(1) REQUIREMENT TO
APPLY.
(a)
Duty to apply.
1. The designated representative of any
source with an affected unit shall submit a complete acid rain portion of an
operation permit application by the applicable deadline in pars. (b) and (c),
and the owners and operators of the source and any affected unit at the source
may not operate the source or unit without a permit or permit application
meeting the requirements of sub. (3) that states its acid rain program
requirements.
2. The designated
representative of any source with an affected unit subject to s.
NR 409.065 shall submit, by the applicable deadline under
par. (c) 2., a complete acid rain portion of an operation permit application
or, if the unit is covered by an acid rain portion of an operation permit, a
complete permit revision that includes a complete compliance plan for
NOx emissions covering the unit.
Note: Application forms may be obtained from the regional and
area offices of the department or from the Wisconsin Department of Natural
Resources, Bureau of Air Management, PO Box 7921, Madison WI 53707-7921,
Attention: Operation permits.
(b)
Deadlines.
1. For any source with an existing unit
described under s.
NR 409.01(1) (a)
2., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department on or before January 1, 1996.
2. For any source with a new unit described
under s.
NR 409.01(1) (a)
3. a., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department at least 24 months before the later of
January 1, 2000 or the date on which the unit commences operation.
3. For any source with a unit described under
s.
NR 409.01(1) (a)
3. b., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department at least 24 months before the later of
January 1, 2000 or the date on which the unit begins to serve a generator with
a nameplate capacity greater than 25 MWe.
4. For any source with a unit described under
s.
NR 409.01(1) (a)
3. c., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department at least 24 months before the later of
January 1, 2000 or the date on which the auxiliary firing commences
operation.
5. For any source with a
unit described under s.
NR 409.01(1) (a)
3. d., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department before the later of January 1, 1998 or
March 1 of the year following the 3 calendar year periods in which the unit
sold to a utility power distribution system an annual average of more than
one-third of its potential electrical output capacity and more than 219,000
MWe-hrs actual electric output, on a gross basis.
6. For any source with a unit described under
s.
NR 409.01(1) (a)
3. e., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department before the later of January 1, 1998 or
March 1 of the year following the calendar year in which the facility fails to
meet the definition of qualifying facility.
7. For any source with a unit described under
s.
NR 409.01(1) (a)
3. f., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department before the later of January 1, 1998 or
March 1 of the year following the calendar year in which the facility fails to
meet the definition of an independent power production facility.
8. For any source with a unit described under
s.
NR 409.01(1) (a)
3. g., the designated representative shall
submit a complete acid rain portion of an operation permit application
governing the unit to the department before the later of January 1, 1998 or
March 1 of the year following the 3 calendar year periods in which the
incinerator consumed 20% or more fossil fuel, on a Btu basis.
Note: Early election units were required to submit an
application to U.S. EPA not later than January 1, 1997. For a Phase I or Phase
II unit with a Group 1 or Group 2 boiler, the designated representative was
required to submit a complete permit application and compliance plan for
NOx emissions covering the unit in Phase II to the
department and U.S. EPA not later than January 1, 1998.
(c)
Duty to
reapply.
1. The designated
representative shall submit a complete acid rain portion of an operation permit
application for each source with an affected unit at least 6 months before the
permit expires.
2. The designated
representative of any source with an affected unit subject to s.
NR 409.065 shall submit a complete acid rain portion of
an operation permit application, including a complete compliance plan for NOx
emissions covering the unit, in accordance with par. (d) and with the deadlines
in subd. 1.
(d)
Number of copies.
1. The
original and 3 copies of all permit applications shall be submitted to the
department.
2. The original and 3
copies of the compliance plan for NOx emissions for
Phase II shall be submitted to the department, and one copy of the compliance
plan for NOx emissions submitted to U.S. EPA
headquarters, acid rain division.
(e)
Multiple applications.
Where 2 or more affected units are located at a source, the department may
allow the designated representative of the source to submit, under par. (a) or
(c), 2 or more acid rain portions of operation permit applications covering the
units at the source, provided that each affected unit is covered by one and
only one application.
Note: Application forms may be obtained from the regional
offices of the department or from the Wisconsin Department of Natural
Resources, Bureau of Air Management, PO Box 7921, Madison WI 53707-7921,
Attention: Operation permits.