(1) At least 30 days prior to the proposed date of commencement of drillhole construction, the explorer shall submit an application for drillhole construction approval to the department. The application shall be submitted as an original, in reproducible form, and 5 copies. The explorer shall, at the same time, submit one copy of the application to the county clerk of the county in which the drilling is proposed to occur. The application shall contain the following information:
(2) If the department finds that the proposed drillhole location, construction, abandonment, and site reclamation will adequately protect the waters of the state, it shall grant the approval. If it finds that the exploration as proposed will not provide such protection, the department may grant an approval subject to such conditions as it deems necessary to provide such protection, or it may deny the approval if it determines that such protection cannot be provided. Written approvals of drillhole construction plans shall be issued, issued with conditions or denied within 20 business days after the department receives a complete application as described in sub. (1). If it is determined, pursuant to ch. NR 150 that an environmental impact statement is required to comply with s. 1.11, Stats., this time limit shall be extended. Approval of drillhole construction plans shall terminate one year after date of issuance, if such construction has not commenced.