(1) GENERAL. In ss. NR 151.241 to 151.249, "post-construction site" means a construction site subject to regulation under this subchapter, after construction is completed and final stabilization has occurred.
(2) APPLICABILITY. Sections NR 151.241 to 151.249 apply to a transportation facility post-construction site that is or was subject to the construction performance standards of s. NR 151.23, except any of the following:
(3) STORM WATER MANAGEMENT PLAN. The responsible party under s. NR 151.22 shall develop and implement a written storm water management plan for each transportation facility post-construction site and shall incorporate the requirements of ss. NR 151.242 to 151.249.
(4) MAINTENANCE OF EFFORT. For non-highway transportation facility redevelopment sites and highway reconstruction where the redevelopment or reconstruction will be replacing older development or highway that was subject to post-construction performance standards of this chapter in effect on or after October 1, 2004, the responsible party shall meet the total suspended solids reduction, peak flow control, infiltration, and protective areas standards applicable to the older development or highway, or meet the redevelopment or highway reconstruction standards of ss. NR 151.242 to 151.249, whichever are more stringent.