Section 220-660-330 - Authorized work times in saltwater areas
Current through Register Vol. 24-18, September 15, 2024
(1) Description: The department applies timing windows to reduce the risk of impacts to fish life at sensitive life stages. In-water work is not allowed during critical periods of the year unless a person can take mitigation measures to eliminate risk during critical periods.
(2) Fish life concerns: Work in or near salt waters of the state can harm fish life at sensitive life stages including spawning, incubation, juvenile migration, rearing, and feeding. Therefore, work must occur at times of the year when the risk to fish life is reduced unless the risk can be avoided.
(3) Authorized work times: The department must specify authorized work times for hydraulic projects when it issues HPAs. The department will allow work waterward of the OHWL for the following times, areas, and species.
Table 4 Authorized Times for Protection of Juvenile Salmonid Migration, Feeding and Rearing Areas and Pacific Herring Spawning and Surf Smelt Spawning Beds
AUTHORIZED TIMES | |||
Tidal Reference Area | Juvenile Salmonid Migration, Feeding and Rearing Areas | Surf Smelt Spawning Beds | Herring Spawning Beds |
1 | July 15 - February 15 | (not present) | April 1 - January 15 |
2 | July 15 - February 15 | April 1 - June 30 | April 1 - January 15 |
3 | July 15 - February 15 | May 1 - September 30 | April 1 - January 15 |
4 |
August 1 - February 15 for all work except dredging in all areas except Commencement Bay. September 1 - February 15 for dredging in all areas except Commencement Bay. July 15 - February 15 for all work in Commencement Bay. |
April 15 - September 30 | April 15 - January 15 |
5 |
August 1 - February 15 for all work except dredging. September 1 - February 15 for dredging in all areas except Duwamish Waterway. October 16 - February 15 for dredging in the Duwamish Waterway upstream of the East and West Water ways. |
April 1 - August 31 in all areas except Eagle Harbor and Sinclair Inlet. In Eagle Harbor and Sinclair Inlet, authorization is conditional upon inspection because year-round spawning occurs. |
May 1 - January 15 |
6 |
July 15 - February 15 for all work except dredging. September 1 - February 15 for dredging. |
April 1 - August 31 | (not present) |
7 |
July 15 - February 15 for all work except dredging in Port Gardner and the Snohomish River. September 15 - February 15 for dredging in Port Gardner. September 1 - February 15 for dredging in the Snohomish River. |
Authorization is conditional upon inspection because year-round spawning occurs. | April 15 - January 31 |
8 | August 1 - February 15 | Authorization is conditional upon inspection, because year-round spawning occurs. | April 15 - January 31 |
9 | August 1 - February 15 | Authorization is conditional upon inspection, because year-round spawning occurs. |
April 15 - January 31 south of a line running due west from Governor's Point. June 15 - January 31 north of a line running due west from Governor's Point. |
10 |
July 15 - February 15 July 15 - January 15 for all work from Tala Point to the Dungeness River. September 1 - March 1 San Juan Islands. |
April 1 - July 31 except in the San Juan Islands where authorization is conditional upon inspection because year-round spawning occurs. | May 1 - January 15 |
11 | July 15 - January 15 | March 1 - September 15 | April 1 - January 15 |
12 | July 15 - January 15 | March 1 - August 31 | April 15 - February 15 |
13 | July 15 - January 15 | February 16 - July 31 | April 15 - January 15 |
14 | July 15 - February 15 | October 1 - June 30 | (not present) |
15 | July 15 - February 15 | (not present) | February 1 - March 31 |
16 | July 15 - February 15 | (not present) | March 15 - January 31 |
17 | July 15 - February 15 | (not present) | March 15 - January 31 |