Current through August 26, 2024
(1)
APPLICABILITY AND DESIGNATION OF AFFECTED FACILITY.
(a) The provisions of this section apply to
each affected facility designated in par.
(b) that produces any of the chemicals listed
in sub. (8) as a product, co-product, by-product or intermediate, except as
provided in par. (c). (b) The affected facility is any of the following for
which construction, modification or reconstruction commenced after October 21,
1983:
1. Each air oxidation reactor not
discharging its vent stream into a recovery system.
2. Each combination of an air oxidation
reactor and the recovery system into which its vent stream is
discharged.
3. Each combination of
2 or more air oxidation reactors and the common recovery system into which
their vent streams are discharged.
(c) Each affected facility that has a total
resource effectiveness (TRE) index value greater than 4.0 is exempt from all
provisions of this section except for subs. (3), (5) (f), (6) (h) and (L).
Note: The intent of these standards is to minimize the
emissions of VOC through the application of best demonstrated technology (BDT).
The numerical emission limits in these standards are expressed in terms of
total organic compounds (TOC), measured as TOC minus methane and ethane. This
emission limit reflects the performance of BDT.
(d)
1.
Owners or operators of process vents that are subject to this section may
choose to comply with the provisions of 40 CFR part 65, subpart D, as in effect
on December 14, 2000, to satisfy the requirements of subs. (3) to (6). The
provisions of 40 CFR part 65, subpart D, as in effect on December 14, 2000,
also satisfy the criteria of par. (c). Other provisions applying to an owner or
operator who chooses to comply with 40 CFR part 65, subpart D, as in effect on
December 14, 2000, are provided in
40
CFR 65.1.
2. Owners or operators who choose to comply
with 40 CFR part 65, subpart D, as in effect on December 14, 2000, shall also
comply with ss.
NR 440.01, 440.02, 440.05, 440.06, 440.07(1) (a) and (d), 440.14 and 440.15 for those process vents. All
sections or subsections from ss.
NR 440.01
to 440.19 not specified in this
subdivision do not apply to owners or operators of process vents complying with
40 CFR part 65, subpart D, as in effect on December 14, 2000, except that
provisions required to be met prior to implementing 40 CFR part 65 still apply.
Owners or operators who choose to comply with 40 CFR part 65, subpart D, as in
effect on December 14, 2000, shall comply with 40 CFR part 65, subpart
A.
3. Owners or operators who
choose to comply with 40 CFR part 65, subpart D, as in effect on December 14,
2000, at initial startup shall comply with subds. 1. and 2. for each vent
stream on and after the date on which the initial performance test is
completed, but not later than 60 days after achieving the maximum production
rate at which the affected facility will be operated, or 180 days after the
initial startup, whichever date comes first.
4. Each owner or operator subject to the
provisions of this section that chooses to comply with 40 CFR part 65, subpart
D, as in effect on December 14, 2000, at initial startup shall notify the
administrator of the specific provisions of
40 CFR
65.63(a) (1), (2) or (3)
with which the owner or operator has elected to comply. Notification shall be
submitted with the notification of initial startup required by
40 CFR
65.5(b).
(2) DEFINITIONS. As
used in this section, all terms not defined here shall have the meanings given
them in s.
NR 440.02 and the following terms shall have the specific
meanings given them.
(a) "Air oxidation
reactor" means any device or process vessel in which one or more organic
reactants are combined with air or a combination of air and oxygen, to produce
one or more organic compounds. Ammoxidation and oxychlorination reactions are
included in this definition.
(b)
"Air oxidation reactor recovery train" means an individual recovery system
receiving the vent stream from at least one air oxidation reactor, along with
all air oxidation reactors feeding vent streams into this system.
(c) "Air oxidation unit process" means a unit
process, including ammoxidation and oxychlorination unit process, that uses air
or a combination of air and oxygen, as an oxygen source in combination with one
or more organic reactants to produce one or more organic compounds.
(d) "Boilers" means any enclosed combustion
device that extracts useful energy in the form of steam.
(e) "By compound" means by individual stream
components, not carbon equivalents.
(f) "Continuous recorder" means a data
recording device recording an instantaneous data value at least once every 15
minutes.
(g) "Flame zone" means the
portion of the combustion chamber in a boiler occupied by the flame
envelope.
(h) "Flow indicator"
means a device which indicates whether gas flow is present in a vent
stream.
(i) "Halogenated vent
stream" means any vent stream determined to have a total concentration, by
volume, of compounds containing halogens of 20 ppmv by compound or
greater.
(j) "Incinerator" means
any enclosed combustion device that is used for destroying organic compounds
and does not extract energy in the form of steam or process heat.
(k) "Process heater" means a device that
transfers heat liberated by burning fuel to fluids contained in tubes,
including all fluids except water that is heated to produce steam.
(L) "Process unit" means equipment assembled
and connected by pipes or ducts to produce, as intermediate or final products,
one or more of the chemicals in sub. (8). A process unit can operate
independently if supplied with sufficient fuel or raw materials and sufficient
product storage facilities.
(m)
"Product" means any compound or chemical listed in sub. (8) that is produced
for sale as a final product as that chemical or is produced for use in a
process that needs that chemical for the production of other chemicals in
another facility. By-products, co-products and intermediates are considered to
be products.
(n) "Recovery device"
means an individual unit of equipment, such as an absorber, condenser and
carbon adsorber, capable of and used to recover chemicals for use, reuse or
sale.
(o) "Recovery system" means
an individual recovery device or series of such devices applied to the same
process stream.
(p) "Total organic
compounds" or "TOC" means those compounds measured according to the procedures
in sub. (5) (b) 4. For the purposes of measuring molar composition as required
in sub. (5) (e) 3. a., hourly emissions rate as required in sub. (5) (e) 6. and
(f), and TOC concentration as required in sub. (6) (b) 4. and (g) 4., those
compounds which the department has determined do not contribute appreciably to
the formation of ozone are to be excluded. The compounds to be excluded are
identified in s.
NR 400.02(162).
(q) "Total resource effectiveness (TRE) index
value" means a measure of the supplemental total resource requirement per unit
reduction of TOC associated with an individual air oxidation vent stream, based
on vent stream flow rate, emission rate of TOC, net heating value and corrosion
properties, whether or not the vent stream is halogenated, as quantified by the
equation given under sub. (5) (e).
(r) "Vent stream" means any gas stream,
containing nitrogen which was introduced as air to the air oxidation reactor,
released to the atmosphere directly from any air oxidation reactor recovery
train or indirectly, after diversion through other process equipment. The vent
stream excludes equipment leaks and relief valve discharges including, but not
limited to, pumps, compressors and valves.
(3) STANDARDS. Each owner or operator of any
affected facility shall comply with par. (a), (b) or (c) for each vent stream
on and after the date on which the initial performance test required by s.
NR 440.08 and
sub. (5) is completed, but not later than 60 days after achieving the maximum
production rate at which the affected facility will be operated or 180 days
after the initial startup, whichever date comes first. Each owner or operator
shall either:
(a) Reduce emissions of TOC
(minus methane and ethane) by 98 weight- percent or to a TOC (minus methane and
ethane) concentration of 20 ppmv on a dry basis corrected to 3% oxygen,
whichever is less stringent. If a boiler or process heater is used to comply
with this paragraph, then the vent stream shall be introduced into the flame
zone of the boiler or process heater; or
(b) Combust the emissions in a flare that
meets the requirements of s.
NR 440.18; or
(c) Maintain a TRE index value greater than
1.0 without use of VOC emission control devices.
(4) MONITORING OF EMISSIONS AND OPERATIONS.
(a) The owner or operator of an affected
facility that uses an incinerator to seek to comply with the TOC emission limit
specified under sub. (3) (a) shall install, calibrate, maintain and operate
according to manufacturer's specifications the following equipment:
1. A temperature monitoring device equipped
with a continuous recorder and having an accuracy of ± 1% of the
temperature being monitored expressed in degrees Celsius or ± 0.5°C,
whichever is greater.
a. Where an incinerator
other than a catalytic incinerator is used, a temperature monitoring device
shall be installed in the firebox.
b. Where a catalytic incinerator is used,
temperature monitoring devices shall be installed in the gas stream immediately
before and after the catalyst bed.
2. A flow indicator that provides a record of
vent stream flow to the incinerator at least once every hour for each affected
facility. The flow indicator shall be installed in the vent stream from each
affected facility at a point closest to the inlet of each incinerator and
before being joined with any other vent stream.
(b) The owner or operator of an affected
facility that uses a flare to seek to comply with sub. (3) (b) shall install,
calibrate, maintain and operate according to manufacturer's specifications the
following equipment:
1. A heat sensing
device, such as an ultra-violet sensor or thermocouple, at the pilot light to
indicate the continuous presence of a flame.
2. A flow indicator that provides a record of
vent stream flow to the flare at least once every hour for each affected
facility. The flow indicator shall be installed in the vent stream from each
affected facility at a point closest to the flare and before being joined with
any other vent stream.
(c) The owner or operator of an affected
facility that uses a boiler or process heater to seek to comply with sub. (3)
(a) shall install, calibrate, maintain and operate according to the
manufacturer's specifications the following equipment:
1. A flow indicator that provides a record of
vent stream flow to the boiler or process heater at least once every hour for
each affected facility. The flow indicator shall be installed in the vent
stream from each air oxidation reactor within an affected facility at a point
closest to the inlet of each boiler or process heater and before being joined
with any other vent stream.
2. A
temperature monitoring device in the firebox equipped with a continuous
recorder and having an accuracy of " 1% of the temperature being measured
expressed in degrees Celsius or " 0.5°C, whichever is greater, for boilers
or process heaters of less than 44 MW (150 million Btu/hr) heat input design
capacity.
(d) The owner
or operator of an affected facility that uses a boiler or process heater to
comply with sub. (3) (a) shall monitor and record the periods of operation of
the boiler or process heater if the design input capacity of the boiler is 44
MW (150 million Btu/hr) or greater. The records shall be readily available for
inspection.
(e) The owner or
operator of an affected facility that seeks to demonstrate compliance with the
TRE index value limit specified under sub. (3) (c) shall install, calibrate,
maintain and operate according to manufacturer's specifications the following
equipment, unless alternative monitoring procedures or requirements are
approved for that facility by the department:
1. Where an absorber is the final recovery
device in a recovery system:
a. A scrubbing
liquid temperature monitoring device having an accuracy of " 1% of the
temperature being monitored expressed in degrees Celsius or " 0.5°C,
whichever is greater, and a specific gravity monitoring device having an
accuracy of " 0.02 specific gravity units, each equipped with a continuous
recorder;
b. An organic monitoring
device used to indicate the concentration level of organic compounds exiting
the recovery device based on a detection principle such as infra-red,
photoionization or thermal conductivity, each equipped with a continuous
recorder.
2. Where a
condenser is the final recovery device in a recovery system:
a. A condenser exit or product side
temperature monitoring device equipped with a continuous recorder and having an
accuracy of " 1% of the temperature being monitoring expressed in degrees
Celsius or "0.5°C, whichever is greater;
b. An organic monitoring device used to
indicate the concentration level of organic compounds exiting the recovery
device based on a detection principle such as infra-red, photoionization or
thermal conductivity, each equipped with a continuous recorder.
3. Where a carbon adsorber is the
final recovery device in a recovery system:
a. An integrating steam flow monitoring
device having an accuracy of " 10% and a carbon bed temperature monitoring
device having an accuracy of " 1% of the temperature being monitored expressed
in degrees Celsius or " 0.5°C, whichever is greater, both equipped with a
continuous recorder;
b. An organic
monitoring device used to indicate the concentration level of organic compounds
exiting the recovery device based on a detection principle such as infra-red,
photoionization or thermal conductivity, each equipped with a continuous
recorder.
(f)
An owner or operator of an affected facility seeking to demonstrate compliance
with the standards specified under sub. (3) with control devices other than an
incinerator, boiler, process heater or flare; or recovery devices other than an
absorber, condenser or carbon adsorber shall provide to the administrator
information describing the operation of the control device or recovery device
and the process parameters which would indicate proper operation and
maintenance of the device. The administrator may request further information
and will specify appropriate monitoring procedures or requirements.
(5) TEST METHODS AND PROCEDURES.
(a) For the purpose of demonstrating
compliance with sub. (3), all affected facilities shall be run at full
operating conditions and flow rates during any performance test.
(b) The following methods in Appendix A of 40
CFR part 60, incorporated by reference in s.
NR 440.17, except as provided under s.
NR 440.08(2)
(b), shall be used as reference methods to
determine compliance with the emission limit or percent reduction efficiency
specific under sub. (3) (a):
1. Method 1 or
1A, as appropriate, for selection of the sampling sites. The control device
inlet sampling site for determination of vent stream molar composition or TOC
(less methane and ethane) reduction efficiency shall be prior to the inlet of
the control device and after the recovery system.
2. Method 2, 2A, 2C or 2D, as appropriate,
for determination of the volumetric flow rates.
3. The emission rate correction factor,
integrated sampling and analysis procedure of Method 3 shall be used to
determine the oxygen concentration (%O2d) for the purposes of determining
compliance with the 20 ppmv limit. The sampling site shall be the same as that
of the TOC samples and the samples shall be taken during the same time that the
TOC samples are taken.
The TOC concentration corrected to 3% O2 (Cc) shall be
computed using the following equations:
Cc = CTOC
17.9/20.9 - %02d
where:
Cc is the concentration of TOC corrected to 3% O2, dry
basis, ppm by volume
CTOC is the concentration of TOC (minus methane and
ethane), dry basis, ppm by volume
%O2d is the concentration of O2, dry basis, percent by
volume
4. Method 18 to
determine concentration of TOC in the control device outlet and the
concentration of TOC in the inlet when the reduction efficiency of the control
device is to be determined.
a. The sampling
time for each run shall be 1 hour in which either an integrated sample or 4
grab samples shall be taken. If grab sampling is used then the samples shall be
taken at 15-minute intervals.
b.
The emission reduction (R) of TOC (minus methane and ethane) shall be
determined using the following equation:
R =
Ei-Eo/Eix100
where:
R is the emission reduction, percent by weight
Ei is the mass rate of TOC entering the control device,
kg/hr (lb/hr)
Eo is the mass rate of TOC discharged to the atmosphere,
kg/hr (lb/hr)
c. The mass
rates of TOC (Ei, Eo) shall be computed using the following equations:
See PDF
for diagram
where:
Cij and Coj are the concentration of sample component "j"
of the gas stream at the inlet and outlet of the control device, respectively,
dry basis, ppm by volume
Mij and Moj are the molecular weight of sample component
"j" of the gas stream at the inlet and outlet of the control device,
respectively, g/g-mole (lb/lb-mole)
Qi and Qo are the flow rate of gas stream at the inlet and
outlet of the control device, respectively, dscm/min (dscf/min)
K2 is a constant, 2.494 x 10-6
(1/ppm)(g-mole/scm)(kg/g)(min/hr) for metric units, where standard temperature
for (g-mole/scm) is 20°C, and 1.557 x 10-7 (1/ppm)(lb-mole/scf)(min/hr) for
English units, where standard temperature for (lb-mole/scf) is 68°F
d. The TOC concentration (CTOC) is
the sum of the individual components and shall be computed for each run using
the following equation:
where:
See PDF
for diagram
CTOC is the concentration of TOC (minus methane and
ethane), dry basis, ppm by volume
Cj is the concentration of sample components in the
sample
n is the number of components in the sample
(c) When a
boiler or process heater with a design heat input capacity of 44 MW (150
million Btu/hour) or greater is used to seek to comply with sub. (3) (a), the
requirement for an initial performance test is waived, in accordance with s.
NR 440.08(2). However, the department
reserves the option to require testing at such other times as may be
required.
(d) When a flare is used
to seek to comply with sub. (3) (b), the flare shall comply with the
requirements of s.
NR 440.18.
(e) The following test methods in Appendix A
of 40 CFR part 60, incorporated by reference in s.
NR 440.17, except as provided under s.
NR 440.08(2), shall be used for
determining the net heating value of the gas combusted to determine compliance
under sub. (3) (b) and for determining the process vent stream TRE index value
to determine compliance under sub. (3) (c).
1. Method 1 or 1A, as appropriate, for
selection of the sampling site. The sampling site for the vent stream flow rate
and molar composition determination prescribed in subds. 3. and 4. shall be,
except for the situations outlined in subd. 2., prior to the inlet of any
control device, prior to any post-reactor dilution of the stream with air and
prior to any post-reactor introduction of halogenated compounds into the vent
stream. No transverse site selection method is needed for vents smaller than 10
centimeters (4 inches) in diameter.
2. If any gas stream other than the air
oxidation vent stream from the affected facility is normally conducted through
the final recovery device:
a. The sampling
site for vent stream flow rate and molar composition shall be prior to the
final recovery device and prior to the point at which the nonair oxidation
stream is introduced.
b. The
efficiency of the final recovery device is determined by measuring the TOC
concentration using Method 18 at the inlet to the final recovery device after
the introduction of any nonair oxidation vent stream and at the outlet of the
final recovery device.
c. This
efficiency is applied to the TOC concentration measured prior to the final
recovery device and prior to the introduction of the nonair oxidation stream to
determine the concentration of TOC in the air oxidation stream from the final
recovery device. This concentration of TOC is then used to perform the
calculations outlined in subds. 5. and 6.
3. The molar composition of the process vent
stream shall be determined as follows:
a.
Method 18 to measure the concentration of TOC including those containing
halogens.
b. ASTM D1946-90
(reapproved 1994), incorporated by reference in s.
NR 440.17(2) (a) 24., to measure the
concentration of carbon monoxide and hydrogen.
c. Method 4 to measure the content of water
vapor.
4. The volumetric
flow rate shall be determined using Method 2, 2A, 2C or 2D, as
appropriate.
5. The net heating
value of the vent stream shall be calculated using the following equation:
See PDF
for diagram
where:
HT is the net heating value of the sample, MJ/scm
(Btu/scf), where the net enthalpy per mole of vent stream is based on
combustion at 25°C and 760 mm Hg (77°F and 30 in Hg), but the standard
temperature for determining the volume corresponding to one mole is 20°C
(68°F)
K1 is a constant, 1.740 x 10-7 (1/ppm)(g-mole/scm)(MJ/kcal)
for metric units where standard temperature for (g-mole/scm) is 20°C, and
1.03 x 10-11 (1/ppm)(lb-mole/scf)(Btu/kcal) for English units where standard
temperature for (lb-mole/scf) is 68°F
Cj is the concentration on a wet basis of compound j in
ppm, as measured for organics by Method 18 and measured for hydrogen and carbon
monoxide by ASTM D1946-90 (reapproved 1994), incorporated by reference in s.
NR 440.17(2) (a) 24., as indicated in
subd 3.
Hj is the net heat of combustion of compound j, kcal/g-mole
(kcal/lb-mole), based on combustion at 25°C and 760 mm Hg (77°F and 30
in Hg). The heats of combustion of vent stream components would be required to
be determined using ASTM D2382-88 or D4809-95, incorporated by reference as
specified in s.
NR 440.17(2) (a) 30. and 61., if
published values are not available or cannot be calculated
6. The emission rate of TOC in the process
vent stream shall be calculated using the following equation:
See PDF
for diagram
where:
ETOC is the emission rate of TOC in the sample, kg/hr
(lb/hr)
K2 is the constant, 2.494 10-6 (1/ppm) (g-mole/scm) (kg/g)
(min/hr) for metric units, where standard temperature for (g-mole/scm) is
20°C, and 1.557 x 10-7 (1/ppm)(lb-mole/scf)(min/hr) for English units,
where standard temperature for (lb-mole/scf) is 68°F
Cj is the concentration on a wet basis of compound j in ppm
as measured by Method 18 as indicated in subd. 3.
Mj is the molecular weight of sample j, g/g-mole
(lb/lb-mole)
Qs is the vent stream flow rate (scm/min) (scf/hr) at a
standard temperature of 20°C (68°F)
7. The total process vent stream
concentration (by volume) of compounds containing halogens (ppmv, by compound)
shall be summed from the individual concentrations of compounds containing
halogens which were measured by Method 18.
(f) For purposes of complying with sub. (3)
(c), the owner or operator of a facility affected by this section shall
calculate the TRE index value of the vent stream using the equation for
incineration in subd. 1. for halogenated vent streams. The owner or operator of
an affected facility with a nonhalogenated vent stream shall determine the TRE
index value by calculating values using both the incinerator equation in subd.
1. and the flare equation in subd. 2. and selecting the lower of the 2 values.
1. The TRE index value of the vent stream
controlled by an incinerator shall be calculated using the following equation:
See PDF
for diagram
a. Where for a
vent stream flow rate that is greater than or equal to 14.2 scm/min (501
scf/min) at a standard temperature of 20°C (68°F):
TRE is the TRE index value
Qs is the vent stream flow rate scm/min (scf/min), at a
standard temperature of 20°C (68°F)
HT is the vent stream net heating value, MJ/scm (Btu/scf),
where the net enthalpy per mole of vent stream is based on combustion at
25°C and 760 mm Hg (68°F and 30 in Hg), but the standard temperature
for determining the volume corresponding to one mole is 20°C (68°F), as
in the definition of Qs
Ys = Qs for all vent stream categories listed in Table 1
except for Category E vent streams where Ys = (Qs) (HT)/3.6 for metric units
and Ys = (Qs)(HT)/97 for English units
ETOC is the hourly emissions of TOC, kg/hr (lb/hr)
a, b, c, d, e and f are coefficients
The set of coefficients which apply to a vent stream shall
be obtained from Table 1.
Design Category A1. For
Halogenated Process Vent Streams, If 0 <= Net Heating Value (MJ/scm) <=
3.5 Or If 0 <= Net Heating Value (Btu/scf) <= 94:
|
Qs = Vent Stream Flow Rate scm/min
(scf/min)
|
a
|
b
|
c
|
d
|
e
|
f
|
1) |
14.2 <= Qs <= 18.8 (501 <= Qs <= 664)
|
19.18370 (42.29238) |
0.27580 (0.017220) |
0.75762 (0.072549) |
-0.13064 (-0.00030361) |
0 (0) |
0.01025 (0.003803) |
2) |
18.8 < Qs <=699 (664 < Qs <= 24,700)
|
20.00563 (44.10441) |
0.27580 (0.017220) |
0.30387 (0.029098) |
-0.13064 (-0.00030361) |
0 (0) |
0.01025 (0.003803) |
3) |
699 < Qs <=1400 (24,700 < Qs <= 49,000)
|
39.87022 (87.89789) |
0.29973 (0.018714) |
0.30387 (0.029098) |
-0.13064 (-0.00030361) |
0 (0) |
0.01449 (0.005376) |
4) |
1400 < Qs <=2100 (49,000 < Qs <= 74000)
|
59.73481 (131.6914) |
0.31467 (0.019647) |
0.30387 (0.029098) |
-0.13064 (-0.00030361) |
0 (0) |
0.01775 (0.006585) |
5) |
2100 < Qs <=2800 (74,000 < Qs <= 99,000)
|
79.59941 (175.4849) |
0.32572 (0.020337) |
0.30387 (0.029098) |
-0.13064 (-0.00030361) |
0 (0) |
0.02049 (0.007602) |
6) |
2800 < Qs <=3500 (99,000 < Qs <=
120,000) |
99.46400 (219.2783) |
0.33456 (0.020888) |
0.30387 (0.029098) |
-0.13064 (-0.00030361) |
0 (0) |
0.02291 (0.008500) |
Design Category A2. For
Halogenated Process Vent Streams, If Net Heating Value > 3.5 MJ/scm Or If
Net Heating Value > 94 (Btu/scf):
|
Qs = Vent Stream Flow Rate scm/min
(scf/min)
|
a
|
b
|
c
|
d
|
e
|
f
|
7) |
14.2 <= Qs <= 18.8 |
18.84466 |
0.26742 |
-0.20044 |
0 |
0 |
0.01025 |
(501 <= Qs <= 664) |
(41.54494) |
(0.016696) |
(-0.019194) |
(0) |
(0) |
(0.003803) |
8) |
18.8 < Qs <= 699 |
19.66658 |
0.26742 |
-0.25332 |
0 |
0 |
0.01025 |
(664 < Qs <= 24,700) |
(43.35694) |
(0.016696) |
(-0.024258) |
(0) |
(0) |
(0.003803) |
9) |
699 < Qs <=1400 (24,700 < Qs <= 49,000)
|
39.19213 (86.40297) |
0.29062 (0.018145) |
-0.25332 (-0.024258) |
0 (0) |
0 (0) |
0.01449 (0.005376) |
10) |
1400 < Qs <=2100 (49,000 < Qs <= 74000)
|
58.71768 (129.4490) |
0.30511 (0.019050) |
-0.25332 (-0.024258) |
0 (0) |
0 (0) |
0.01775 (0.006585) |
11) |
2100 < Qs <=2800 (74,000 < Qs <= 99,000)
|
78.24323 (172.4950) |
0.31582 (0.019718) |
-0.25332 (-0.024258) |
0 (0) |
0 (0) |
0.02049 (0.007602) |
12) |
2800 < Qs <=3500 (99,000 < Qs = 120,000)
|
97.76879 (215.5411) |
0.32439 (0.020253) |
-0.25332 (-0.024258) |
0 (0) |
0 (0) |
0.02291 (0.008500) |
Design Category B. For
Nonhalogenated Process Vent Streams, If 0 <= Net Heating Value (MJ/scm)
<= 0.48 Or If 0 <= Net Heating Value (Btu/scf) <= 13:
|
Qs = Vent Stream Flow Rate scm/min
(scf/min)
|
a
|
b
|
c
|
d
|
e
|
f
|
13) |
14.2 < Qs <=1340 (501 < Qs <= 47,300)
|
8.54245 (18.83268) |
0.10555 (0.0065901) |
0.09030 (0.008647) |
-0.17109 (-0.00039762) |
0 (0) |
0.01025 (0.003803) |
14) |
1340 < Qs <=2690 (47,300 < Qs <= 95,000)
|
16.94386 (37.35443) |
0.11470 (0.0071614) |
0.09030 (0.008647) |
-0.17109 (-0.00039762) |
0 (0) |
0.01449 (0.005376) |
15) |
2690 < Qs <=4040 (95,000 < Qs <=
143,000) |
25.34528 (55.87620) |
0.12042 (0.0075185) |
0.09030 (0.008647) |
-0.17109 (-0.00039762) |
0 (0) |
0.01775 (0.00658) |
16) |
14.2 <= Qs <=1340 (501 <= Qs <= 47,300)
|
9.25233 (20.39769) |
0.06105 (0.003812) |
0.31937 (0.030582) |
-0.16181 (-0.00037605) |
0 (0) |
0.01025 (0.003803) |
17) |
1,340< Qs <= 2,690 |
18.36363 |
0.06635 |
0.31937 |
-0.16181 |
0 |
0.01449 |
(47,300 < Qs <=
95,000) | (40.48446) | (0.004143) | (0.030582) | (-0.00037605) | (0) | (0.005376) |
18) |
2,690< Qs <= 4,040 |
27.47492 |
0.06965 |
0.31937 |
-0.16181 |
0 |
0.01775 |
(95,000 < Qs <=
143,000) | (60.57121) | (0.004349) | (0.030582) | (-0.00037605) | (0) | (0.006585) |
Design Category D. For
Nonhalogenated Process Vent Streams, If 1.9 < Net Heating Value (MJ/scm)
<= 3.6: Or If 51 < Net Heating Value (Btu/scf) <= 97:
|
Qs = Vent Stream Flow Rate
scm/min
(scf/min) | a | b | c | d | e | f |
19) |
14.2 < Qs <= 1,180 |
6.67868 |
0.06943 |
0.02582 |
0 |
0 |
0.01025 |
(501 <= Qs <=
41,700) | (14.72382) | (0.004335) | (0.002472) | (0) | (0) | (0.003803) |
20) |
1,180 < Qs <= 2,370 |
13.21633 |
0.07546 |
0.02582 |
0 |
0 |
0.01449 |
(41,000 < Qs <=
83,700) | (29.13672) | (0.004711) | (0.002472) | (0) | (0) | (0.005376) |
21) |
2,370< Qs <= 3,550 |
19.75398 |
0.07922 |
0.02582 |
0 |
0 |
0.01755 |
(83,700 < Qs <=
125,000) | (43.54962) | (0.004946) | (0.002472) | (0) | (0) | (0.00658) |
Design Category E. For
Nonhalogenated Process Vent Streams, If Net Heating Value > 3.6 MJ/scm Or If
Net Heating Value > 97 Btu/scf):
|
Ys = Dilution Flow Rate
scm/min = (Qs)(HT)/3.6 (scf/min) =
(Qs)(HT)/97 | a | b | c | d | e | f |
22) |
14.2 <= Ys <=1,180 |
6.67868 |
0 |
0 |
-0.00707 |
0.02220 |
0.01025 |
(501 <= Ys <=
41,700) | (14.72382) | (0) | (0) | (-0.0000164) | (0.0001174) | (0.003803) |
23) |
1,180 < Ys <= 2,370 |
13.21633 |
0 |
0 |
-0.00707 |
0.02412 |
0.01449 |
(41,700 < Ys <=
83,700) | (29.13672) | (0) | (0) | (-0.0000164) | (0.0001276) | (0.005376) |
24) |
2,370< Ys <= 3,550 |
19.75398 |
0 |
0 |
-0.00707 |
0.02533 |
0.01755 |
(83,700 < Ys <= 125,000) |
(43.54962) |
(0) |
(0) |
(-0.0000164) |
(0.0001340) |
(0.006585) |
b.
Where for a vent stream flow rate that is less than 14.2 scm/min (501 scf/min)
at a standard temperature of 20°C (68°F):
TRE is the TRE index value
Qs is 14.2 scm/min (501 scf/min)
HT is (FLOW) (HVAL) / Qs
where the following inputs are used:
FLOW is the vent stream flow rate (scm/min) (scf/min), at a
standard temperature of 20°C (68°F)
HVAL is the vent stream net heating value MJ/scm (Btu/scf),
where the net enthalpy per mole of vent stream is based on combustion at
25°C and 760 mm Hg (77°F and 30 in Hg), but the standard temperature
for determining the volume corresponding to 1 mole is 20°C (68°F) as in
the definition of Qs
Ys = Qs for all vent stream categories listed in Table 1
except for Category E vent streams, where Ys = QsHT/3.6 for metric units and Ys
= QsHT/97 for English units.
ETOC is the hourly emissions of TOC reported in kg/hr
(lb/hr)
a,b,c,d,e and f are coefficients
The set of coefficients that apply to a vent stream shall
be obtained from Table 1.
2. The equation for calculating the TRE index
value of a vent stream controlled by a flare is as follows:
See
PDF for diagram
where:
TRE is the TRE index value
ETOC is the hourly emissions of TOC, kg/hr (lb/hr)
Qs is the vent stream flow rate, scm/min (scf/min) at a
standard temperature of 20°C (68°F)
HT is the vent stream net heating value, MJ/scm (Btu/scf),
where the net enthalpy per mole of vent stream is based on combustion at
25°C and 760 mm Hg (77°F and 30 in Hg), but the standard temperature
for determining the volume corresponding to 1 mole is 20°C (68°F) as in
the definition of Qs
a, b, c, d and e are coefficients
The set of coefficients that apply to a vent stream shall
be obtained from Table 2.
Table 2. Air Oxidation Processes NSPS TRE
Coefficients For Vent Streams Controlled By a Flare
a
|
b
|
c
|
d
|
e
|
a. |
HT < 11.2 MJ/scm |
2.25 |
0.288 |
-0.193 |
-0.0051 |
2.08 |
(HT < 301 Btu/scf) |
(0.140) |
(0.0367) |
(-0.000448) |
(-0.0051) |
(4.59) |
b. |
HT >= 11.2 MJ/scm |
0.309 |
0.0619 |
-0.0043 |
-0.0034 |
2.08 |
(HT >= 301 Btu/scf) |
(0.0193) |
(0.00788) |
(-0.000010) |
(-0.0034) |
(4.59) |
(g) Each owner or operator of an affected
facility seeking to comply with sub. (1) (c) or (3) (c) shall recalculate the
TRE index value for that affected facility whenever process changes are made.
Some examples of process changes are changes in production capacity, feedstock
type or catalyst type or whenever there is replacement, removal or addition of
recovery equipment. The TRE index value shall be recalculated based on test
data or on best engineering estimates of the effects of the change to the
recovery system.
1. Where the recalculated
TRE index value is less than or equal to 1.0, the owner or operator shall
notify the department within 1 week of the recalculation and shall conduct a
performance test according to the methods and procedures required by sub. (5)
to determine compliance with sub. (3) (a). Performance tests shall be conducted
as soon as possible after the process change but no later than 180 days from
the time of the process change.
2.
Where the initial TRE index value is greater than 4.0 and the recalculated TRE
index value is less than or equal to 4.0, but greater than 1.0, the owner or
operator shall conduct a performance test in accordance with s.
NR 440.08 and
this subsection, and shall comply with subs. (4) and (6) and this subsection.
Performance tests shall be conducted as soon as possible after the process
change but no later than 180 days from the time of the process
change.
(6)
REPORTING AND RECORDKEEPING REQUIREMENTS.
(a)
Each owner or operator subject to sub. (3) shall notify the department of the
specific provisions of sub. (3) with which the owner or operator has elected to
comply. Notification shall be submitted with the notification of initial
startup required by s.
NR 440.07(1)
(c). If an owner or operator elects at a
later date to use an alternative provision of sub. (3) with which he or she
will comply, then the department shall be notified by the owner or operator 90
days before implementing a change and, upon implementing the change, a
performance test shall be performed as specified by sub. (5) within 180
days.
(b) Each owner or operator
subject to the provisions of this section shall keep up-to-date, readily
accessible records of the following data measured during each performance test
and also include the following data in the report of the initial performance
test required under s.
NR 440.08.
Where a boiler or process heater with a design heat input capacity of 44 MW
(150 million Btu/hour) or greater is used to comply with sub. (3) (a), a report
containing performance test data need not be submitted, but a report containing
the information of subd. 2. a. is required. The same data specified in this
subsection shall be submitted in the reports of all subsequently required
performance tests where either the emission control efficiency of a control
device, outlet concentration of TOC or the TRE index value of a vent stream
from a recovery system is determined.
1.
Where an owner or operator subject to this section seeks to demonstrate
compliance with sub. (3) (a) through use of either a thermal or catalytic
incinerator: a. The average firebox temperature of the incinerator, or the
average temperature upstream and downstream of the catalyst bed for a catalytic
incinerator, measured at least every 15 minutes and averaged over the same time
period of the performance testing, and b. The percent reduction of TOC
determined as specified in sub. (5) (b) achieved by the incinerator or the
concentration of TOC (ppmv, by compound) determined as specified in sub. (5)
(b) at the outlet of the control device on a dry basis corrected to 3% oxygen.
2. Where an owner or operator
subject to the provisions of this section seeks to demonstrate compliance with
sub. (3) (a) through use of a boiler or process heater:
a. A description of the location at which the
vent stream is introduced into the boiler or process heater, and
b. The average combustion temperature of the
boiler or process heater with a design heat input capacity of less than 44 MW
(150 million Btu/hr) measured at least every 15 minutes and averaged over the
same time period of the performance testing.
3. Where an owner or operator subject to the
provisions of this section seeks to comply with sub. (3) (b) through the use of
a smokeless flare, flare design, that is, steam-assisted, air-assisted or
nonassisted, all visible emission readings, heat content determinations, flow
rate measurements and exit velocity determinations made during the performance
test, continuous records of the flare pilot flame monitoring and records of all
periods of operations during which the pilot flame is absent.
4. Where an owner or operator seeks to
demonstrate compliance with sub. (3) (c).
a.
Where an absorber is the final recovery device in a recovery system, the exit
specific gravity, or alternative parameter which is a measure of the degree of
absorbing liquid saturation, if approved by the department, and average exit
temperature of the absorbing liquid, measured at least every 15 minutes and
averaged over the same time period of the performance testing, both measured
while the vent stream is normally routed and constituted; or
b. Where a condenser is the final recovery
device in a recovery system, the average exit, that is, product side,
temperature, measured at least every 15 minutes and average over the same time
period of the performance testing while the vent stream is normally routed and
constituted.
c. Where a carbon
adsorber is the final recovery device in a recovery system, the total steam
mass flow measured at least every 15 minutes and averaged over the same time
period of the performance test, that is, full carbon bed cycle, temperature of
the carbon bed after regeneration, and within 15 minutes of completion of any
cooling cycle, and duration of the carbon bed steaming cycle, all measured
while the vent stream is normally routed and constituted; or
d. As an alternative to subd. 4. a., b. or
c., the concentration level or reading indicated by the organic monitoring
device at the outlet of the absorber, condenser or carbon adsorber measured at
least every 15 minutes and averaged over the same time period of the
performance testing while the vent stream is normally routed and
constituted.
e. All measurements
and calculations performed to determine the TRE index value of the vent
stream.
(c)
Each owner or operator subject to the provisions of this section shall keep
up-to-date, readily accessible continuous records of the equipment operating
parameters specified to be monitored under sub. (4) (a) and (c) as well as
up-to-date, readily accessible records of periods of operation during which the
parameter boundaries established during the most recent performance test are
exceeded. The department may at any time require a report of these data. Where
a combustion device is used by an owner or operator seeking to demonstrate
compliance with sub. (3) (a) or (c), periods of operation during which the
parameter boundaries established during the most recent performance tests are
exceeded are defined as follows:
1. For
thermal incinerators, all 3-hour periods of operation during which the average
combustion temperature was more than 28°C (50°F) below the average
temperature of the vent stream during the most recent performance test at which
compliance with sub. (3) (a) was determined.
2. For catalytic incinerators, all 3-hour
periods of operation during which the average temperature of the vent stream
immediately before the catalyst bed is more than 28°C (50°F) below the
average temperature of the vent stream during the most recent performance test
at which compliance with sub. (3) (a) was determined. The owner or operator
also shall record all 3-hour periods of operation during which the average
temperature difference across the catalyst bed is less than 80% of the average
temperature difference of the device during the most recent performance test at
which compliance with sub. (3) (a) was determined.
3. All 3-hour periods of operation during
which the average combustion temperature was more than 28°C (50°F)
below the average combustion temperature during the most recent performance
test at which compliance with sub. (3) (a) was determined for boilers or
process heaters with a design heat input capacity of less than 44 MW (150
million Btu/hr).
4. For boilers or
process heaters, whenever there is a change in the location at which the vent
stream is introduced into the flame zone as required under sub. (3)
(a).
(d) Each owner or
operator subject to the provisions of this section shall keep up-to-date,
readily accessible continuous records of the flow indication specified under
sub. (4) (a) 2., (b) 2. and (c) 1. as well as up-to-date, readily accessible
records of all periods when the vent stream is diverted from the control device
or has no flow rate.
(e) Each owner
or operator subject to the provisions of this section who uses a boiler or
process heater with a design heat input capacity of 44 MW (150 million
Btu/hour) or greater to comply with sub. (3) (a) shall keep an up-to-date,
readily accessible record of all periods of operation of the boiler or process
heater.
Note: Examples of such records could include records of
steam use, fuel use or monitoring data collected pursuant to other state or
federal regulatory requirements.
(f) Each owner or operator subject to the
provisions of this section shall keep up-to-date, readily accessible continuous
records of the flare pilot flame monitoring specified in sub. (4) (b), as well
as up-to-date, readily accessible records of all periods of operations in which
the pilot flame is absent.
(g) Each
owner or operator subject to the provisions of this section shall keep
up-to-date, readily accessible continuous records of the equipment operating
parameters specified to be monitored under sub. (4) (e) as well as up-to-date,
readily accessible records of periods of operation during which the parameter
boundaries established during the most recent performance test are exceeded.
The department may at any time require a report of these data. Where the owner
or operator seeks to demonstrate compliance with sub. (3) (c), periods of
operation during which the parameter boundaries established during the most
recent performance tests are exceeded are defined as follows:
1. Where an absorber is the final recovery
device in a recovery system and where an organic monitoring device is not used:
a. All 3-hour periods of operation during
which the average absorbing liquid temperature was more than 11°C (20
°F) above the average absorbing liquid temperature during the most recent
performance test or
b. All 3-hour
periods of operation during which the average absorbing liquid specific gravity
was more than 0.1 unit above or more than 0.1 unit below, the average absorbing
liquid specific gravity during the most recent performance test, unless
monitoring of an alternative parameter, which is a measure of the degree of
absorbing liquid saturation, is approved by the department, in which case the
department will define appropriate parameter boundaries and periods of
operation during which they are exceeded.
2. When a condenser is the final recovery
device in a recovery system and where an organic monitoring device is not used,
all 3-hour periods of operation during which the average exit or product side
condenser operating temperature was more than 6°C (11°F) above the
average exit (product side) operating temperature during the most recent
performance test.
3. Where a carbon
adsorber is the final recovery device in a recovery system and where an organic
monitoring device is not used:
a. All carbon
bed regeneration cycles during which the total mass steam flow was more than
10% below the total mass steam flow during the most recent performance test;
or
b. All carbon bed regeneration
cycles during which the temperature of the carbon bed after regeneration, and
after completion of any cooling cycle, was more than 10% greater than the
carbon bed temperature, in degrees Celsius, during the most recent performance
test.
4. Where an
absorber, condenser or carbon adsorber is the final recovery device in the
recovery system and an organic monitoring device approved by the department is
used, all 3-hour periods of operation during which the average concentration
level or reading of organic compounds in the exhaust gases is more than 20%
greater than the exhaust gas organic compound concentration level or reading
measured by the monitoring device during the most recent performance
test.
(h) Each owner or
operator subject to the provisions of this section and seeking to demonstrate
compliance with sub. (3) (c) shall keep up-to-date, readily accessible records
of:
1. Any changes in production capacity,
feedstock type or of any replacement, removal or addition of recovery equipment
or air oxidation reactors;
2. Any
recalculation of the TRE index value performed pursuant to sub. (5)
(f);
3. The results of any
performance test performed pursuant to the methods and procedures required by
sub. (5) (d).
(i) Each
owner and operator subject to the provisions of this section is exempt from the
quarterly reporting requirements contained in s.
NR 440.07(3).
(j) Each owner or operator that seeks to
comply with the requirements of this section by complying with the requirements
of sub. (3) shall submit to the department semiannual reports of the following
information. The initial report shall be submitted within 6 months after the
initial startup date.
1. Exceedances of
monitored parameters recorded under pars. (c) and (g).
2. All periods recorded under par. (d) when
the vent stream is diverted from the control device or has no flow
rate.
3. All periods recorded under
par. (e) when the boiler or process heater was not operating.
4. All periods recorded under par. (f) in
which the pilot flame of the flare was absent.
5. Any recalculation of the TRE index value,
as recorded under par. (h).
Note: The requirements of par. (j) remain in force until
and unless EPA, in delegating enforcement authority to a state under section
111 (c) of the act, approves reporting requirements or an alternative means of
compliance surveillance adopted by such state. In that event, affected sources
within the state will be relieved of the obligation to comply with par. (j),
provided that they comply with the requirements established by the
state.
(L) The
department will specify appropriate reporting and recordkeeping requirements
where the owner or operator of an affected facility seeks to demonstrate
compliance with the standards specified under sub. (3) other than as provided
under sub. (4) (a) to (d).
(7) RECONSTRUCTION.
(a) For purposes of this section "fixed
capital cost of the new components", as used in s.
NR 440.15, includes the fixed capital cost of all
depreciable components which are or will be replaced pursuant to all continuous
programs of components which are commenced within any 2-year period following
October 21, 1983. For purposes of this paragraph,"commenced" means that an
owner or operator has undertaken a continuous program of component replacement
or that an owner or operator has entered into a contractual obligation to
undertake and complete, within a reasonable time, a continuous program of
component replacement.
(8) CHEMICALS AFFECTED BY THIS SECTION.
Chemical Name
|
CAS No.*
|
(a) |
Acetaldehyde ...................... |
75-07-0 |
(b) |
Acetic acid ........................ |
64-19-7 |
(c) |
Acetone .......................... |
67-64-1 |
(d) |
Acetonitrile........................ |
75-05-8 |
(e) |
Acetophenone...................... |
98-86-2 |
(f) |
Acrolein .......................... |
107-02-8 |
(g) |
Acrylic acid ....................... |
79-10-7 |
(h) |
Acrylonitrile....................... |
107-13-1 |
(i) |
Anthraquinone ..................... |
84-65-1 |
(J) |
Benzaldehyde...................... |
100-52-7 |
(k) |
Benzoic acid, tech................... |
65-85-0 |
(L) |
1,3-Butadiene...................... |
106-99-0 |
(m) |
p-t-Butyl benzoic acid............... |
98-73-7 |
(n) |
N-Butyric acid..................... |
107-92-6 |
(o) |
Crotonic acid ...................... |
3724-65-0 |
(P) |
Cumene hydroperoxide .............. |
80-15-9 |
(q) |
Cyclohexanol ...................... |
108-93-0 |
(qm) |
Cyclohexanone..................... |
108-94-1 |
(r) |
Dimethyl terephthalate............... |
120-61-6 |
(rm) |
Ethylene dichloride .................. |
107-06-2 |
(s) |
Ethylene oxide ..................... |
75-21-8 |
(sm) |
Formaldehyde ...................... |
50-00-0 |
(t) |
Formic acid ........................ |
64-18-6 |
(tm) |
Glyoxal........................... |
107-22-2 |
(u) |
Hydrogen cyanide .................. |
74-90-8 |
(um) |
Isobutyric acid ..................... |
79-31-2-5 |
(v) |
Isophthalic acid ..................... |
121-91 |
(vm) |
Maleic anhydride ................... |
108-31-6 |
(w) |
Methyl ethyl ketone ................. |
78-93-3 |
(wm) |
a-Methyl styrene................... |
98-83-9 |
(x) |
Phenol............................ |
108-95-2 |
(xm) |
Phthalic anhydride .................. |
85-44-9 |
(y) |
Propionic acid ...................... |
79-09-4 |
(ym) |
Propylene oxide .................... |
75-56-9 |
(z) |
Styrene ........................... |
100-42-5 |
(zm) |
Terephthalic acid ................... |
100-21-0 |
*CAS numbers refer to the Chemical Abstracts Service
Registry numbers assigned to specific isomers or mixtures of chemicals. Some
isomers or mixtures that are covered by the standards do not have CAS numbers
assigned to them. The standards apply to all of the chemicals listed, whether
CAS numbers have been assigned or not.