(1) PLAN FORMAT. All solid waste management plans shall be developed and written according to the planning criteria outlined in s. NR 185.07.
(2) PRELIMINARY SUBMITTAL. Entities shall make a preliminary submittal to the department to include 3 draft copies of the material required in s. NR 185.07(1), (2), (3), (4) and (5) prior to completion of the remaining portions of s. NR 185.07. The department shall review and comment on the submittal within 90 days of receipt.
(3) FINAL REVIEW. An entity seeking final department review and approval of a plan shall submit a total of 4 copies of the following package to the department and one copy to the appropriate regional planning commission or other planning agency for their comment as to whether the plan is in conflict with any plans adopted by the agency.
(4) APPROVAL. Within 90 days after submittal, the department shall approve or disapprove the plan. The department may issue written plan approvals that are subject to completion of conditions. If the department finds that portions of a plan are inaccurate, incomplete, or inconsistent with the requirements or intent of this chapter, it may disapprove the plan, stating the reasons for disapproval.