West Virginia Code of State Rules
Agency 167 - Infrastructure And Jobs Development Council
Title 167 - LEGISLATIVE RULE WEST VIRGINIA INFRASTRUCTURE & JOBS DEVELOPMENT COUNCIL
Series 167-01 - Infrastructure and Jobs Development Council
Section 167-1-3 - Projects
Current through Register Vol. XLI, No. 52, December 27, 2024
3.1. Project Review. Prior to applying for or receiving any loan, loan guarantee, grant or other funding assistance for a project from any State infrastructure agency, a project sponsor shall submit a preliminary application on the Council's form and must receive the Council's recommendation.
3.2. Exemption from Review. The Council shall exempt the following from the preliminary application review process:
3.3. Preliminary Application Filing. A project sponsor may file a preliminary application with the Council, at the offices of the Water Development Authority, at any time: Provided, that the preliminary application shall not be formally accepted until it is presented to the Council at the next regularly scheduled Council meeting, at which time the thirty-day review period begins. The Water Development Authority may, but is not required to, circulate the preliminary application to Council members or Council committees in advance of the meeting.
3.4. Preliminary Application Review. Within thirty days of the Council's formal acceptance of a complete preliminary application from a project sponsor, the Council shall either recommend that the project sponsor seek funding or that the project sponsor not seek funding for the project or request additional information if necessary to make a determination.
3.5. Approval. If the Council determines that the project is consistent with the Act, it shall make a written recommendation for the project financing stating:
3.6. Funding of Project. The Council may provide that if the recommended funding sources have not or cannot dedicate money for the project, the project sponsor shall submit a supplement to its preliminary application to the Council for consideration of alternate funding from another funding source or the Infrastructure Fund.
3.7. Denial. If the Council determines that the project is not eligible for funding assistance from any State infrastructure agency, or that the project is not otherwise an appropriate or prudent investment of State funds, it shall recommend that the project sponsor not seek funding from any State infrastructure agency.
3.8. Recommendations. The Council shall provide a copy of its recommendation, together with a copy of the preliminary application, if not previously provided, to all State infrastructure agencies which are listed in the recommendation as recommended funding sources.