Washington Administrative Code
Title 479 - Transportation Improvement Board
Chapter 479-05 - Program requirements
Section 479-05-212 - The stages of delayed projects

Universal Citation: WA Admin Code 479-05-212

Current through Register Vol. 24-18, September 15, 2024

For TIB funded projects, there are two stages of delay:

(1) Stage 1 delay - If the project does not meet the project target date per WAC 479-05-211.

(2) Stage 2 delay - If the project does not meet the revised bid date as agreed to under Stage 1 delay under WAC 479-05-213(1), or one year after being designated as a Stage 1 delayed project.

Statutory Authority: Chapter 47.26 RCW. 12-08-060, § 479-05-212, filed 4/3/12, effective 5/4/12; 07-18-050, § 479-05-212, filed 8/30/07, effective 9/30/07.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.