(1) ELIGIBLE ACTIVITIES. The following activities, in priority order, are eligible for funding under this section:
(a) Acquisition
and removal of structures which, due to zoning restrictions, cannot be rebuilt
or repaired.
(b) Acquisition and
removal of structures in the 100-year floodplain.
(c) Acquisition and removal of repetitive
loss or substantially damaged structures.
(d) Acquisition and removal of other flood
damaged structures.
(e)
Floodproofing and elevation of structures.
(f) Riparian restoration projects, including
removal of dams and other artificial obstructions, restoration of fish and
native plant habitat, erosion control and streambank restoration
projects.
(g) Acquisition of vacant
land, or perpetual conservation or flowage easements to provide additional
flood storage or to facilitate natural or more efficient flood flows.
(h) Construction of structures for the
collection, detention, retention, storage and transmission of stormwater and
groundwater for flood control and riparian restoration projects.
(i) Preparation of flood insurance studies
and other flood mapping projects.
(2) INELIGIBLE ACTIVITIES. The following activities are not eligible for funding under this chapter:
(a) Dam repair and operation.
(b) Design, installation, operation or
maintenance of sanitary sewers, treatment plants or onsite sewerage
systems.
(c) Projects which would
adversely affect a watercourse by causing increases in flood heights,
velocities, sedimentation or erosion, reducing the amount or complexity of fish
and wildlife habitat, reducing natural shore cover, or restricting navigation,
or any other negative impact, except temporary impacts caused by dam removal or
other approved restoration activities.
(d) Projects which would dredge or channelize
a stream or line a natural streambed with impervious materials.
(e) Projects which conflict with land use,
watershed or other resource management plans.
(f) Projects or applicants which are not
compliant with minimum state floodplain management requirements, as enumerated
in ch. NR 116, or with minimum national flood insurance program requirements,
as enumerated in 44 CFR Parts 59 - 78.
(g) Creation or enhancement of stormwater
management plans.
(h) Projects for
the purchase, installation or operation of mechanical pumping
systems.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.