Section 479-05-211 - When a project is considered delayed

Universal Citation: WA Admin Code 479-05-211

Current through Register Vol. 24-18, September 15, 2024

Projects are considered delayed when one of the following occurs:

(1) Urban program projects do not reach construction phase within four years and six months.

(2) Projects awarded funding as "construction ready" will be considered delayed if construction does not begin within one year of funding becoming available.

(3) All other programs must reach construction phase within two years and six months.

The award date or date funding is made available to the local agency by TIB, whichever is earlier, is the starting point in calculating the delay date.

Statutory Authority: Chapter 47.26 RCW. 12-08-060, § 479-05-211, filed 4/3/12, effective 5/4/12; 09-09-002, § 479-05-211, filed 4/1/09, effective 5/2/09; 07-18-050, § 479-05-211, filed 8/30/07, effective 9/30/07.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.