on controls option'. If you used the
emission rate with add-on controls option in s.
NR 465.43(2) (c) and there was a
deviation from an emission limit in s.
NR 465.43(1), including any periods when
emissions bypassed the add-on control device and were diverted to the
atmosphere, the semiannual compliance report shall contain the information in
subd. 7. a. to n. This includes periods of startup, shutdown and malfunction
during which deviations occurred.
a. The
beginning and ending dates of each compliance period during which the 12-month
organic HAP emission rate exceeded the applicable emission limit in s.
NR 465.43(1).
b. The calculations used to determine the
12-month organic HAP emission rate for each compliance period in which a
deviation occurred. You shall provide the calculation of the total mass of
organic HAP emissions for the coatings, thinners, other additives and cleaning
materials used each month using Equations 1 and 1A to 1C of s.
NR 465.47(2); and, if applicable, the
calculation used to determine mass of organic HAP in waste materials according
to s.
NR 465.47(2) (e) 2. the calculation of
the total volume of coating solids used each month using Equation 2 of s.
NR 465.47(2); the calculation of the
mass of organic HAP emission reduction each month by emission capture systems
and add-on control devices using Equations 1 and 1A to 1D of s.
NR 465.48(2), and Equations 2, 3 and 3A
to 3C of s.
NR 465.48(2), as applicable; the
calculation of the total mass of organic HAP emissions each month using
Equation 4 of s.
NR 465.48(2); and the calculation of the
12-month organic HAP emission rate using Equation 5 of s.
NR 465.48(2). You do not need to submit
the background data supporting these calculations, such as information provided
by materials suppliers or manufacturers, or test reports.
c. The date and time that each malfunction
started and stopped.
d. A brief
description of the CPMS.
e. The
date of the latest CPMS certification or audit.
f. The date and time that each CPMS was
inoperative, except for zero (low-level) and high-level checks.
g. The date, time and duration that each CPMS
was out-of-control, including the information in s.
NR 460.07(3)
(h).
h. The date and time period of each deviation
from an operating limit in Table 1 of this subchapter; date and time period of
any bypass of the add-on control device; and whether each deviation occurred
during a period of startup, shutdown or malfunction or during another
period.
i. A summary of the total
duration of each deviation from an operating limit in Table 1 of this
subchapter and each bypass of the add-on control device during the semiannual
reporting period, and the total duration as a percent of the total source
operating time during that semiannual reporting period.
j. A breakdown of the total duration of the
deviations from the operating limits in Table 1 of this subchapter and bypasses
of the add-on control device during the semiannual reporting period into those
that were due to startup, shutdown, control equipment problems, process
problems, other known causes and other unknown causes.
k. A summary of the total duration of CPMS
downtime during the semiannual reporting period and the total duration of CPMS
downtime as a percent of the total source operating time during that semiannual
reporting period.
L. A description
of any changes in the CPMS, coating operation, emission capture system or
add-on control device since the last semiannual reporting period.
m. For each deviation from the work practice
standards, a description of the deviation, the date and time period of the
deviation and the actions you took to correct the deviation.
n. A statement of the cause of each
deviation.
(b)
Performance test reports. If you use the emission rate with
add-on controls option in s.
NR 465.43(2) (c), you shall submit
reports of performance test results for emission capture systems and add-on
control devices no later than 60 days after completing the tests as specified
in s.
NR 460.09(4) (b).
(c)
Startup, shutdown, malfunction
reports. If you used the emission rate with add-on controls option in
s.
NR 465.43(2) (c) and you had a startup,
shutdown or malfunction during the semiannual reporting period, you shall
submit the reports specified in subds. 1. and 2.
1. If your actions were consistent with your
startup, shutdown and malfunction plan, you shall include the information
specified in s.
NR 460.09(4) in the semiannual
compliance report required by par. (a).
2. If your actions were not consistent with
your startup, shutdown and malfunction plan, you shall submit an immediate
startup, shutdown and malfunction report as described in subd. 2. a. and b.
a. You shall describe the actions taken
during the event in a report delivered by facsimile, telephone or other means
to the department within 2 working days after starting actions that are
inconsistent with the plan.
b. You
shall submit a letter to the department within 7 working days after the end of
the event, unless you have made alternative arrangements with the department as
specified in s.
NR 460.09(4) (e) 2. The letter shall
contain the information specified in s.
NR 460.09(4) (e) 2.
(3) WHAT RECORDS MUST I KEEP? You shall collect and keep records of the data and information specified in pars. (a) to (k). Failure to collect and keep the following records is a deviation from the applicable standard:
(a) A copy of each notification and report
that you submitted to comply with this subchapter, and the documentation
supporting each notification and report. If you are using the predominant
activity alternative under s.
NR 465.43(1) (c) 1., you shall keep
records of the data and calculations used to determine the predominant
activity. If you are using the facility-specific emission limit alternative
under s.
NR 465.43(1) (c) 2., you shall keep
records of the data used to calculate the facility-specific emission limit for
the initial compliance demonstration. You shall also keep records of any data
used in each annual predominant activity determination and in the calculation
of the facility-specific emission limit for each 12-month compliance period
included in the semi-annual compliance reports.
(b) A current copy of information provided by
materials suppliers or manufacturers, such as manufacturer's formulation data,
or test data used to determine the mass fraction of organic HAP and density for
each coating, thinner, other additive and cleaning material, and the volume
fraction of coating solids for each coating. If you conducted testing to
determine mass fraction of organic HAP, density or volume fraction of coating
solids, you shall keep a copy of the complete test report. If you used
information provided to you by the manufacturer or supplier of the material
that was based on testing, you shall keep the summary sheet of results provided
to you by the manufacturer or supplier. You are not required to obtain the test
report or other supporting documentation from the manufacturer or
supplier.
(c) For each compliance
period, the records specified in subds. 1. to 4.:
1. A record of the coating operations on
which you used each compliance option and the time periods, beginning and
ending dates and times, for each option you used.
2. For the compliant material option in s.
NR 465.43(2) (a), a record of the
calculation of the organic HAP content for each coating, using Equation 2 of s.
NR 465.46(2).
3. For the emission rate without add-on
controls option in s.
NR 465.43(2) (b), a record of the
calculation of the total mass of organic HAP emissions for the coatings,
thinners, other additives and cleaning materials used each month using
Equations 1, 1A to 1C and 2 of s.
NR 465.47(2); and, if applicable, the
calculation used to determine mass of organic HAP in waste materials according
to s.
NR 465.47(2) (e) 2.; the calculation of
the total volume of coating solids used each month using Equation 2 of s.
NR 465.47(2); and the calculation of
each 12-month organic HAP emission rate using Equation 3 of s.
NR 465.47(2).
4. For the emission rate with add-on controls
option in s.
NR 465.43(2) (c), records of all the
calculations specified in subd. 4. a. to e.
a. The calculation of the total mass of
organic HAP emissions for the coatings, thinners, other additives and cleaning
materials used each month using Equations 1 and 1A to 1C of s.
NR 465.47(2) and, if applicable, the
calculation used to determine mass of organic HAP in waste materials according
to s.
NR 465.47(2) (e) 2.
b. The calculation of the total volume of
coating solids used each month using Equation 2 of s.
NR 465.47(2).
c. The calculation of the mass of organic HAP
emission reduction by emission capture systems and add-on control devices using
Equations 1 and 1A to 1D of s.
NR 465.48(2) and Equations 2, 3 and 3A
to 3C of s.
NR 465.48(2), as applicable.
d. The calculation of each month's organic
HAP emission rate using Equation 4 of s.
NR 465.48(2).
e. The calculation of each 12-month organic
HAP emission rate using Equation 5 of s.
NR 465.48(2).
(d) A record of the name and
volume of each coating, thinner, other additive and cleaning material used
during each compliance period. If you are using the compliant material option
in s.
NR 465.43(2) (a) for all coatings at the
source, you may maintain purchase records for each material used rather than a
record of the volume used.
(e) A
record of the mass fraction of organic HAP for each coating, thinner and other
additive, and cleaning material used during each compliance period unless the
material is tracked by weight.
(f)
A record of the volume fraction of coating solids for each coating used during
each compliance period.
(g) If you
use either the emission rate without add-on controls option in s.
NR 465.43(2) (b) or the emission rate
with add-on controls compliance option in s.
NR 465.43(2) (c), the density for each
coating, thinner, other additive and cleaning material used during each
compliance period.
(h) If you use
an allowance in Equation 1 of s.
NR 465.47(2) for organic HAP contained
in waste materials sent to or designated for shipment to a treatment, storage,
and disposal facility (TSDF) according to s.
NR 465.47(2) (e) 2., you shall keep
records of the information specified in subds. 1. to 3.
1. The name and address of each TSDF to which
you sent waste materials for which you use an allowance in Equation 1 of s.
NR 465.47(2); a statement of which
subparts under 40 CFR parts 262, 264, 265 and 266 apply to the facility; and
the date of each shipment.
2.
Identification of the coating operations producing waste materials included in
each shipment and the month or months in which you used the allowance for these
materials in Equation 1 of s.
NR 465.47(2).
3. The methodology used in accordance with s.
NR 465.47(2) (e) 2. to determine the
total amount of waste materials sent to or the amount collected, stored and
designated for transport to a TSDF each month; and the methodology to determine
the mass of organic HAP contained in these waste materials. You shall include
the sources for all data used in the determination, methods used to generate
the data, frequency of testing or monitoring and supporting calculations and
documentation, including the waste manifest for each shipment.
(j) You shall keep records of the
date, time and duration of each deviation.
(k) If you use the emission rate with add-on
controls option in s.
NR 465.43(2) (c), you shall keep the
records specified in subds. 1. to 8.
1. For
each deviation, a record of whether the deviation occurred during a period of
startup, shutdown or malfunction.
2. The records in s.
NR 460.05(4) (c)3. to 5. related to
startup, shutdown and malfunction.
3. The records required to show continuous
compliance with each operating limit specified in Table 1 of this subchapter
that applies to you.
4. For each
capture system that is a PTE, the data and documentation you used to support a
determination that the capture system meets the criteria in Method 204 in 40
CFR part 51, Appendix M, incorporated by reference in s.
NR 484.04(9), for a PTE and has a
capture efficiency of 100%, as specified in s.
NR 465.48(6) (a).
5. For each capture system that is not a PTE,
the data and documentation you used to determine capture efficiency according
to the requirements specified in s.
NR 465.48(5) and (6) (b) to (e),
including the records specified in subd. 5. a. to c. that apply to you.
a. For a liquid-to-uncaptured gas protocol
using a temporary total enclosure or building enclosure, records of the mass of
total volatile hydrocarbon (TVH) as measured by Method 204A or 204F in 40 CFR
part 51, Appendix M, incorporated by reference in s.
NR 484.04(9), for each material used in
the coating operation or operations, and the total TVH for all materials used
during each capture efficiency test run, including a copy of the test report.
Records of the mass of TVH emissions not captured by the capture system that
exited the temporary total enclosure or building enclosure during each capture
efficiency test run, as measured by Method 204D or 204E in 40 CFR part 51,
Appendix M, incorporated by reference in s.
NR 484.04(9), including a copy of the
test report. Records documenting that the enclosure used for the capture
efficiency test met the criteria in Method 204 in 40 CFR part 51, Appendix M,
incorporated by reference in s.
NR 484.04(9), for either a temporary
total enclosure or a building enclosure.
b. For a gas-to-gas protocol using a
temporary total enclosure or a building enclosure, records of the mass of TVH
emissions captured by the emission capture system as measured by Method 204B or
204C in 40 CFR part 51, Appendix M, incorporated by reference in s.
NR 484.04(9), at the inlet to the add-on
control device, including a copy of the test report. Records of the mass of TVH
emissions not captured by the capture system that exited the temporary total
enclosure or building enclosure during each capture efficiency test run as
measured by Method 204D or 204E in 40 CFR part 51, Appendix M, including a copy
of the test report. Records documenting that the enclosure used for the capture
efficiency test met the criteria in Method 204 in 40 CFR part 51, Appendix M
for either a temporary total enclosure or a building enclosure.
c. For an alternative protocol, records
needed to document a capture efficiency determination using an alternative
method or protocol as specified in s.
NR 465.48(6) (e), if
applicable.
6. The
records specified in subd. 6. a. and b. for each add-on control device organic
HAP destruction or removal efficiency determination as specified in s.
NR 465.48(7).
a. Records of each add-on control device
performance test conducted according to s.
NR 465.48(5) and (7).
b. Records of the coating operation
conditions during the add-on control device performance test showing that the
performance test was conducted under representative operating
conditions.
7. Records
of the data and calculations you used to establish the emission capture and
add-on control device operating limits as specified in s.
NR 465.48(8) and to document compliance
with the operating limits as specified in Table 1 of this subchapter.
8. A record of the work practice plan
required by s.
NR 465.43(4) and documentation that you
are implementing the plan on a continuous basis.
(4) IN WHAT FORM AND FOR HOW LONG MUST I KEEP MY RECORDS?
(a) Your records
shall be in a form suitable and readily available for expeditious review,
according to s.
NR 460.09(2) (a). Where appropriate, the
records may be maintained as electronic spreadsheets or as a
database.
(b) As specified in s.
NR 460.09(2) (a), you shall keep each
record for 5 years following the date of each occurrence, measurement,
maintenance, corrective action, report or record.
(c) You shall keep each record on-site for at
least 2 years after the date of each occurrence, measurement, maintenance,
corrective action, report or record according to s.
NR 460.09(2) (a). You may keep the
records off-site for the remaining 3 years.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.