Section 479-10-565 - Project phases for the complete streets program

Universal Citation: WA Admin Code 479-10-565

Current through Register Vol. 24-06, March 15, 2024

(1) Complete streets program projects will have five phases. Each phase will require specific documentation as described below and each phase must be approved before the applicant agency is eligible to receive the related funding:

(a) Application phase;

(b) Design phase;

(c) Bid authorization phase;

(d) Bid award phase; and

(e) Project closeout phase.

(2) A manually signed copy of a contract or any amendments, statement of work, or other transaction documents delivered by email shall be deemed to have the same legal effect as delivery of an original signed copy.

(3) An electronic signature shall have the same force and effect as a manual signature on all agreements, forms, and other documents submitted in support of a project under this chapter. For purposes of this section, an "electronic signature" has the same meaning as in RCW 1.80.010(10).

TIB will provide documents for the city or county to sign and return.

All necessary project cost documentation must be received prior to final payment.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.