(1) Preparation of draft and final EISs and SEISs is the responsibility of the environmental review section. Before the department issues an EIS, the responsible official shall be satisfied that it complies with these rules and chapter 197-11 WAC.
(2) The department normally will prepare its own draft and final EISs. It may require an applicant to provide information that the department does not possess, including specific investigations. However, the applicant is not required to supply information that is not required under these rules.
(3) If the department would be unable to prepare a draft and/or final EIS due to its commitments or other constraints or when a local agency transfers lead agency status to the department under WAC 197-11-940, the department may allow an applicant the following option for preparation of the draft and/or final EIS for the applicant's proposal:
(4) Whenever someone other than the department prepares a draft or final EIS, the department shall:
Statutory Authority: RCW 43.21C.120 and 43.21C.135. 84-13-037 (Order DE 84-21), § 173-802-090, filed 6/15/84. Formerly chapter 173-801 WAC.