(1) APPLICABILITY. Except as provided under sub. (2), this section applies to all of the following:
Note: Land disturbing construction sites of less than one acre are not regulated under subch. III of ch. NR 216 unless designated by the department under s. NR 216.51 (3).
(2) EXEMPTIONS. This section does not apply to the following:
(3) RESPONSIBLE PARTY. The landowner of the construction site or other person contracted or obligated by other agreement with the landowner to implement and maintain construction site BMPs is the responsible party and shall comply with this section.
(4) REQUIREMENTS. Erosion and sediment control practices at each site where land disturbing construction activity is to occur shall be used to prevent or reduce all of the following:
Note: In accordance with subch. V, the department has developed technical standards to help meet the construction site performance standards. These technical standards are available from the department at dnr.wi.gov.
(5) LOCATION. BMPs shall be located so that treatment occurs before runoff enters waters of the state.
(6) IMPLEMENTATION. The BMPs used to comply with this section shall be implemented as follows: