(1) APPLICABILITY.
(a) Each of the following emissions units is
an affected unit and any source that includes such a unit shall be an affected
source subject to the requirements of the acid rain program:
1. A unit listed in Table 1 of
40 CFR
73.10(a).
2. An existing unit that is identified in
Table 2 or 3 of
40 CFR
73.10 and any other existing utility unit,
except a unit excluded under par. (b).
3. A utility unit, except a unit excluded
under par. (b), that:
a. Is a new
unit.
b. Did not serve a generator
with a nameplate capacity greater than 25 MWe on November 15, 1990 but serves
such a generator after November 15, 1990.
c. Was a simple cycle combustion turbine on
November 15, 1990 but adds or uses auxiliary firing after November 15,
1990.
d. Was an exempt cogeneration
facility under par. (b) 4. but during any 3 calendar year period after November
15, 1990 sold, to a utility power distribution system, an annual average of
more than one-third of its potential electrical out-put capacity and more than
219,000 MWe-hrs electric output, on a gross basis.
e. Was an exempt qualifying facility under
par. (b) 5. but, at any time after the later of November 15, 1990 or the date
the facility commences commercial operation, fails to meet the definition of a
qualifying facility as defined in s.
NR 409.02.
f.
Was an exempt independent power production facility under par. (b) 6. but, at
any time after the later of November 15, 1990 or the date the facility
commences commercial operation, fails to meet the definition of independent
power production facility.
g. Was
an exempt solid waste incinerator under par. (b) 7. but during any 3 calendar
year period after November 15, 1990 consumes 20% or more of the total heat
input, expressed on a Btu basis, as fossil fuel.
(b) The following types of utility
units are exempt from the requirements of this chapter and the acid rain
program:
1. A simple cycle combustion turbine
that commenced operation before November 15, 1990.
2. Any unit that commenced commercial
operation before November 15, 1990 and that did not, as of November 15, 1990,
and does not serve a generator with a nameplate capacity of greater than 25
MWe.
3. Any unit that, during 1985,
did not serve a generator that produced electricity for sale and that did not,
as of November 15, 1990, and does not serve a generator that produces
electricity for sale.
4. A
cogeneration unit which:
a. For a unit that
commenced construction on or prior to November 15, 1990, was constructed for
the purpose of supplying equal to or less than one-third its potential
electrical output capacity or equal to or less than 219,000 MWe-hrs actual
electric output on an annual basis to any utility power distribution system for
sale on a gross basis. If the purpose of construction is not known, it is
presumed to be consistent with the actual operation from 1985 to 1987. However,
if in any 3 calendar year period after November 15, 1990, the unit sells to a
utility power distribution system an annual average of more than one-third of
its potential electrical output capacity and more than 219,000 MWe-hrs actual
electric output on a gross basis, that unit is an affected unit, subject to the
requirements of this chapter and the acid rain program.
b. For a unit that commenced construction
after November 15, 1990, supplies equal to or less than one-third its potential
electrical output capacity or equal to or less than 219,000 MWe-hrs actual
electric output on an annual basis to any utility power distribution system for
sale on a gross basis. However, if in any 3 calendar year period after November
15, 1990, the unit sells to a utility power distribution system an annual
average of more than one-third of its potential electrical output capacity and
more than 219,000 MWe-hrs actual electric output on a gross basis, that unit is
an affected unit, subject to the requirements of this chapter and the acid rain
program.
5. A qualifying
facility that:
a. Has, as of November 15,
1990, one or more qualifying power purchase commitments to sell at least 15% of
its total planned net output capacity; and
b. Consists of one or more units designated
by the owner or operator with total installed net output capacity not exceeding
130% of the total planned net output capacity. If the emissions rates of the
units are not the same, the administrator may exercise discretion to designate
which units are exempt.
6. An independent power production facility
that:
a. Has, as of November 15, 1990, one or
more qualifying power purchase commitments to sell at least 15% of its total
planned net output capacity; and
b.
Consists of one or more units designated by the owner or operator with total
installed net output capacity not exceeding 130% of its total planned net
output capacity. If the emissions rates of the units are not the same, the
administrator may exercise discretion to designate which units are
exempt.
7. A solid waste
incinerator, if more than 80%, on a Btu basis, of the annual fuel consumed at
the incinerator is other than fossil fuels. For a solid waste incinerator which
began operation before January 1, 1985, the average annual fuel consumption of
non-fossil fuels for calendar years 1985 to 1987 shall be greater than 80% for
an incinerator to be exempt. For a solid waste incinerator which began
operation after January 1, 1985, the average annual fuel consumption of
non-fossil fuels for the first 3 years of operation shall be greater than 80%
for an incinerator to be exempt. If, during any 3 calendar year period after
November 15, 1990, the incinerator consumes 20% or more of the total heat
input, expressed on a Btu basis, as fossil fuel, the incinerator is an affected
source under this chapter and the acid rain program.
8. A unit that is not a utility
unit.
9. A unit for which an
exemption under s.
NR 409.04 or 409.05 is in 409.055 effect. Although
the unit is not an affected unit, the unit shall be subject to the requirements
of s.
NR 409.04, 409.05 or 409.055, as applicable to the
exemption.
(c) For a
determination of applicability, a certifying official of an owner or operator
of any unit may petition the administrator under
40
CFR 72.6(c). The
administrator's determination of applicability shall be binding upon the
department, unless the petition is found to have contained significant errors
or omissions.
(d) All references to
40 CFR part 72, 40 CFR part 73, 40 CFR part 74, 40 CFR part 75, 40 CFR part 76, 40 CFR part 77 and 40 CFR part 78 in this chapter mean those parts of the code
of federal regulations as in effect on July 1, 1998, except that in the case of
CFR appendices incorporated by reference in ch. NR 484, if a more recent date
is specified in the applicable section of ch. NR 484, that date shall
apply.