Washington Administrative Code
Title 246 - Health, Department of
SEWER SYSTEMS
Chapter 246-272B - Large on-site sewage system regulations
Part 2 - APPROVAL AND PERMITTING PROCESS
Subpart A - New Construction
Section 246-272B-02100 - Engineering
Current through Register Vol. 24-24, December 15, 2024
(1) Upon receiving the department determination that the HGR contains sufficient information to determine the public health and environmental impacts of the LOSS and the LOSS is feasible, the owner may proceed with engineering. To proceed, the owner shall submit a copy, in electronic format acceptable to the department, of the engineering report that meets the requirements of WAC 246-272B-04000, and a draft O&M manual that meets the requirements of WAC 246-272B-04200 that are prepared, stamped, signed, and dated by a design engineer.
(2) After reviewing all submitted information, the department shall provide a written notice of determination to the owner.
(3) Upon receiving the notice to proceed, the owner may proceed with plans and specifications. To proceed, the owner shall submit a copy, in electronic format acceptable to the department, of plans and specifications that meet the requirements of WAC 246-272B-04400 that are prepared, stamped, signed, and dated by a design engineer.
(4) After reviewing all submitted information, the department shall provide a written notice of determination to the owner.
(5) If the department approves the plans and specifications, the department shall send a copy of the department-approved plans and specifications to the design engineer.
(6) The owner shall use department-approved plans and specifications for bidding and construction purposes.
Statutory Authority: RCW 70.118B.020. 11-12-035, § 246-272B-02100, filed 5/25/11, effective 7/1/11.