Wisconsin Administrative Code
Department of Natural Resources
NR 300-399 - Environmental Protection - Water Regulation
Chapter NR 335 - Municipal Dam Grant Program
Section NR 335.08 - Eligible and ineligible costs
Universal Citation: WI Admin Code ยง NR 335.08
Current through August 26, 2024
(1) ELIGIBLE COSTS. The following project costs, whether incurred under contract or in the form of salaries and benefits, may be reimbursed under this chapter, if the grant is awarded:
(a) Actual and reasonable engineering
costs incurred in preparing the studies and application form required under s.
NR 335.07(2) (e) and
(f);
(b) Actual and reasonable engineering costs
incurred in preparing plans and specifications as required in s.
NR 335.06(4), the operation, inspection
and maintenance plan, and the emergency action plan;
(c) Actual and reasonable construction costs
incurred in the repair, modification or abandonment of the dam, including labor
and materials;
(d) Actual and
reasonable engineering costs involved in the on-site inspection of the repair,
modification or abandonment of the dam. On-site inspection by an engineer
registered in the state of Wisconsin is required, at a minimum, during critical
stages of construction and could be required full time for certain
projects.
(e) Actual and reasonable
costs for activities other than the maintenance, repair or modification of the
dam (structural alternative) only if the cost of that activity is less than the
cost of the structural alternative.
(2) INELIGIBLE COSTS. Ineligible costs include:
(a) Costs incurred prior to August 9,
1989;
(b) The cost of materials and
labor for installation or repair of items directly associated with
hydroelectric power facilities at the dam;
(c) Costs incurred prior to the date of the
state grant award except engineering costs as provided in sub. (1) or
construction costs for a project that was under department orders, was approved
by the department and was undertaken as emergency repairs or modifications to a
high or significant hazard dam. Construction work shall have started within 1
year prior to the grant application deadline;
(d) Costs of routine maintenance including,
but not limited to, mowing grass, painting signs and debris removal;
(e) Costs of equipment necessary for routine
maintenance of the dam;
(f) Costs
for which payment for a dam abandonment and removal project has been or will be
received under another state or federal cost sharing or grant program or from
another municipality or any other outside funding source;
(g) Costs attributable to the correction of
errors or deficiencies in construction funded under this chapter due to failure
to comply with department approved construction plans and
specifications.
(3) ALLOCATION OF COSTS. Total project costs may be allocated between eligible and ineligible costs using one of the following methods:
(a)
Unit cost method. When
the unit cost method is used, costs for individual work items shall be prorated
between eligible and ineligible portions of the project based on an equal cost
per unit.
(b)
Project cost
method. When the project cost method is used, eligible project costs
shall be based on engineering costs plus the cost of construction reflected in
the contractor's billings to the owner. Owners using this method shall submit
the contractor's itemized billings showing the breakdown of eligible work
items.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.