Section 332-18-01003 - Issuing reclamation permits

Universal Citation: WA Admin Code 332-18-01003

Current through Register Vol. 24-18, September 15, 2024

(1) After July 1, 1994, the department shall not issue a reclamation permit until the applicant has:

(a) Met all requirements of these rules and the act;

(b) Provided documentation of SEPA review sufficient for the department to determine that the impacts of the proposal can be adequately mitigated;

(c) Received the following approvals if required by state or local governments:
(i) Approvals under local zoning and land use regulations;

(ii) A shoreline permit;

(iii) A hydraulic project approval; and/or

(iv) All solid waste permits.

(2) When an applicant has met all provisions of subsection (1) of this section, these rules, and the act, the department shall issue a reclamation permit within thirty days. Appeals of any existing permits listed in subsection (1) of this section shall not stay the timely issuance of a reclamation permit.

Statutory Authority: RCW 78.44.040, 34.05.220, 43.21C.135 and 78.44.250. 94-14-051, § 332-18-01003, filed 6/30/94, effective 8/2/94.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.