Section 246-272B-02300 - LOSS greater than 14,500 gpd - Operating permit and approval to construct
Current through Register Vol. 24-24, December 15, 2024
(1) The department shall consider comments received within thirty days of the first published public notice required by WAC 246-272B-02250, and may:
(2) The department shall notify the owner in writing of additional submittals required by subsection (1) of this section.
(3) The owner shall submit required information and changes to the LOSS design, O&M manual, or management plan to the department.
(4) After reviewing all submitted information, the department shall provide a written notice of determination to the owner.
(5) The department shall provide on the department's web site at doh.wa.gov the notice of final decision that identifies whether the LOSS operating permit has been approved and issued, or has been denied. The department may also use any of the following methods to provide the notice of final decision:
(6) An owner may appeal the department's decision on the operating permit by requesting an adjudicative proceeding consistent with WAC 246-272B-08200.
(7) An aggrieved person may appeal the department's issuance of an initial operating permit according to WAC 246-272B-08300.
(8) The department shall notify the owner in writing of approval to construct when all fees are paid and all appeals, if any, are resolved.
Statutory Authority: RCW 70.118B.020. 11-12-035, § 246-272B-02300, filed 5/25/11, effective 7/1/11.