(1) APPLICABILITY.
(a) The affected facility to which this
section applies is each MWC unit with an MWC unit capacity greater than 225
megagrams per day (250 tons per day) of MSW for which construction,
modification or reconstruction is commenced as follows:
1. Construction is commenced after December
20, 1989 and on or before September 20, 1994.
2. Modification or reconstruction is
commenced after December 20, 1989 and on or before June 19, 1996.
(c) Any unit combusting a
single-item waste stream of tires is exempt from this section if the owner or
operator of the unit does the following:
1.
Notifies the department of an exemption claim.
2. Provides data documenting that the unit
qualifies for the exemption.
(d) Any cofired combustor, as defined under
sub. (2), located at a plant that meets the capacity specification in par. (a)
is exempt from other requirements of this section if the owner or operator of
the cofired combustor does all of the following:
1. Notifies the department of an exemption
claim.
2. Provides a copy of the
federally enforceable permit specified in the definition of cofired combustor
under sub. (2).
3. Keeps a record
on a calendar quarter basis of the weight of MSW combusted at the cofired
combustor and the weight of all other fuels combusted at the cofired
combustor.
(e) Any
cofired combustor that is subject to a federally enforceable permit limiting
the operation of the combustor to no more than 225 megagrams per day (250 tons
per day) of MSW is exempt from this section.
(f) Physical or operational changes made to
an existing MWC unit primarily for the purpose of complying with emission
guidelines under 40 CFR part 60 subpart Cb are not considered a modification or
reconstruction and do not result in an existing MWC unit becoming subject to
this section.
(g) A qualifying
small power production facility, as defined in section 3 (17) (C) of the
Federal Power Act (16
USC 796(17) (C)), that
burns homogeneous waste, such as automotive tires or used oil, but not
including refuse-derived fuel, for the production of electric energy is exempt
from this section if the owner or operator of the facility notifies the
department of an exemption claim and provides data documenting that the
facility qualifies for this exemption.
(h) A qualifying cogeneration facility, as
defined in section 3 (18) (B) of the Federal Power Act (16
USC 796(18) (B)), that
burns homogeneous waste such as automotive tires or used oil, but not including
refuse-derived fuel, for the production of electric energy and steam or forms
of useful energy such as heat that are used for industrial, commercial, heating
or cooling purposes, is exempt from this section if the owner or operator of
the facility notifies the department of an exemption claim and provides data
documenting that the facility qualifies for this exemption.
(i) Any unit required to have a permit under
section 3005 of the Solid Waste Disposal Act (42
USC 6925) is exempt from this
section.
(j) Any materials recovery
facility, including primary or secondary smelters, that combusts waste for the
primary purpose of recovering metals is exempt from this section.
(k) Pyrolysis or combustion units that are an
integrated part of a plastics or rubber recycling unit, as defined under sub.
(2), are exempt from this section if the owner or operator of the plastics or
rubber recycling unit keeps records of the weight of plastics, rubber and
rubber tires processed on a calendar quarter basis; the weight of chemical
plant feedstocks and petroleum refinery feedstocks produced and marketed on a
calendar quarter basis; and the name and address of the purchaser of the
feedstocks. The combustion of gasoline, diesel fuel, jet fuel, fuel oils,
residual oil, refinery gas, petroleum coke, liquified petroleum gas, propane or
butane produced by chemical plants or petroleum refineries that use feedstocks
produced by plastics or rubber recycling units are exempt from this
section.
(2)
DEFINITIONS. All terms not defined in this section have the meanings given in
s.
NR 440.02. In this section:
(a) "Batch MWC"means an MWC unit designed
such that it cannot combust MSW continuously 24 hours per day because the
design does not allow waste to be fed to the unit or ash to be removed while
combustion is occurring.
(b)
"Bubbling fluidized bed combustor" means a fluidized bed combustor in which the
majority of the bed material remains in a fluidized state in the primary
combustion zone.
(be) "Calendar
quarter" means a consecutive 3-month period, nonoverlapping, beginning on
January 1, April 1, July 1 or October 1.
(bm) "Chief facility operator" means the
person in direct charge and control of the operation of an MWC and who is
responsible for daily on site supervision, technical direction, management and
overall performance of the facility.
(c) "Circulating fluidized bed combustor"
means a fluidized bed combustor in which the majority of the fluidized bed
material is carried out of the primary combustion zone and is transported back
to the primary zone through a recirculation loop.
(cm) "Clean wood" means untreated wood or
untreated wood products including clean untreated lumber, tree stumps (whole or
chipped) and tree limbs (whole or chipped). Clean wood does not include yard
waste, construction, renovation and demolition wastes (which includes railroad
ties and telephone poles), which are exempt from the definition of
MSW.
(d) "Cofired combustor" means
a unit combusting MSW with a non-MSW fuel (for example, coal or industrial
process waste) and subject to a federally enforceable permit limiting the unit
to combusting a fuel feed stream, 30% or less of the weight of which is
comprised, in aggregate, of MSW as measured on a calendar quarter basis.
(dm) "Continuous emission
monitoring system" or "CEMS" means a monitoring system for continuously
measuring the emissions of a pollutant from an affected facility.
(ds) "Continuous monitoring system" means the
total equipment used to sample and condition (if applicable), to analyze and to
provide a permanent record of emissions or process parameters.
(e) "Dioxin/furan" means total tetra through
octa-chlorinated dibenzo-p- dioxins and dibenzofurans.
(em) "Four-hour block average" or "4-hour
block average" means the average of all hourly emission rates when the affected
facility is operating and combusting MSW measured over 4-hour periods of time
from 12:00 midnight to 4 a.m., 4 a.m. to 8 a.m., 8 a.m. to 12:00 noon, 12:00
noon to 4 p.m., 4 p.m. to 8 p.m., and 8 p.m. to 12:00 midnight.
(f) "Large MWC plant" means an MWC plant with
an MWC aggregate plant capacity for affected facilities that is greater than
225 megagrams per day (250 tons per day) of MSW.
(fm) "Mass burn refractory MWC" means a
field-erected combustor that combusts MSW in a refractory wall furnace. Unless
otherwise specified, this includes combustors with a cylindrical rotary
refractory wall furnace.
(g) "Mass
burn rotary waterwall MWC" means a field-erected combustor that combusts MSW in
a cylindrical rotary waterwall furnace.
(gm) "Mass burn waterwall MWC" means a
field-erected combustor that combusts MSW in a waterwall furnace.
(h) "Maximum demonstrated MWC unit load"
means the highest 4-hour arithmetic average MWC unit load achieved during 4
consecutive hours during the most recent dioxin/furan performance test
demonstrating compliance with the applicable limit for MWC organics specified
under sub. (4).
(hm) "Maximum
demonstrated particulate matter control device temperature" means the maximum
4-hour arithmetic average flue gas temperature measured at the particulate
matter control device inlet during 4 consecutive hours during the most recent
dioxin/furan performance test demonstrating compliance with the applicable
limit for MWC organics specified under sub. (4).
(i) "Modification" or "modified MWC unit"
means an MWC unit to which changes have been made if the cumulative cost of the
changes, over the life of the unit, exceed 50% of the original cost of
construction and installation of the unit, not including the cost of any land
purchased in connection with the construction or installation, updated to
current costs; or any physical change in the MWC unit or change in the method
of operation of the MWC unit which increases the amount of any air pollutant
emitted by the unit for which standards have been established under section 111
or 129 of the Act (42 USC
7411 or
7429).
Increases in the amount of any air pollutant emitted by the MWC unit are
determined at 100% physical load capability and downstream of all air pollution
control devices, with no consideration given for load restrictions based on
permits or other non-physical operational restrictions.
(im) "Modular excess air MWC" means a
combustor that combusts MSW and that is not field erected and has multiple
combustion chambers, all of which are designed to operate at conditions with
combustion air amounts in excess of theoretical air requirements.
(j) "Modular starved air MWC" means a
combustor that combusts MSW and that is not field erected and has multiple
combustion chambers in which the primary combustion chamber is designed to
operate at substoichiometric conditions.
(jm) "Municipal solid waste" or "municipal
type solid waste" or "MSW" means household, commercial, retail or institutional
waste. Household waste includes material discarded by single and multiple
residential dwellings, hotels, motels and other similar permanent or temporary
housing establishments or facilities. Commercial or retail waste includes
material discarded by stores, offices, restaurants, warehouses,
nonmanufacturing activities at industrial facilities and other similar
establishments or facilities. Institutional waste includes material discarded
by schools, nonmedical waste discarded by hospitals, material discarded by
nonmanufacturing activities at prisons and government facilities and material
discarded by other similar establishments or facilities. Household, commercial
or retail and institutional waste do not include used oil; sewage sludge; wood
pallets; construction, renovation and demolition wastes (which includes
railroad ties and telephone poles); industrial process or manufacturing wastes;
medical waste or motor vehicles including motor vehicle parts or vehicle fluff.
Household, commercial, retail and institutional wastes include yard waste,
refuse-derived fuel and motor vehicle maintenance materials limited to vehicle
batteries and tires except as specified in sub. (1) (c).
(k) "Municipal waste combustor" or "MWC" or
"MWC unit" means any setting or equipment that combusts solid, liquid or
gasified MSW including, but not limited to, field erected incinerators with or
without heat recovery; modular incinerators, starved air or excess air; boilers
or steam generating units; furnaces whether suspension fired, grate fired, mass
fired, air curtain incinerators or fluidized bed fired; and pyrolysis or
combustion units. MWC does not include pyrolysis or combustion units located at
plastics or rubber recycling units. MWC does not include internal combustion
engines, gas turbines or other combustion devices that combust landfill gases
collected by landfill gas collection systems. The MWC unit includes the MSW
fuel feed system, grate system, flue gas system, bottom ash system and the
combustor water system. The MWC boundary starts at the MSW pit or hopper and
extends through the combustor flue gas system, which ends immediately following
the heat recovery equipment or, if there is no heat recovery equipment,
immediately following the combustion chamber; the combustor bottom ash system,
which ends at the truck loading station or similar ash handling equipment that
transfers the ash to final disposal, including all ash handling systems that
are connected to the bottom ash handling system; and the combustor water
system, which starts at the feed water pump and ends at the piping exiting the
steam drum or superheater. The MWC unit does not include air pollution control
equipment, the stack, water treatment equipment or the turbine generator set.
(L) "MWC acid gases" means all acid
gases emitted in the exhaust gases from MWC units including but not limited to
sulfur dioxide and hydrogen chloride gases.
(m) "MWC metals" means metals and metal
compounds emitted in the exhaust gases from MWC units.
(n) "MWC organics" means organic compounds
emitted in the exhaust gases from MWC units and includes total tetra through
octa-chlorinated dibenzo-p- dioxins and dibenzofurans.
(o) "MWC plant" means one or more MWC units
at the same location for which construction, modification or reconstruction is
commenced after December 20, 1989 and on or before September 20,
1994.
(p) "MWC plant capacity"
means the aggregate MWC unit capacity of all MWC units at an MWC plant for
which construction, modification or reconstruction of the units commenced after
December 20, 1989 and on or before September 20, 1994. Any MWC units for which
construction, modification or reconstruction is commenced on or before December
20, 1989 or after September 20, 1994 are not included for determining
applicability under this section.
(q) "MWC unit capacity" means the maximum
design charging rate of an MWC unit expressed in megagrams per day or tons per
day of MSW combusted, calculated according to the procedures under sub. (9)
(j). Municipal waste combustor unit capacity is calculated using a design
heating value of 10,500 kilojoules per kilogram (4,500 British thermal units
per pound) for MSW. The calculational procedures under sub. (9) (j) include
procedures for determining MWC unit capacity for continuous and batch feed
MWCs.
(r) "Particulate matter"
means total particulate matter emitted from MWC units as measured by Method 5
of Appendix A of 40 CFR part 60, incorporated by reference in s.
NR 440.17.
(rm) "Plastics or rubber recycling unit"
means an integrated processing unit where plastics, rubber or rubber tires are
the only feed materials and the feed materials are processed into a chemical
plant feedstock or petroleum refinery feedstock, where the feedstock is
marketed to and used by a chemical plant or petroleum refinery as input
feedstock. The combined weight of the chemical plant feedstock and petroleum
refinery feedstock produced by the plastics or rubber recycling unit on a
calendar quarter basis shall be more than 70% of the combined weight of the
plastic, rubber and rubber tires processed by the plastics or rubber recycling
unit on a calendar quarter basis. The plastics, rubber or rubber tire feed
materials to the plastics or rubber recycling unit may originate from the
separation or diversion of plastics, rubber or rubber tires from MSW or
industrial solid waste and may include manufacturing scraps, trimmings and
off-specification plastics, rubber and rubber tire discards. The plastics,
rubber and rubber tire feed materials to the plastics or rubber recycling unit
may contain incidental contaminants, for example, paper labels on plastic
bottles, metal rings on plastic bottle caps, etc.
(s) "Potential hydrogen chloride emission
rate" means the hydrogen chloride emission rate that would occur from
combustion of MSW in the absence of any hydrogen chloride emissions
control.
(t) "Potential sulfur
dioxide emission rate" means the sulfur dioxide emission rate that would occur
from combustion of MSW in the absence of any sulfur dioxide emissions control.
(tg) "Pulverized coal and RDF
mixed fuel-fired combustor" means a combustor that fires coal and RDF
simultaneously, in which pulverized coal is introduced into an air stream that
carries the coal to the combustion chamber of the unit where it is fired in
suspension. This includes both conventional pulverized coal and micropulverized
coal.
(tr) "Pyrolysis or
combustion unit" means a unit that produces gases, liquids or solids through
the heating of MSW, and the gases, liquids or solids produced are combusted and
emissions vented to the atmosphere.
(u) "RDF stoker" means a steam generating
unit that combusts RDF in a semi-suspension firing mode using air fed
distributors.
(ug) "Reconstruction"
means rebuilding an MWC unit for which the cumulative costs of the construction
over the life of the unit exceed 50% of the original cost of construction and
installation of the unit, not including any cost of land purchased in
connection with such construction or installation, updated to current dollars.
(ur) "Refractory unit" or
"refractory wall furnace" means a combustion unit having no energy recovery
(for example, via a waterwall) in the furnace (that is, radiant heat transfer
section) of the combustor.
(v)
"Refuse derived fuel" or "RDF" means a type of MSW produced by processing MSW
through shredding and size classification. This includes all classes of RDF
including low density fluff RDF through densified RDF and RDF fuel
pellets.
(w) "Same location" means
the same or contiguous property that is under common ownership or control,
including properties that are separated only by a street, road, highway or
other public right of way. Common ownership or control includes properties that
are owned, leased or operated by the same entity, parent entity, subsidiary,
subdivision or any combination thereof, including any municipality or other
governmental unit or any quasi- governmental authority such as a public utility
district or regional waste disposal authority.
(x) "Shift supervisor" means the person in
direct charge and control of the operation of an MWC and who is responsible for
on site supervision, technical direction, management and overall performance of
the facility during an assigned shift.
(xm) "Spreader stoker coal and RDF mixed
fuel-fired combustor" means a combustor that fires coal and RDF simultaneously,
in which coal is introduced to the combustion zone by a mechanism that throws
the fuel onto a grate from above. Combustion takes place both in suspension and
on the grate.
(y) "Standard
conditions" means a temperature of 20°C (68°F) and a pressure of 101.3
kPa (29.92 in Hg).
(z)
"Twenty-four-hour daily average" or "24-hour daily average" means the
arithmetic or geometric mean as specified in sub. (9) (e), (g) or (h), as
applicable, of all hourly emission rates when the affected facility is
operating and firing MSW measured over a 24-hour period between 12:00 midnight
and the following midnight.
(ze)
"Untreated lumber" means wood or wood products that have been cut or shaped and
includes wet, air-dried and kiln-dried wood products. Untreated lumber does not
include wood products that have been painted, pigment-stained or
pressure-treated. Pressure treating compounds include chromate copper arsenate,
pentachlorophenol and creosote.
(zm) "Waterwall furnace" means a combustion
unit having energy (heat) recovery in the furnace (that is, radiant heat
transfer section) of the combustor.
(zs) "Yard waste" means grass, grass
clippings, bushes, shrubs and clippings from bushes and shrubs that are
generated by residential, commercial or retail, institutional or industrial
sources as part of maintenance activities associated with yards or other
private or public lands. Yard waste does not include construction, renovation
and demolition wastes, which are exempt from the definition of MSW. Yard waste
does not include clean wood, which is exempt from the definition of
MSW.
(7) STANDARDS FOR
MUNICIPAL WASTE COMBUSTOR OPERATING PRACTICES.
(a) On and after the date on which the
initial compliance test is completed or is required to be completed under s.
NR 440.08, no
owner or operator of an affected facility located within a large MWC plant may
cause the facility to exceed the carbon monoxide standards shown in Table 1.
Table 1.
MWC Operating Standards
MWC Technology
|
Carbon Monoxide Emission Limit (parts per
million by volume)1
|
1. Mass burn waterwall |
100 |
2. Mass burn refractory |
100 |
3. Mass burn rotary water-wall |
100 |
4. Modular starved air |
50 |
5. Modular excess air |
50 |
6. RDF Stoker |
150 |
7. Bubbling fluidized bed combustor |
100 |
8. Circulating fluidized bed combustor |
100 |
9. Pulverized coal/RDF mixed fuel-fired com-bustor
|
150 |
10. Spreader stoker coal/ RDF mixed fuel-fired
combustor |
150 |
1 Measured at the combustor
outlet in conjunction with a measurement of oxygen concentration, corrected to
7% oxygen dry basis. The averaging times are specified in sub. (9) (h).
(b) No owner or operator of
an affected facility located within a large MWC plant may cause the facility to
operate at a load level greater than 110% of the maximum demonstrated MWC unit
load as defined in sub. (2). The averaging time is specified under sub. (9)
(h).
(c) No owner or operator of an
affected facility located within a large MWC plant may cause the facility to
operate at a temperature, measured at the final particulate matter control
device inlet, exceeding 17°C (30°F) above the maximum demonstrated
particulate matter control device temperature as defined in sub. (2). The
averaging time is specified under sub. (9) (h).
(d) Within 24 months from the date of startup
of an affected facility or before February 11, 1993, whichever is later, each
chief facility operator and shift supervisor of an affected facility located
within a large MWC plant shall obtain and keep current either a provisional or
operator certification in accordance with ASME QRO-1-1994, incorporated by
reference in s.
NR 440.17(2) (h) 1., or an equivalent
state approved certification program.
(e) No owner or operator of an affected
facility may allow the affected facility located at a large MWC plant to
operate at any time without a certified shift supervisor, as provided under
par. (d), on duty at the affected facility. This requirement shall take effect
24 months after the date of startup of the affected facility or on and after
February 11, 1993, whichever is later.
(f) The owner or operator of an affected
facility located within a large MWC plant shall develop and update on a yearly
basis a site specific operating manual that shall, at a minimum, address the
following elements of MWC unit operation:
1.
Summary of the applicable standards under this section;
2. Description of basic combustion theory
applicable to an MWC unit;
3.
Procedures for receiving, handling and feeding MSW;
4. MWC unit startup, shutdown and malfunction
procedures;
5. Procedures for
maintaining proper combustion air supply levels;
6. Procedures for operating the MWC unit
within the standards established under this section;
7. Procedures for responding to periodic
upset or off specification conditions;
8. Procedures for minimizing particulate
matter carryover;
10. Procedures
for handling ash;
11. Procedures
for monitoring MWC unit emissions; and
12. Reporting and recordkeeping
procedures.
(g) The
owner or operator of an affected facility located within a large MWC plant
shall establish a program for reviewing the operating manual annually with each
person who has responsibilities affecting the operation of an affected facility
including, but not limited to, chief facility operators, shift supervisors,
control room operators, ash handlers, maintenance personnel and crane or load
handlers.
(h) The initial review of
the operating manual, as specified under par. (g), shall be conducted prior to
assumption of responsibilities affecting MWC unit operation by any person
required to undergo training under par. (g). Subsequent reviews of the manual
shall be carried out annually by each such person.
(i) The operating manual shall be kept in a
readily accessible location for all persons required to undergo training under
par. (g). The operating manual and records of training shall be available for
inspection by U.S. EPA or the department upon request.
(9) COMPLIANCE AND PERFORMANCE TESTING.
(a) The standards under this section apply at
all times except during periods of startup, shutdown or malfunction, provided
that the duration of the period of startup, shutdown or malfunction does not
exceed 3 hours per occurrence.
1. The startup
period commences when the affected facility begins the continuous burning of
MSW and does not include any warm up period when the affected facility is
combusting only a fossil fuel or other non-MSW fuel and no MSW is being
combusted.
2. Continuous burning is
the continuous, semicontinuous or batch feeding of MSW for purposes of waste
disposal, energy production or providing heat to the combustion system in
preparation for waste disposal or energy production. The use of MSW solely to
provide thermal protection of grate or hearth during the startup period is not
considered to be continuous burning.
(b) The procedures and test methods in this
paragraph shall be used to determine compliance with the emission limits for
particulate matter under sub. (3). The cited procedures and test methods are
contained in Appendix A of 40 CFR part 60, incorporated by reference in s.
NR 440.17.
1. Method 1
shall be used to select sampling site and number of traverse points.
2. Method 3 shall be used for gas
analysis.
3. Method 5 shall be used
for determining compliance with the particulate matter emission limit. The
minimum sample volume shall be 1.7 cubic meters (60 cubic feet). The probe and
filter holder heating systems in the sample train shall be set to provide a gas
temperature of 160° " 14 °C (320° " 25°F). An oxygen or carbon
dioxide measurement shall be obtained simultaneously with each Method 5
run.
4. For each Method 5 run, the
emission rate shall be determined using:
a.
Oxygen or carbon dioxide measurements;
b. Dry basis F factor; and
c. Dry basis emission rate calculation
procedures in Method 19.
5. An owner or operator may request that
compliance be determined using carbon dioxide measurements corrected to an
equivalent of 7% oxygen. The relationship between oxygen and carbon dioxide
levels for the affected facility shall be established during the initial
compliance test.
6. The owner or
operator of an affected facility shall conduct an initial compliance test for
particulate matter and opacity as required under s.
NR 440.08.
7.
Method 9 shall be used for determining compliance with the opacity
limit.
8. The owner or operator of
an affected facility shall install, calibrate, maintain and operate a
continuous opacity monitoring system (COMS) and record the output of the system
on a 6-minute average basis.
9.
Following the date the initial compliance test for particulate matter is
completed or is required to be completed under s.
NR 440.08 for
an affected facility located within a large MWC plant, the owner or operator
shall conduct a performance test for particulate matter on an annual basis (no
more than 12 calendar months following the previous compliance test).
(d) The procedures and test
methods in this paragraph shall be used to determine compliance with the limits
for dioxin/furan emissions under sub. (4). The cited procedures and test
methods are contained in Appendix A of 40 CFR part 60, incorporated by
reference in s.
NR 440.17.
1. Method 23
shall be used for determining compliance with the dioxin/furan emission limits.
The minimum sample time shall be 4 hours per test run.
2. The owner or operator of an affected
facility shall conduct an initial compliance test for dioxin/furan emissions as
required under s.
NR 440.08.
3.
Following the date of the initial compliance test or the date on which the
initial compliance test is required to be completed under s.
NR 440.08, the
owner or operator of an affected facility located within a large MWC plant
shall conduct a performance test for dioxin/furan emissions on an annual basis
(no more than 12 calendar months following the previous compliance
test).
5. An owner or operator may
request that compliance with the dioxin/furan emissions limit be determined
using carbon dioxide measurements corrected to an equivalent of 7% oxygen. The
relationship between oxygen and carbon dioxide levels for the affected facility
shall be established during the initial compliance test.
(e) The procedures and test methods in this
paragraph shall be used for determining compliance with the sulfur dioxide
limit under sub. (5). The cited procedures and test methods are contained in
Appendix A of 40 CFR part 60, incorporated by reference in s.
NR 440.17.
1. Method
19, sectio n 5.4, shall be used to determine the daily geometric average
percent reduction in the potential sulfur dioxide emission rate.
2. Method 19, sectio n 4.3, shall be used to
determine the daily geometric average sulfur dioxide emission rate.
3. An owner or operator may request that
compliance with the sulfur dioxide emissions limit be determined using carbon
dioxide measurements corrected to an equivalent of 7% oxygen. The relationship
between oxygen and carbon dioxide levels for the affected facility shall be
established during the initial compliance test.
4. The owner or operator of an affected
facility shall conduct an initial compliance test for sulfur dioxide as
required under s.
NR 440.08.
Compliance with the sulfur dioxide emission limit and percent reduction is
determined by using a CEMS to measure sulfur dioxide and calculating a 24-hour
daily geometric mean emission rate and daily geometric mean percent reduction
using Method 19 sections 4.3 and 5.4, as applicable, except as provided under
subd. 5.
5. For batch MWCs or MWC
units that do not operate continuously, compliance shall be determined using a
daily geometric mean of all hourly average values for the hours during the day
that the affected facility is combusting MSW.
6. The owner or operator of an affected
facility shall install, calibrate, maintain and operate a CEMS for measuring
sulfur dioxide emissions discharged to the atmosphere and record the output of
the system.
7. Following the date
of the initial compliance test or the date on which the initial compliance test
is required to be completed under s.
NR 440.08,
compliance with the sulfur dioxide emission limit or percent reduction shall be
determined based on the geometric mean of the hourly arithmetic average
emission rates during each 24-hour daily period measured between 12:00 midnight
and the following midnight using: CEMS inlet and outlet data, if compliance is
based on a percent reduction; or CEMS outlet data only if compliance is based
on an emission limit.
8. At a
minimum, valid CEMS data shall be obtained for 75% of the hours per day for 75%
of the days per month the affected facility is operated and combusting
MSW.
9. The 1-hour arithmetic
averages required under subd. 7. shall be expressed in parts per million dry
basis and used to calculate the 24-hour daily geometric mean emission rates.
The 1-hour arithmetic averages shall be calculated using the data points
required under s.
NR 440.13(5)
(b). At least 2 data points shall be used to
calculate each 1-hour arithmetic average.
10. All valid CEMS data shall be used in
calculating emission rates and percent reductions even if the minimum CEMS data
requirements of subd. 8. are not met.
11. The procedures under s.
NR 440.13
shall be followed for installation, evaluation and operation of the
CEMS.
12. The CEMS shall be
operated according to performance specifications 1, 2 and 3 of Appendix B of 40
CFR part 60, incorporated by reference in s.
NR 440.17.
13. Quarterly accuracy determinations and
daily calibration drift tests shall be performed in accordance with procedure 1
of Appendix F of 40 CFR part 60, incorporated by reference in s.
NR 440.17.
14. The span value of the CEMS at the inlet
to the sulfur dioxide control device is 125% of the maximum estimated hourly
potential sulfur dioxide emissions of the MWC unit and the span value of the
CEMS at the outlet of the sulfur dioxide control device is 50% of the maximum
estimated hourly potential sulfur dioxide emissions of the MWC unit.
15. When sulfur dioxide emissions data are
not obtained because of CEMS breakdowns, repairs, calibration checks and zero
and span adjustments, emissions data shall be obtained by using other
monitoring systems as approved by the department or Method 19 to provide, as
necessary, valid emission data for a minimum of 75% of the hours per day for
75% of the days per month the unit is operated and combusting MSW.
16. Not operating a sorbent injection system
for the sole purpose of testing in order to demonstrate compliance with the
percent reduction standards for MWC acid gases is not considered a physical
change in the method of operation under ch. NR 405, 406 or 408.
(f) The procedures and test
methods in this paragraph shall be used for determining compliance with the
hydrogen chloride limits under sub. (5). The cited procedures and test methods
are contained in Appendix A of 40 CFR part 60, incorporated by reference in s.
NR 440.17.
1. The
percentage reduction in the potential hydrogen chloride emissions (%PHCl) is
computed using the following formula:
See
PDF for diagram
where:
Ei is the potential hydrogen chloride emission rate
Eo is the hydrogen chloride emission rate measured at the
outlet of the acid gas control device
2. Method 26 or 26A shall be used for
determining the hydrogen chloride emission rate. The minimum sampling time for
Method 26 or 26A shall be one hour.
3. An owner or operator may request that
compliance with the hydrogen chloride emissions limit be determined using
carbon dioxide measurements corrected to an equivalent of 7% oxygen. The
relationship between oxygen and carbon dioxide levels for the affected facility
shall be established during the initial compliance test.
4. The owner or operator of an affected
facility shall conduct an initial compliance test for hydrogen chloride as
required under s.
NR 440.08.
5.
Following the date of the initial compliance test or the date on which the
initial compliance test is required under s.
NR 440.08, the
owner or operator of an affected facility located within a large MWC plant
shall conduct a performance test for hydrogen chloride on an annual basis and
no more than 12 calendar months following the previous compliance
test.
7. Not operating a sorbent
injection system for the sole purpose of testing in order to demonstrate
compliance with the percent reduction standards for MWC acid gases is not
considered a physical change in the method of operation under ch. NR 405, 406
or 408.
(g) The
procedures and test methods in this paragraph shall be used to determine
compliance with the nitrogen oxides limit under sub. (6). The cited procedures
and test methods are contained in Appendix A of 40 CFR part 60, incorporated by
reference in s.
NR 440.17.
1. Method
19, sectio n 4.1, shall be used for determining the daily arithmetic average
nitrogen oxides emission rate.
2.
An owner or operator may request that compliance with the nitrogen oxides
emissions limit be determined using carbon dioxide measurements corrected to an
equivalent of 7% oxygen. The relationship between oxygen and carbon dioxide
levels for the affected facility shall be established during the initial
compliance test.
3. The owner or
operator of an affected facility subject to the nitrogen oxides limit under
sub. (6) shall conduct an initial compliance test for nitrogen oxides as
required under s.
NR 440.08.
Compliance with the nitrogen oxides emission standard shall be determined by
using a CEMS for measuring nitrogen oxides and calculating a 24-hour daily
arithmetic average emission rate using Method 19, section 4.1, except as
specified under subd. 4.
4. For
batch MWCs or MWCs that do not operate continuously, compliance shall be
determined using a daily arithmetic average of all hourly average values for
the hours during the day that the affected facility is combusting
MSW.
5. The owner or operator of an
affected facility subject to the nitrogen oxides emissions limit under sub. (6)
shall install, calibrate, maintain and operate a CEMS for measuring nitrogen
oxides discharged to the atmosphere and record the output of the
system.
6. Following the initial
compliance test or the date on which the initial compliance test is required to
be completed under s.
NR 440.08,
compliance with the emission limit for nitrogen oxides required under sub. (6)
shall be determined based on the arithmetic average of the arithmetic average
hourly emission rates during each 24-hour daily period measured between 12:00
midnight and the following midnight using CEMS data.
7. At a minimum, valid CEMS data shall be
obtained for 75% of the hours per day for 75% of the days per month the
affected facility is operated and combusting MSW.
8. The 1-hour arithmetic averages required by
subd. 6. shall be expressed in parts per million volume dry basis and used to
calculate the 24-hour daily arithmetic average emission rates. The 1-hour
arithmetic averages shall be calculated using the data points required under s.
NR 440.13(2). At least 2 data points
shall be used to calculate each 1-hour arithmetic average.
9. All valid CEMS data shall be used in
calculating emission rates even if the minimum CEMS data requirements of subd.
7. are not met.
10. The procedures
under s.
NR 440.13
shall be followed for installation, evaluation and operation of the
CEMS.
11. Quarterly accuracy
determinations and daily calibration drift tests shall be performed in
accordance with procedure 1 of Appendix F of 40 CFR part 60, incorporated by
reference in s.
NR 440.17.
12. When nitrogen oxides emissions data are
not obtained because of CEMS breakdowns, repairs, calibration checks and zero
and span adjustments, emission data calculations to determine compliance shall
be made using other monitoring systems as approved by the department or Method
19 to provide, as necessary, valid emission data for a minimum of 75% of the
hours per day for 75% of the days per month the unit is operated and combusting
MSW.
(h) The following
procedures shall be used for determining compliance with the operating
standards under sub. (7):
1. Compliance with
the carbon monoxide emission limits in sub. (7) (a) shall be determined using a
4-hour block arithmetic average for all types of affected facilities except
mass burn rotary waterwall MWCs, RDF stokers and spreader stoker and RDF mixed
fuel-fired combustors.
2. For
affected mass burn rotary waterwall MWCs, RDF stokers and spreader stoker and
RDF mixed fuel-fired combustors, compliance with the carbon monoxide emission
limits in sub. (7) (a) shall be determined using a 24-hour daily arithmetic
average.
3. The owner or operator
of an affected facility shall install, calibrate, maintain and operate a CEMS
for measuring carbon monoxide at the combustor outlet and record the output of
the system.
4. The 4-hour and
24-hour daily arithmetic averages in subds. 1. and 2. shall be calculated from
1-hour arithmetic averages expressed in parts per million by volume dry basis.
The 1-hour arithmetic averages shall be calculated using the data points
generated by the CEMS. At least 2 data points shall be used to calculate each
1-hour arithmetic average.
5. An
owner or operator may request that compliance with the carbon monoxide emission
limit be determined using carbon dioxide measurements corrected to an
equivalent of 7% oxygen. The relationship between oxygen and carbon dioxide
levels for the affected facility shall be established during the initial
compliance test.
6. The following
procedures shall be used to determine compliance with load level requirements
under sub. (7) (b):
a. The owner or operator
of an affected facility with steam generation capability shall install,
calibrate, maintain and operate a steam flow meter or a feedwater flow meter,
measure steam or feedwater flow in kilograms per hour or pounds per hour on a
continuous basis, and record the output of the monitor. Steam or feedwater flow
shall be calculated in 4-hour block arithmetic averages.
b. The method contained in ASME Power Test
Codes: Test Code for Steam Generating Units, PTC 4.1 (1964) section 4,
incorporated by reference in s.
NR 440.17(2) (h) 2., shall be used for
calculating the steam or feedwater flow required under subd. 6. a. The
recommendations of Instruments and Apparatus: Measurement of Quantity of
Materials, ASME Interim Supplement 19.5 (1971) chapter 4, incorporated by
reference in s.
NR 440.17(2) (h) 3., shall be followed
for design, construction, installation, calibration and use of nozzles and
orifices except as specified in subd. 6. c.
c. Measurement devices such as flow nozzles
and orifices are not required to be recalibrated after they are
installed.
d. All signal conversion
elements associated with steam or feedwater flow measurements shall be
calibrated according to the manufacturer's instructions before each dioxin or
furan compliance and performance test, and at least once per
year.
7. To determine
compliance with the maximum particulate matter control device temperature
requirements under sub. (7) (c), the owner or operator of an affected facility
shall install, calibrate, maintain and operate a device for measuring
temperature of the flue gas stream at the inlet to the final particulate matter
control device on a continuous basis and record the output of the device.
Temperature shall be calculated in 4-hour block arithmetic averages.
8. Maximum demonstrated MWC unit load shall
be determined during the initial compliance test for dioxins/furans and each
subsequent performance test during which compliance with the dioxin/furan
emission limit under sub. (4) is achieved. Maximum demonstrated MWC unit load
shall be the maximum 4- hour arithmetic average load achieved during the most
recent test during which compliance with the dioxin/furan limit was
achieved.
9. The maximum
demonstrated particulate matter control device temperature shall be determined
during the initial compliance test for dioxins/furans and each subsequent
performance test during which compliance with the dioxin/furan emission limit
under sub. (4) is achieved. Maximum demonstrated particulate matter control
device temperature shall be the maximum 4-hour arithmetic average temperature
achieved at the final particulate matter control device inlet during the most
recent test during which compliance with the dioxin/furan limit was
achieved.
10. At a minimum, valid
CEMS data for carbon monoxide, steam or feedwater flow and particulate matter
control device inlet temperature shall be obtained 75% of the hours per day for
75% of the days per month the affected facility is operated and combusting
MSW.
11. All valid data shall be
used in calculating the parameters specified under this paragraph even if the
minimum data requirements of subd. 10. are not met.
12. Quarterly accuracy determinations and
daily calibration drift tests for carbon monoxide CEMS shall be performed in
accordance with procedure 1 of Appendix F of 40 CFR part 60, incorporated by
reference in s.
NR 440.17.
(j) The following procedures shall be used
for calculating MWC unit capacity as defined under sub. (2):
1. For MWC units capable of combusting MSW
continuously for a 24-hour period, MWC unit capacity in megagrams per day or
tons per day of MSW combusted shall be calculated based on 24 hours of
operation at the maximum design charging rate. The design heating values under
subd. 4. shall be used in calculating the design charging rate.
2. For batch MWC units, MWC unit capacity in
megagrams per day or tons per day of MSW combusted shall be calculated as the
maximum design amount of MSW that can be charged per batch multiplied by the
maximum number of batches that could be processed in a 24-hour period. The
maximum number of batches that could be processed in a 24-hour period is
calculated as 24 hours divided by the design number of hours required to
process one batch of MSW, and may include fractional batches. The design
heating values under subd. 4. shall be used in calculating the MWC unit
capacity in megagrams per day or tons per day of MSW.
Note: For example, if one batch requires 16 hours then
24/16 or 1.5 batches could be combusted in a 24-hour period.
4. MWC unit capacity shall be calculated
using a design heating value of 10,500 kilojoules per kilogram (4,500 Btu per
pound) for all MSW.
(10c) DAILY RECORDS.
The owner or operator of an affected facility located within a small or large
MWC plant and subject to the standards under sub. (3), (4), (5), (6) or (7)
shall maintain records of the following information for each affected facility
for a period of at least 2 years:
(a) Calendar
date.
(b) The emission rates and
parameters measured using CEMS as follows:
1.
The following measurements shall be recorded in computer readable format and on
paper:
a. All 6-minute average opacity levels
required under sub. (9) (b).
b. All
1-hour average sulfur dioxide emission rates at the inlet and outlet of the
acid gas control device if compliance is based on a percent reduction or at the
outlet only if compliance is based on the outlet emission limit as specified
under sub. (9) (e).
c. All 1-hour
average nitrogen oxides emission rates as specified under sub. (9)
(g).
d. All 1-hour average carbon
monoxide emission rates, MWC unit load measurements and particulate matter
control device inlet temperatures as specified under sub. (9) (h).
2. The following average rates
shall be computed and recorded:
a. All 24-hour
daily geometric average percent reductions in sulfur dioxide emissions and all
24-hour daily geometric average sulfur dioxide emission rates as specified
under sub. (9) (e).
b. All 24-hour
daily arithmetic average nitrogen oxides emission rates as specified under sub.
(9) (g).
c. All 4-hour block or
24-hour daily arithmetic average carbon monoxide emission rates, as applicable,
as specified under sub. (9) (h).
d.
All 4-hour block arithmetic average MWC unit load levels and particulate matter
control device inlet temperatures as specified under sub. (9) (h).
(c) Identification of
the operating days when any of the average emission rates, percent reductions
or operating parameters specified under par. (b) 2. or the opacity level
exceeded the applicable limits with reasons for such exceedances as well as a
description of corrective actions taken.
(d) Identification of operating days for
which the minimum number of hours of sulfur dioxide or nitrogen oxides
emissions or operational data, including carbon monoxide emissions, unit load
or particulate matter control device temperature, have not been obtained,
including reasons for not obtaining sufficient data and a description of
corrective actions taken.
(e)
Identification of the times when sulfur dioxide or nitrogen oxides emission or
operational data, including carbon monoxide emissions, unit load or particulate
matter control device temperature, have been excluded from the calculation of
average emission rates or parameters and the reasons for excluding
data.
(f) The results of daily
sulfur dioxide, nitrogen oxides and carbon monoxide CEMS drift tests and
accuracy assessments as required under procedure 1 of Appendix F of 40 CFR part
60, incorporated by reference in s.
NR 440.17.
(g) The results of all annual performance
tests conducted to determine compliance with the particulate matter,
dioxin/furan and hydrogen chloride limits. For all annual dioxin/furan tests,
the maximum demonstrated MWC unit load and maximum demonstrated particulate
matter control device temperature shall be recorded along with supporting
calculations.