(1) Introduction. Chapter 82.60 RCW established a limited sales and use tax deferral program. The purpose of the program is to promote economic stimulation, create new employment opportunities in distressed areas, and reduce poverty in certain distressed counties of the state. RCW 82.60.010.
This rule does not address specific requirements of RCW 82.08.02565 and 82.12.02565 that provide statewide sales and use tax exemptions for machinery and equipment used directly in a manufacturing operation. Repayment of tax deferred under chapter 82.60 RCW is not required, and interest and penalties under RCW 82.60.070 will not be imposed, on machinery and equipment that qualifies for exemption under RCW 82.08.02565 or 82.12.02565. For additional information on statewide sales and use tax exemptions for machinery and equipment refer to WAC 458-20-13601.
(2) Definitions. For the purposes of this rule, the following definitions apply:
The department, with the assistance of the employment security department, established a list of qualifying counties effective July 1, 2010. RCW 82.60.120. The list of qualifying counties is effective for a 24-month period and must be updated by July 1st of the year that is two calendar years after the list was established or last updated, as the case may be; or
"Eligible investment project" does not include any portion of an investment project undertaken by a light and power business as defined in RCW 82.16.010, other than that portion of a cogeneration project that is used to generate power for consumption within the manufacturing site where the cogeneration project is an integral part. It also does not include investment projects that have already received deferrals under chapter 82.60 RCW. RCW 82.60.020 and 82.60.049.
"Initiation of construction" does not include soil testing, site clearing and grading, site preparation, or any other related activities that are initiated before the issuance of a building permit for the construction of the foundation of the building.
If the investment project is a phased project, "initiation of construction" shall apply separately to each phase.
For purposes of this rule, both manufacturers and processors for hire may qualify for the deferral program as being engaged in manufacturing activities. For additional information on processors for hire, refer to WAC 458-20-136.
For purposes of this rule, "vegetable seeds" include the seeds of those crops that are grown in gardens and on truck farms and are generally known and sold under the name of vegetable or herb seeds in this state. "Vegetable seeds" include, but are not limited to, cabbage seeds, carrot seeds, onion seeds, tomato seeds, and spinach seeds. Vegetable seeds do not include grain seeds, cereal seeds, fruit seeds, flower seeds, tree seeds, and other similar properties.
* Specialized sewerage pipes connected to a qualified building that are specifically designed and used exclusively for manufacturing or research and development; and
* Parking lots connected to or adjacent to the building if the parking lots are for the use of workers performing manufacturing or research and development in the building. Parking lots may be apportioned based on qualifying use.
"Qualified buildings" does not include construction of landscaping or most other work outside the building itself, even though the landscaping or other work outside the building may be required by the city or county government in order for the city or county to issue a permit for the construction of a building.
(3) Who is eligible for the sales and use tax deferral program? A person engaged in manufacturing or research and development activity is eligible for this deferral program for its eligible investment project.
For example, the economic benefit of the deferral can be passed through to the lessee when evidenced in writing that the amounts paid to the lessor for construction of tenant improvements are reduced by the amount of the sales tax deferred. Another method of passing the economic benefit is if the lessee receives a credit for tenant improvements or other mechanism in the lease, equal to the amount of the sales tax deferred.
The following examples illustrate the application process with lessors and lessees.
Example 1. Prior to the initiation of construction, Owner/Lessor AA enters into an agreement with Lessee BB, a company engaged in qualified manufacturing or research and development. Under the agreement, AA will build a building to house BB's research and development activities, will apply for a tax deferral on construction of the building, will lease the building to BB, and will pass on the economic benefit in the amount of the deferral to BB. BB agrees in writing with the department to complete annual tax performance reports. AA applies for the deferral before the initiation of construction that is prior to the date the building permit is issued. AA is entitled to a deferral on building construction costs assuming all eligibility qualifications are met.
Example 2. The following example assumes no deferral on initial construction activity. After the building construction has begun, Lessee CC asks that certain tenant improvements be added to the building. Lessor DD and Lessee CC each agree to pay a portion of the cost of the improvements. DD agrees with CC in writing that DD will pass on the entire value of DD's portion of the tax deferral to CC, and CC agrees in writing with the department to complete annual tax performance reports. CC and DD each apply for a deferral on the costs of the tenant improvements they are legally responsible for before the date the building permit is issued for the tenant improvements. The department will approve both applications assuming all eligibility qualifications are met. While construction of the building was initiated before submission of the applications, tenant improvements on a building under construction are deemed to be the expansion or renovation of an existing structure. In addition, lessees are entitled to the deferral only if they are legally responsible and actually pay contractors for the improvements, rather than merely reimbursing lessors for the costs.
Example 3. After building construction has begun but before machinery or equipment has been acquired, Lessee EE applies for a deferral on machinery and equipment. The department will approve the application assuming all eligibility qualifications are met, and EE will be required to complete annual tax performance reports. Even though it is too late to apply for a deferral of tax on building costs, it is not too late to apply for a deferral for the machinery and equipment.
(4) What if an investment project is located in an area that qualifies as a high unemployment county and as a CEZ? If an investment project is located in an area that qualifies under more than one type of eligible area, the department will automatically assign the project to the eligible area that imposes the least burden on the taxpayer and with the greatest benefit to the taxpayer. If the applicant elects to be bound by the requirements of the other potential eligible area, the applicant must make a written statement to that effect.
Example 4. On October 1, 2014, a city in a high unemployment county qualifies as a CEZ, and the high unemployment county is on the list as a qualifying county. The CEZ employment requirements are more restrictive than those for qualifying counties. The department will assign the project to the qualifying county designation unless the applicant elects in writing to be bound by the CEZ employment requirements. Refer to subsection (7) of this rule for more information on the application process.
(5) When is apportionment of qualified buildings appropriate? The deferral is allowable only in respect to investment in the construction of a new building or the expansion or renovation of an existing building used in manufacturing or research and development. Where a building(s) is used partly for manufacturing or research and development and partly for purposes that do not qualify for deferral under this rule, apportionment is necessary.
Apportionment formula:
Percent of building eligible x Total Project Costs = Eligible Costs.
"Total Project Costs" is the cost of multipurpose buildings and other improvement costs associated with the deferral project. Machinery and equipment are not included in this calculation.
Eligible Costs (as determined above) x Tax Rate = Eligible Tax Deferred.
Example 5. A taxpayer is constructing a 10,000 square foot building, of which 8,000 square feet will be eligible for tax deferral. The cost of the project is $1,000,000. The combined sales/use tax rate at this location is 9.2%.
Based on the above apportionment formula, 80% of the building is eligible for deferral. By multiplying the qualifying percentage 80% by the cost of $1,000,000 to determine eligible costs of $800,000. Multiply the eligible cost of $800,000 by the sales/use tax rate of 9.2% to determine a sales/use tax deferral of $73,600.
Example 6. Taxpayer is planning to build a 10,000 square foot building of which 7,000 square feet will be used for manufacturing and 1,000 square feet will be common area. The remaining portion of the building will not be eligible for any deferral. The cost of the project will be $850,000 for the manufacturing area, $260,000 for the common area, and $140,000 for the remaining portion of the building, for a total cost of construction of $1,250,000. The combined sales/use tax rate at this location is 8.8%.
Based on the apportionment formula: 78% of common area costs are eligible. Multiply the common area costs of $260,000 by 78% to determine that $202,800 of common area costs are eligible for deferral. Therefore the $850,000 for the manufacturing portion of the building plus the $202,800 for common areas total $1,052,800 of eligible project costs. Multiply the eligible project costs of $1,052,800 by the tax rate of 8.8% to determine a sales/use tax deferral of $92,646.
(6) Are there any hiring requirements for an investment project? There may or may not be a hiring requirement, depending on the location of the project.
The department has instituted a geographic information system (GIS) to assist taxpayers in determining taxing jurisdiction boundaries, local tax rates, and a mapping and address lookup system to determine whether a specific address is within a CEZ. The system is available on the department's website at dor.wa.gov. A recipient must fill the qualified employment positions by the end of the calendar year following the year in which the project is certified as operationally complete and retain the positions during the entire tax year. Refer to subsection (12) of this rule for more information on certification of an investment project as operationally complete. If the recipient does not fill the qualified employment positions by the end of the second calendar year following the year in which the project is certified as operationally complete, all deferred taxes are immediately due.
(7) What are the application and review processes? An application for sales and use tax deferral under this program must be made prior to the initiation of construction, prior to taking possession of machinery and equipment, and prior to the filling of qualified employment positions. Persons, applying after construction is initiated or finished or after taking possession of machinery and equipment, are not eligible for the program. When an application for sales and use tax deferral is timely submitted, costs incurred before the application date are allowable, if they otherwise qualify. Applications for persons subject to hiring requirements must include information regarding the estimated total project cost and the qualified employment positions.
Similarly, after an application has been granted, a deferral certificate is no longer valid and should not be used if construction has not begun within one year from the date of application or there is not a specific and active program to begin construction within two years from the date of application. However, the department will grant requests to extend the period for which the certificate is valid if the holder of the certificate can demonstrate that the delay in starting construction is due to circumstances beyond the certificate holder's control such as the acquisition of building permit(s). Refer to subsection (9) of this rule for more information on the use of tax deferral certificates.
(8) What happens after the department approves the deferral application? The department will issue a sales and use tax deferral certificate for state and local sales and use taxes due under chapters 82.08, 82.12, and 82.14 RCW for an eligible investment project. The department will state on the certificate the amount of tax deferral the recipient is eligible for. Recipients must keep track of how much tax is deferred.
(9) How should a tax deferral certificate be used? A tax deferral certificate issued under this program is for the use of the recipient for deferral of sales and use taxes due on each eligible investment project. Deferral is limited only to investment in qualified buildings or qualified machinery and equipment as defined in this rule. Thus, sales and use taxes cannot be deferred on items that do not become part of the qualified buildings, machinery, or equipment. In addition, the deferral is not to be used to defer the taxes of the persons with whom the recipient does business, persons the recipient hires, or employees of the recipient.
The certificate holder must provide a copy of the tax deferral certificate to the seller at the time goods or services are purchased. The seller will be relieved of the responsibility for collecting sales or use tax upon presentation of the certificate. The seller must retain a copy of the certificate as part of its permanent records for a period of at least five years. A blanket certificate may be provided by the certificate holder and accepted by the seller covering all such purchases relative to the eligible project. The seller is liable for business and occupation tax on all tax deferral sales.
(10) May an applicant apply for multiple deferrals at the same project location? The department may not issue a certificate for an investment project that has already received a deferral under chapter 82.60 RCW. For example, replacement machinery and equipment that replaces qualified machinery and equipment is not eligible for the deferral. In addition, if an existing building that received a deferral under chapter 82.60 RCW for the construction of the building is renovated, the renovation is not eligible for the deferral unless the original deferral project is closed and has no more deferral requirements.
(11) May an applicant or recipient amend an application or certificate? Applicants and recipients may make a written request to the special programs division to amend an application or certificate when the original estimates change.
(12) What are the processes for an investment project? An applicant must provide the department with the estimated cost of the investment project at the time the application is made. Following approval of the application and issuance of a tax deferral certificate, a certificate holder must notify the department, in writing, when the value of the investment project reaches the estimated cost as stated on the tax deferral certificate.
Example 7. Taxpayer estimated a project end date of June 2018, but the project was actually operationally complete in November 2017. Taxpayer must submit the 2017 annual tax performance report by May 31, 2018. Taxpayer is responsible for notifying the department when the project is operationally complete regardless of the estimated completion date. If the 2017 annual tax performance report is not submitted timely, taxpayer will be assessed 12.5% of the deferred sales/use tax for this project.
Example 8. Taxpayer estimated a project end date of May 2017, but the project was actually not operationally complete until December 2017. Taxpayer must submit the 2017 annual tax performance report by May 31, 2018. Taxpayer is responsible for notifying the department when the project is operationally complete regardless of the estimated completion date. If the 2017 annual tax performance report is not submitted timely, taxpayer will be assessed 12.5% of the deferred sales/use tax for this project.
(13) Is a recipient of a tax deferral required to submit annual tax performance report? RCW 82.32.534 requires each recipient of a tax deferral to complete an annual tax performance report, every year, by May 31st for eight years following the year in which the project is operationally complete, regardless if the department has audited the project. If the economic benefits of the deferral are passed to a lessee as provided in RCW 82.60.025, the lessee must agree in writing to complete the annual tax performance report and the applicant is not required to complete the annual tax performance report. If the annual tax performance report is not submitted by the due date, or any extension under RCW 82.32.590, the recipient of the tax deferral or lessee, if required to submit, will be billed 12.5% of the deferred tax amount. For example, the deferral project is operationally complete in 2017. The recipient is required to submit the 2017-2024 annual tax performance reports that are due by May 31, 2018-2025, respectively. For more information on the requirements to file annual tax performance reports refer to WAC 458-20-267.
(14) Is a recipient of a tax deferral required to repay deferred taxes for reasons other than not submitting the annual tax performance report? Repayment of tax deferred under chapter 82.60 RCW is waived, as long as all eligibility requirements are met, except as provided in RCW 82.60.070 and this subsection (14).
The following describes the various circumstances under which repayment of the deferral may occur. Outstanding taxes are determined as of December 31st of each year by reference to the following table. No proration is allowed for completing a partial year of the deferral use requirement.
Repayment Year |
Percentage of Deferred Tax Waived |
|
1 |
(Year operationally complete) |
0% |
2 |
0% |
|
3 |
0% |
|
4 |
10% |
|
5 |
15% |
|
6 |
20% |
|
7 |
25% |
|
8 |
30% |
Any action taken by the department to disqualify a recipient for tax deferral or assess interest will be subject to administrative review pursuant to the provisions of WAC 458-20-100, Appeals. The filing of a petition for review with the department starts a review of departmental action.
(15) When will the tax deferral program expire? This tax deferral program is scheduled to expire July 1, 2020. No applications for deferral of taxes will be accepted after June 30, 2020. Businesses wishing to take advantage of this program are advised to apply to the department by April 30, 2020. While the department will make every effort to process applications in a timely manner, the department is allowed 60 days to review applications and issue deferral certificates. Applications received after April 30, 2020, may not be processed in time for the business to receive a deferral certificate and would not be eligible for the program. In addition, incomplete applications may be denied or not processed in time for the business to be issued a deferral certificate before July 1, 2020.
(16) Is debt extinguishable because of insolvency or sale? Insolvency or other failure of the recipient does not extinguish the debt for deferred taxes nor will the sale, exchange, or other disposition of the recipient's business extinguish the debt for the deferred taxes.
(17) Does transfer of ownership terminate tax deferral? Transfer of ownership does not terminate the deferral. The deferral is transferred, subject to the successor meeting the eligibility requirements of chapter 82.60 RCW, for the remaining periods of the deferral. Any person who becomes a successor to such investment project is liable for the full amount of any unpaid, deferred taxes under the same terms and conditions as the original recipient of the deferral. For additional information on successorship or quitting business refer to WAC 458-20-216.
Any questions regarding the potential eligibility of deferrals to be transferred on the sale of a business, should be directed to the special programs division as provided for in subsection (7)(a) of this rule.
Statutory Authority: RCW 82.32.300 and 82.01.060(2). 10-21-052, § 458-20-24001, filed 10/14/10, effective 11/14/10. Statutory Authority: RCW 82.32.300, 82.01.060(2), chapters 82.04, 82.08, 82.12 and 82.32 RCW. 10-06-070, § 458-20-24001, filed 2/25/10, effective 3/28/10. Statutory Authority: RCW 82.32.300 and 82.01.060(2). 06-17-007, § 458-20-24001, filed 8/3/06, effective 9/3/06; 04-01-127, § 458-20-24001, filed 12/18/03, effective 1/18/04. Statutory Authority: RCW 82.32.300. 01-12-041, § 458-20-24001, filed 5/30/01, effective 6/30/01; 88-17-047 (Order 88-5), § 458-20-24001, filed 8/16/88; 87-19-139 (Order 87-6), § 458-20-24001, filed 9/22/87; 86-14-019 (Order ET 86-13), § 458-20-24001, filed 6/24/86; 85-21-013 (Order ET 85-5), § 458-20-24001, filed 10/7/85.