(1) NEW OR RECONSTRUCTED AFFECTED SOURCES. The owner or operator of a new or reconstructed affected source which is exempt from the permit requirements of chs. NR 406 and 407 is subject to this section.
(a) No person may construct a new affected
source or reconstruct an affected source subject to this subchapter, or
reconstruct a source such that it becomes an affected source subject to this
subchapter, without either meeting the permit application and approval
requirements under ch. NR 406 or 407, if applicable, or submitting a
notification of construction or reconstruction to the department under this
section. Notification under this section shall contain the information
identified in pars. (b) and (c), as appropriate.
(b) The notification of construction or
reconstruction required under this subsection shall include all of the
following:
1. The owner or operator's name,
title and address.
2. The address
or proposed address where the affected source would be located, if different
from the owner's or operator's.
3.
A notification of intention to construct a new affected source or make any
physical or operational changes to an affected source that may meet or has been
determined to meet the criteria for a reconstruction as defined in s.
NR 460.02(32).
4. An identification of this subchapter as
the basis for the notification.
5.
The expected commencement and completion dates of the construction or
reconstruction.
6. The anticipated
date of initial startup of the affected source.
7. The type of process operation to be
performed, hard or decorative chromium electroplating or chromium
anodizing.
8. A description of the
air pollution control technique to be used to control emissions from the
affected source, such as preliminary design drawings and design capacity if an
add-on air pollution control device is used.
9. An estimate of emissions from the source
based on engineering calculations and vendor information on control device
efficiency, expressed in units consistent with the emission limits of this
subchapter. Calculations of emission estimates shall be in sufficient detail to
permit assessment of the validity of the calculations.
(c) If a reconstruction is to occur, the
notification required under this subsection shall include the following in
addition to the information required in par. (b):
1. A brief description of the affected source
and the components to be replaced.
2. A brief description of the present and
proposed emission control technique, including the information required by par.
(b) 8. and 9.
3. An estimate of the
fixed capital cost of the replacements and of constructing a comparable
entirely new source.
4. The
estimated life of the affected source after the replacements.
5. A discussion of any economic or technical
limitations the source may have in complying with relevant standards or other
requirements after the proposed replacements. The discussion shall be
sufficiently detailed to demonstrate to the department's satisfaction that the
technical or economic limitations affect the source's ability to comply with
the relevant standard and how they do so.
6. If in the notification of reconstruction,
the owner or operator designates the affected source as a reconstructed source
and declares that there are no economic or technical limitations to prevent the
source from complying with all relevant standards or requirements, the owner or
operator need not submit the information required in subds. 3. to 5.
(d) The owner or operator of a new
or reconstructed affected source that submits a notification under this
subsection is not subject to approval by the department under this subchapter.
Construction or reconstruction is subject only to notification and may begin
upon submission of a complete notification. This paragraph applies only to
affected sources which are exempt from permit requirements under chs.
NR
406 and
407.
(2) SUBMITTAL TIMEFRAMES. After October 1, 1997, an owner or operator of a new or reconstructed affected source shall submit the notification of construction or reconstruction required by sub. (1) according to the following schedule:
(a) If
construction or reconstruction commences after October 1, 1997, the
notification shall be submitted as soon as practicable before the construction
or reconstruction is planned to commence.
(b) If the construction or reconstruction had
commenced and initial startup had not occurred before October 1, 1997, the
notification shall be submitted as soon as practicable before startup but no
later than 60 days after October 1, 1997.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.