Construction shall be deemed to have started with the initiation of any of the following construction activities:

(1) Site preparation by grading of the site, foundation excavation, or other significant earthwork on the site;

(2) Construction of footings or foundations, form work, installation of rebar, or pouring concrete for a project's major components or auxiliary structures;

(3) Excavation for natural gas supply, water supply, water or waste water discharge pipelines or structures;

(4) Earthwork or construction of access or service roads, electrical transmission lines, switchyard structures, or laydown areas.

Statutory Authority: RCW 80.50.040(1) and (12). 04-21-013, § 463-68-040, filed 10/11/04, effective 11/11/04.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.