Washington Administrative Code
Title 463 - Energy Facility Site Evaluation Council
Chapter 463-43 - Expedited processing
Section 463-43-050 - Expedited processing determination

Universal Citation: WA Admin Code 463-43-050

Current through Register Vol. 24-18, September 15, 2024

Following the review of an application, environmental checklist, and land use hearing and within one hundred twenty days of receipt of an application or such later time as is mutually agreed by the applicant and the council, the council by order will grant expedited processing for an application when it has found that:

(1) The proposed site is consistent and in compliance with city, county or regional land use plans, zoning ordinances; and

(2) The environmental impacts are not significant or may be mitigated to nonsignificant level under RCW 43.21C.031.

Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 09-05-067, § 463-43-050, filed 2/13/09, effective 3/16/09. Statutory Authority: RCW 80.50.040(1) and (12). 04-21-013, § 463-43-050, filed 10/11/04, effective 11/11/04. Statutory Authority: RCW 80.50.071. 78-05-054 (Order 78-2), § 463-43-050, filed 4/26/78.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.