The department of health will use the following criteria for approving the installation of manufactured homes:
(1) New and relocated manufactured homes must be installed according to the manufacturer's written installation instructions;
(2) If the manufacturer's installation instructions are unavailable for manufactured homes, the department of health will accept the following:
(3)The department of health will inspect the installation to determine if the manufactured home is placed on a properly prepared site and anchored according to the:
(4)The department of health will require, at a minimum, specific instructions be obtained from a licensed engineer or architect when a manufactured home is to be installed on a site where the specific soil bearing capacity is not addressed in the manufacturer's instructions.
(5)The department of health may review, at a minimum, the following installation requirements:
(6)Water lines, waste lines, gas lines and electrical systems must be installed according to the requirements of this chapter.
(7)When skirting is used the skirting must:
(8)Provide access to the under floor area of the manufactured home so that all areas under the home are available for inspection. The opening must not be less than eighteen inches by twenty-four inches. The cover must be of metal, pressure treated wood or vinyl.