(1) INITIAL NOTIFICATIONS. The owner or
operator shall submit initial notifications to the department as described in
pars. (a) to (g).
(a) As required by s.
NR 460.08(2)
(a), the owner or operator shall provide
notification for an area source that subsequently increases its emissions such
that the source is a major source subject to the standard.
(b) The owner or operator of a new or
reconstructed affected source, or a source that has been reconstructed such
that it is an affected source, that has an initial startup after September 24,
2002 and for which an application for approval of construction or
reconstruction is not required under ch. NR 406, shall provide notification
that the source is subject to the standard.
(c) As required by s.
NR 460.08(2)
(d), the owner or operator of a new or
reconstructed major affected source that has an initial startup after September
24, 2002 and for which an application for approval of construction or
reconstruction is required by ch. NR 406 shall provide all the following
notifications:
1. Intention to construct a new
major affected source, reconstruct a major source or reconstruct a major source
such that the source becomes a major affected source.
2. Date when construction or reconstruction
was commenced, submitted simultaneously with the application for approval of
construction or reconstruction if construction or reconstruction was commenced
before September 24, 2002, or no later than 30 days after the date construction
or reconstruction commenced if construction or reconstruction commenced after
September 24, 2002.
3. Anticipated
date of startup.
4. Actual date of
startup.
(d) As required
by s.
NR 460.08(2)
(d), after September 24, 2002, an owner or
operator who intends to construct a new affected source or reconstruct an
affected source subject to this subchapter, or reconstruct a source such that
it becomes an affected source subject to this subchapter, shall provide
notification of the intended construction or reconstruction. The notification
shall include all the information required for an application for approval of
construction or reconstruction as required by ch. NR 406. For major sources,
the application for approval of construction or reconstruction may be used to
fulfill these requirements. The application shall be submitted according to one
of the following, as applicable:
1. The
application shall be submitted as soon as practicable before the construction
or reconstruction is planned to commence, but no sooner than September 24,
2002, if the construction or reconstruction commences after September 24,
2002.
2. The application shall be
submitted as soon as practicable before startup but no later than 90 days after
September 24, 2002 if the construction or reconstruction had commenced and
initial startup had not occurred before September 24, 2002.
(e) As required by s.
NR 460.08(4), the owner or operator
shall provide notification of any special compliance obligations for a new
source.
(f) As required by s.
NR 460.08(5) and
(6), the owner or operator shall provide
notification of the anticipated date for conducting performance tests and
visible emission observations. The owner or operator shall notify the
department of the intent to conduct a performance test at least 60 days before
the performance test is scheduled; notification of opacity or visible emission
observations for a performance test shall be provided at least 30 days before
the observations are scheduled to take place.
(g) As required by s.
NR 460.08(7), the owner or operator
shall provide additional notifications for sources with continuous emission
monitoring systems or continuous opacity monitoring systems.
(2) NOTIFICATION OF COMPLIANCE
STATUS REPORT. Each owner or operator of an existing affected source shall
submit a notification of compliance status report within 60 days after the
compliance date established by s.
NR 463.115(1). Each owner or operator of
a new affected source shall submit a notification of compliance status report
within 90 days after conducting the initial performance test required by s.
NR 463.16(2), or within 90 days after
the compliance date established by s.
NR 463.115(2) if no initial performance
test is required. The notification shall be signed by the responsible official
who shall certify its accuracy. A notification of compliance status report
shall include the information specified in pars. (a) to (j). The required
information may be submitted in an operation permit application, in an
amendment to an operation permit application, in a separate submittal, or in
any combination. If an owner or operator submits the information specified in
this section at different times or in different submittals, later submittals
may refer to earlier submittals instead of duplicating and resubmitting the
information previously submitted. A notification of compliance status report
shall include:
(a) All information required
in s.
NR 460.08(8). The owner or operator
shall provide a complete performance test report for each affected source and
emission unit for which a performance test is required. A complete performance
test report includes all data, associated measurements, and calculations,
including visible emission and opacity tests.
(b) The approved site-specific test plan and
performance evaluation test results for each continuous monitoring system,
including a continuous emission or opacity monitoring system.
(c) Unit labeling as described in s.
NR 463.14(2), including process type or
furnace classification and operating requirements.
(d) The compliant operating parameter value
or range established for each affected source or emission unit with supporting
documentation and a description of the procedure used to establish the value,
such as lime injection rate, total reactive chlorine flux injection rate,
afterburner operating temperature, fabric filter inlet temperature, including
the operating cycle or time period used in the performance test.
(e) Design information and analysis, with
supporting documentation, demonstrating conformance with the requirements for
capture and collection systems in s.
NR 463.14(3).
(f) If applicable, analysis and supporting
documentation demonstrating conformance with EPA guidance and specifications
for bag leak detection systems in s.
NR 463.15(6).
(g) Manufacturer's specification or analysis
documenting the design residence time of no less than one second for each
afterburner used to control emissions from a scrap dryer, delacquering kiln or
decoating kiln subject to alternative emission standards in s.
NR 463.13(5).
(h) Manufacturer's specification or analysis
documenting the design residence time of no less than 0.8 seconds and design
operating temperature of no less than 1,600°F for each afterburner used to
control emissions from a sweat furnace that is not subject to a performance
test.
(i) The operation,
maintenance and monitoring (OM&M) plan, including site-specific monitoring
plan for each group 1 furnace with no add-on air pollution control
device.
(j) Startup, shutdown and
malfunction plan, with revisions.