Section NR 447.07 - Demolition and renovation; notification requirements
Universal Citation: WI Admin Code ยง NR 447.07
Current through August 26, 2024
Each owner or operator of a demolition or renovation activity to which this chapter applies shall:
(1) Provide the department with written notice of intention to demolish or renovate. Delivery of the notice by U.S. postal service, commercial delivery service or hand delivery is acceptable.
(2) Update the notice, as necessary, including when the amount of asbestos affected changes by at least 20%.
(3) Postmark or deliver the notice as follows:
(a) At least 10 working
days before asbestos stripping or removal work or any other activity begins,
such as site preparation that would break up, dislodge or similarly disturb
asbestos material, if the operation is described in s.
NR 447.06(2) (a) or (d) 1. If the
operation is as described in s.
NR 447.06(2) (b), notification is
required 10 working days before demolition begins.
(b) At least 10 working days before the end
of the calendar year preceding the year for which notice is being given for
planned renovations referred to in s.
NR 447.06(2) (d) 2.
(c) As early as possible before, but not
later than, the following working day if the operation is a demolition ordered
according to s.
NR 447.06(2) (c) or if the operation is
an emergency renovation referred to in s.
NR 447.06(2) (d) 3.
(d) For asbestos stripping or removal work in
a demolition or renovation operation, described in s.
NR 447.06(2) (a) or (d) 1., and for
demolition described in s.
NR 447.06(2) (b) that will begin on a
date other than the one contained in the original notice, the owner or operator
shall provide notice of the new start date to the department as follows:
1. When the asbestos stripping or removal
operation or demolition operation covered by this paragraph will begin after
the date contained in the notice:
a. Notify
the department of the new start date by telephone as soon as possible before
the original start date, and
b.
Provide the department with a written notice of the new start date as soon as
possible before, but no later than, the original start date. Delivery of the
updated notice by the U.S. postal service, commercial delivery service or hand
delivery is acceptable.
2. When the asbestos stripping or removal
operation or demolition operation covered by this paragraph will begin on a
date earlier than the original start date:
a.
Provide the department with a written notice of the new start date at least 10
working days before asbestos stripping or removal work begins.
b. For demolitions covered by s.
NR 447.06(2) (b), provide the department
written notice of a new start date at least 10 working days before commencement
of demolition. Delivery of updated notice by U.S. postal service, commercial
delivery service or hand delivery is acceptable.
3. In no event may an operation covered by
this paragraph begin on a date other than the date contained in the written
notice of the new start date.
(4) Include the following in the notice:
(a) An indication of whether the notice is
the original or a revised notification.
(b) Name, address and telephone number of
both the facility owner and operator and the asbestos removal contractor owner
or operator.
(c) Type of operation:
demolition or renovation.
(d)
Description of the facility or affected part of the facility including the size
(square meters [square feet] and number of floors), age and present and prior
use of the facility.
(e) Procedure,
including analytical methods, employed to detect the presence of RACM and
Category I and Category II nonfriable ACM.
(f) Estimate of the approximate amount of
RACM to be removed from the facility in terms of length of pipe in linear
meters (linear feet), surface area in square meters (square feet) on other
facility components, or volume in cubic meters (cubic feet) if off the facility
components. Also, estimate the approximate amount of Category I and Category II
nonfriable ACM in the affected part of the facility that will not be removed
before demolition.
(g) Location and
street address, including building number or name and floor or room number, if
appropriate, city, county and state of the facility being demolished or
renovated.
(h) Scheduled starting
and completion dates of asbestos removal work, or any other activity, such as
site preparation that would break up, dislodge or similarly disturb asbestos
material, in a demolition or renovation; planned renovation operations
involving individual nonscheduled operations shall only include the beginning
and ending dates of the report period as described in s.
NR 447.06(2) (d) 2.
(i) Scheduled starting and completion dates
of demolition or renovation.
(j)
Description of planned demolition or renovation work to be performed and
methods to be employed, including demolition or renovation techniques to be
used and description of affected facility components.
(k) Description of work practices and
engineering controls to be used to comply with the requirements of this
chapter, including asbestos removal and waste-handling emission control
procedures.
(l) Name and location
of the waste disposal site where the asbestos-containing waste material will be
deposited.
(m) A certification that
at least one person trained as required by s.
NR 447.08(8) will supervise the
stripping and removal described by this notification. This requirement shall
become effective one year after November 1, 1992.
(n) For facilities described in s.
NR 447.06(2) (c), the name, title and
authority of the state or local government representative who has ordered the
demolition, the date that the order was issued, and the date on which the
demolition was ordered to begin. A copy of the order shall be attached to the
notification.
(o) For emergency
renovations referred to in s.
NR 447.06(2) (d) 3., the date and hour
that the emergency occurred, a description of the sudden, unexpected event, and
an explanation of how the event caused an unsafe condition, or would cause
equipment damage or an unreasonable financial burden.
(p) Description of procedures to be followed
in the event that unexpected RACM is found or Category II nonfriable ACM
becomes crumbled, pulverized or reduced to powder.
(q) Name, address and telephone number of the
waste transporter.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.