Washington Administrative Code
Title 463 - Energy Facility Site Evaluation Council
Chapter 463-61 - Electrical transmission facilities
Section 463-61-050 - Preapplication process
Current through Register Vol. 24-18, September 15, 2024
The preapplication request shall be filed with EFSEC at the EFSEC's office and contain the following information:
(1) The name and mailing address of the preapplicant, including a contact name, address, telephone number, and e-mail address of the contact person.
(2) A description of the proposed transmission route and corridor, including location maps and plot plans to scale, showing all major components, including a description of zoning and site availability for any permanent facility, and including whether and to what extent the proposed project is located within a national interest electric transmission corridor.
(3) A description of the proposed right of way width for the transmission line, including the extent a new right of way will be required or an existing right of way will be widened.
(4) A description of the proposed transmission line structures and their dimensions.
(5) A description of the schedule desired for the project, including the expected application filing date, the expected beginning date for construction, and the expected project operational date.
(6) A list of the federal, state, tribal and local government entities, including mailing addresses, contact names, telephone numbers and e-mail addresses that have possible permitting responsibilities for the project (if the project proponents were not to choose the EFSEC review) or ownership of land on which the project will be located. The list shall also identify governmental entities that have requested the preapplicant to notify them of any application or preapplication for site certification.
(7) Information or data that may be available at a later date.
(8) A summary and timeline of any initial consultation to explain the proposal and/or request input from the EFSEC staff, federal, state and local agencies, tribal governments, property owners, and interested persons.
(9) A public participation plan that:
(10) A negotiation process acceptable to EFSEC between the preapplicant and the cities, towns, and/or counties through which the proposed transmission line corridor will be located except where the cities, towns, and/or counties have designated transmission corridors through their land use plans or zoning ordinances.
Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 08-21-092, § 463-61-050, filed 10/15/08, effective 11/15/08.