Wisconsin Administrative Code
Department of Agriculture, Trade and Consumer Protection
ATCP 20-54 - Agricultural Resource Management
Chapter ATCP 33 - Fertilizer And Pesticide Bulk Storage
Subchapter II - Construction Plans and Siting
Section ATCP 33.10 - Construction plans
Current through August 26, 2024
(1) FILING REQUIRED. At least 21 days before an operator constructs or substantially alters a structure at a storage facility, the operator shall file all of the following with the department:
Note: Subsection (1) does not apply to the routine repair or maintenance of an existing structure. See s. ATCP 33.01(34). This chapter does not require an operator to take soil samples before the operator constructs or substantially alters a structure. However, an operator may wish to do so in order to maintain cost reimbursement eligibility under s. ATCP 35.04.
(2) DISCRETIONARY REVIEW. The department may review and comment on the design specifications filed under sub. (1). The department is not required to review, approve or comment on the design specifications. A failure to comment does not signify approval. An operator is not required to obtain the department's approval for a proposed construction or alteration, but is required to comply with this chapter.
(3) DISCRETIONARY INSPECTION. The department may inspect a construction or alteration under sub. (1).
(4) CONSTRUCTION CONFORMING TO PLAN. An operator may not, without prior written notice to the department, deviate from design specifications filed under sub. (1).