(1) The following school facility construction projects must be reviewed by the local health officer:
(a) Construction of a
new school facility;
(b) Schools
established in all or part of any existing structures previously used for other
purposes;
(c) Additions or
alterations consisting of more than five thousand square feet of floor area or
having a value of more than ten percent of the total replacement value of an
existing school facility;
(d) Any
construction of a shop or laboratory for use by students; and
(e) Installation of a portable.
(2) Review and approval requirements for installation of a playground are established in WAC 246-366A-150.
(3) School officials shall:
(a) Consult with the local health officer
during preliminary planning for school construction projects that are subject
to the requirements of this section;
(b) Invite the local health officer to a
predevelopment conference with school officials and project design
professionals to participate in the discussion about the preliminary design to
highlight health and safety matters and requirements of these rules;
(c) Obtain construction project review and
written approval from the local health officer regarding environmental health
and safety requirements in these rules before starting construction;
(d) Provide construction documents to the
local health officer at the same time as the local building official to
facilitate a concurrent and timely review; and
(e) Provide additional documents requested by
the local health officer, which may include, but are not limited to, written
statements signed by the project's licensed professional engineer verifying
that design elements comply with requirements specified by these
rules.
(4) The local health officer shall:
(a) Consult with school
officials and determine what is required for plan review and
approval;
(b) Review construction
documents to confirm that the health and safety requirements of these rules are
met;
(c) Identify and request any
additional documents required to determine compliance with requirements
specified by these rules; and
(d)
Provide written approval, or describe plan deficiencies needing change to
obtain approval, of the construction project within sixty days of receiving all
documents needed to complete the review, unless the school officials and the
local health officer agree to a different timeline.
Statutory Authority: RCW 43.20.050. 10-01-174, 10-12-018 and 11-10-080, § 246-366A-040, filed 12/22/09, 5/21/10 and 5/3/11, effective 7/1/13.
Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.