Washington Administrative Code
Title 196 - Engineers and Land Surveyors, Board of Registration for Professional
Chapter 196-33 - Rules of professional practice for licensees designing on-site wastewater treatment systems
Section 196-33-500 - Seal and stamp usage
Current through Register Vol. 24-06, March 15, 2024
The use of the seal/stamp shall be in accordance with chapters 18.43 and 18.210 RCW, or as otherwise described herein:
(1) Final documents are those documents that are prepared and distributed for use for construction, final agency approvals, use by clients, and record drawings or asbuilts for filing with public officials where such record drawings or asbuilts are required to be prepared by the licensee. Any final document must contain the seal/stamp, signature, and date of signature of the licensee who prepared or directly supervised the work. For the purpose of this section, "document" is defined as plans, designs, specifications, reports, and as-built documents prepared by the licensee.
(2) Preliminary documents are those documents not considered final as defined herein but are released or distributed by the licensee. Preliminary documents must be clearly identified as "PRELIMINARY" or contain such wording so it may be differentiated from a final document. Preliminary documents must be stamped, but need not be signed or dated by the licensee.
(3) Plan sets: Every page of a plan set must contain the seal/stamp and signature of the licensee(s) who prepared or who had direct supervision over the preparation of the work, and date of signature.
(4) Specifications: Specifications that are prepared by or under the direct supervision of a licensee shall contain the seal/stamp, signature of the licensee, and date of the signature. If the specifications prepared by a licensee are a portion of a bound specification document that contains specifications other than that of an on-site design nature, the licensee need only seal/stamp that portion or portions of the documents for which the licensee is responsible. Nothing herein should be construed to require that each page of an on-site design specification be sealed/stamped by the licensee.
(5) Document review: When a licensee is required to review work prepared by another licensed on-site designer, the reviewing licensee shall fully review those documents. If required, the licensee shall prepare a report that discusses the findings of the review with any supporting calculations and sketches. The reviewing licensee would then seal/stamp, sign, and date the report. The report would make reference to and/or be attached to the subject document(s) reviewed.
(6) Nothing in this section requires the stamping of plans/designs by employees of local health districts acting in that capacity as on-site inspectors/reviewers, whether or not licensed under chapter 18.210 RCW.
Statutory Authority: RCW 18.210.050, 18.210.060. 01-11-102, § 196-33-500, filed 5/21/01, effective 6/21/01.