(1) The
engineering report must outline the scope of the LOSS project, provide
necessary background information, the design guidance or standards used,
calculations for developing plans and specifications, and impact on public
health and the environment.
(3) The engineer may incorporate by
reference, or include in an appendix, information developed for the site review
or environmental review, if still relevant.
(4) At a minimum the report must include:
(a) An executive summary providing a brief
overview of the following:
(i) Nature of the
project, such as a new development, expansion, phased construction;
(ii) Location of the LOSS;
(iii) Proposed ownership and
management;
(iv) Facilities served
when the development is complete;
(v) Design flow;
(vi) Wastewater characteristics and
strength;
(vii) Site and soil
characteristics; and
(viii)
Treatment and dispersal proposal;
(b) A narrative providing a detailed
explanation of the following:
(i) Facilities
served when the development is complete;
(ii) Existing or anticipated wastewater
characteristics and strength;
(iii)
Proposed treatment and dispersal method;
(iv) Local comprehensive plans, land use and
development regulations, sensitive area designations, and requirements by local
jurisdictions to connect to public sewer that apply to property the LOSS will
be sited on and the development to be served, including the primary and reserve
drainfield areas;
(v) Existing
sewer or water systems on the development site; and
(vi) Source of drinking water and water
system purveyor for properties served by the LOSS;
(c) A copy of the applicable parts of:
(i) City, town, or county comprehensive plans
or development regulations for property the LOSS will be sited on and the
development it serves, including the primary and reserve drainfield areas;
and
(ii) City, town, county, or
local health jurisdiction requirements for the property to connect to public
sewer;
(d) A statement
that the LOSS and development are consistent with the regulations and
designations identified in (c) of this subsection;
(e) An explanation of how the LOSS and the
development are consistent with the local comprehensive plan, land use and
development regulations, and sensitive and critical areas. The explanation must
provide sufficient information to demonstrate that the LOSS and the development
are consistent with these regulations and designations, and may include copies
of relevant portions of the local comprehensive plan, land use or development
regulations, sensitive area designations, or other related documents pertaining
to the LOSS site and proposed development;
(f) A copy of the SEPA checklist and
determination or other environmental review and local planning determination
for the project;
(g) A vicinity map
showing the project's location;
(h)
A map and development plan of the development area scaled to clearly show the
following:
(i) Total development
area;
(ii) Proposed primary and
reserve drainfield areas;
(iii) Any
surface water, wetland, or well within one thousand feet of the drainfield
perimeter;
(iv) Topographic contour
lines and elevations shown at intervals of ten feet or less and verified by
field measurements;
(v) Drainage
basins and drainage patterns throughout the development site;
(vi) Any existing or proposed storm water
systems or retention basins on the development site;
(vii) Location of one hundred-year flood
boundaries within one thousand feet of the drainfield perimeter;
(viii) Existing or proposed structures,
roads, and parking areas adjacent to the proposed drainfield;
(ix) Location of existing and proposed
encumbrances affecting system placement; and
(x) All water, sewer, greywater, reclaimed
water, storm water, irrigation lines within ten feet of the project or property
boundaries;
(i) An
analysis of the site's capacity to treat and dispose of the proposed quantity
and quality of sewage;
(j) SRS as
described in WAC
246-272B-03200, if one was
completed;
(k) HGR as described in
WAC 246-272B-03300, if one was
completed;
(l) Soil
characterization as described in WAC
246-272B-03400 if updated since
the department approval of the predesign report;
(m) A discussion of proposed treatment
processes addressing:
(i) Wastewater
characterization, flow patterns, and any site specific constituents of concern
of the wastewater;
(ii) Treatment
standard approved by the department in the site review and environmental review
process, and the expected treatment performance of the proposed treatment
technology;
(iii) Proposed O&M
activities; and
(iv) Any
alternative treatment processes evaluated;
(n) Confirmation, including calculations,
that the development and LOSS design complies with the minimum land
requirements in WAC
246-272B-03500;
(o) Design criteria, calculations, and any
other supporting material needed to develop the plans and specifications,
including:
(i) Design flow;
(ii) Soil type and hydraulic loading
rate;
(iii) Pipe sizes;
(iv) Hydraulic evaluation and drainfield
dosing calculations to determine dose volume, orifice size, spacing, residual
head;
(v) Pump selection with pump
and system curves;
(vi) Tank size;
and
(vii) Treatment component
design calculations, if applicable, and supporting performance
information;
(p)
Proposed monitoring and sampling for influent, effluent, and, if necessary,
water quality monitoring to demonstrate treatment standards will be met on an
ongoing basis;
(q) A summary
description of how the LOSS will be owned and managed after
construction;
(r) A copy of the
legal title or recorded easement to the property where the LOSS will be located
showing that the owner retains legal control of the drainfield and LOSS
components. If there will be sewage tanks on individual lots, the report must
include a plan for obtaining easements if not already established;
(s) Discussion of the construction process
summarizing how the requirements of Part 5 will be met;
(t) Updated general information, including
changes to the following:
(i) Name, telephone
number, fax number, mailing address, and e-mail address of:
(A) Owner of the LOSS proposal;
(B) Authorized representative of the owner,
if any;
(C) Legal owner of property
where the LOSS is proposed to be installed;
(D) Design engineer;
(E) Certified operator, if known;
and
(F) Any other project
contact;
(ii) Project
site address, county, tax parcel number, and legal description; and
(u) A management plan that meets
the requirements of WAC
246-272B-04100.