Section NR 162.14 - Amendments to a financial assistance agreement
Universal Citation: WI Admin Code ยง NR 162.14
Current through August 26, 2024
(1) ADDITIONAL FUNDING.
(a)
General.
1. 'Additional assistance at end of project.'
The department may issue an amendment to a financial assistance agreement to
provide additional financial assistance for eligible project costs incurred
beyond the amount specified in the original financial assistance agreement. The
department may process a request to provide additional financial assistance for
a project only after the total remaining costs to complete the project can be
reasonably determined.
2.
'Consistent with scope.' To be eligible for additional financial assistance,
any changes in the project necessitating the amendment must be consistent with
the objectives and scope of the project as described in the original financial
assistance agreement.
3. 'Plans and
specifications approval.' If there are changes in the project that require
department approval of plans and specifications, the municipality shall obtain
department approval prior to the amendment loan closing. Changes that
necessitate an amendment must be due to unforeseen circumstances or approvable
change orders to a project construction contract.
4. 'New financial assistance agreement.' An
amendment shall be in the form of a new financial assistance agreement tied to
the original project through the budget and project description. The department
and the DOA shall determine the appropriate interest rate for the amendment
based on the market interest rate in effect on the date of the municipality's
meeting at which they pass the related bond resolution.
5. 'Debt coverage requirements.' The
municipality must meet debt coverage requirements for the additional financial
assistance.
(b)
Applicability. Additional financial assistance under par. (a)
for a scored project is subject to all of the following:
1. 'Availability of funds as determined under
s. 281.59, Stats.' If there are
sufficient loan funds available, a municipality may receive loan funds for
additional project costs incurred that cause the total eligible project costs
to be greater than the amount provided in the original financial assistance
agreement. The loan interest rate and loan maturity date shall be determined by
the department and DOA.
2. 'No
principal forgiveness.' The department shall not provide additional principal
forgiveness funds in the amendment to the financial assistance
agreement.
(c)
Requesting funds. A municipality may request financial
assistance for additional project costs using any of the following options:
1. 'Request in writing.' The municipality
shall submit a written request to the department that justifies the need for
additional financial assistance and details the additional eligible costs. A
revised budget shall be submitted with the request indicating in one column the
line item totals in the financial assistance agreement, in a second column the
requested additional costs, and in a third column the total project costs
requested to be funded through the CWFP via an amendment to the original
financial assistance agreement. If there are other funding sources
participating in the project, the revised budget shall indicate all funding
changes applicable to the additional financial assistance being requested. All
costs in the revised budget shall be assigned to the appropriate budget line
items from which disbursement will be requested.
2. 'Electronic submittal.' The department may
require the written request for an amendment to be submitted as an email
message with an attachment, as input into the department's online application
system, or by other appropriate means determined by the
department.
(d)
Plans and specifications. A municipality shall submit to the
department any plans and specifications required for changes in the project
that necessitate the amendment to the financial assistance agreement. The
department shall issue an amendment for the additional project costs only after
the department approves any facilities plans or plans and specifications
required for the work related to the additional costs.
(e)
Notice of intent to
apply. A new notice of intent to apply for funding as described under
s.
NR 162.05 (1) is not required for purposes of
requesting a financial assistance agreement amendment.
(2) EFFECTIVE DATE. A financial assistance agreement amendment is effective when executed by all parties to the agreement.
Disclaimer: These regulations may not be the most recent version. Wisconsin may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.