Washington Administrative Code
Title 246 - Health, Department of
SEWER SYSTEMS
Chapter 246-272B - Large on-site sewage system regulations
Part 2 - APPROVAL AND PERMITTING PROCESS
Subpart C - Permitted LOSS
Section 246-272B-02700 - Operating permit requirements and conditions
Current through Register Vol. 24-24, December 15, 2024
(1) The department shall issue a LOSS operating permit for the LOSS and owner named in the application.
(2) The department may issue a new operating permit when there is a change in LOSS ownership or management, according to WAC 246-272B-02550.
(3) LOSS owners shall employ one or more operators meeting the requirements of WAC 246-272B-07200 at all times and shall notify the department of any change in the operator, including when there is no operator, within thirty days.
(4) LOSS owners shall employ an approved management entity at all times that meets the requirements of WAC 246-272B-04100.
(5) Operating permit conditions may include, but are not limited to, requiring:
(6) The owner shall notify the department within five calendar days when the LOSS is not in compliance with any operating permit monitoring limit or condition.
(7) The owner shall submit an annual operating report that:
(8) Reports required in the operating permit have the following due dates:
Statutory Authority: RCW 70.118B.020. 11-12-035, § 246-272B-02700, filed 5/25/11, effective 7/1/11.