(1) An application for site certification may be submitted when the preapplication process is completed. The preapplication process shall be complete when:
(a) EFSEC has held one or more public meetings under WAC
463-61-060(3);
and
(b) Negotiations between affected cities, towns, and/or
counties have been conducted and a corridor has been agreed on; or
(c) Negotiations under WAC
463-61-080 have been conducted
but the preapplicant, cities, towns, and/or counties have not agreed on a
corridor and EFSEC has determined that negotiations have failed.
(2) Applications for site certification of electrical transmission lines under RCW 80.50.045 and 80.50.060 shall follow the guidelines for applications for site certification found in chapter 463-60 WAC.
Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 08-21-092, § 463-61-100, filed 10/15/08, effective 11/15/08.
Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.