(1) Applications for MSWLF permits and level of detail.
(2) Combined applications. Owners or operators may file a combined application for MSWLF units and other solid waste handling units, such as surface impoundments, composting facilities, and storage piles regulated under chapter 173-350 WAC, Solid waste handling standards, and MSWLF units closed under and/or regulated by chapter 173-304 WAC, Minimum functional standards for solid waste handling or other rules promulgated under the authority of chapter 70.95 RCW, including this regulation. The combined application must contain information required by each applicable regulation.
(3) Modification and renewal applications.
(4) Reissuance/transition applications. An application to reissue a permit previously issued pursuant to this regulation or to convert a chapter 173-304 WAC permit to a valid MSWLF permit under the transition permit rules of WAC 173-351-700(2) must include and address the following:
(5) Engineering plans, reports, and specifications. Unless otherwise specified in chapter 173-351 WAC, all engineering plans, reports, specifications, programs, and manuals must comply with the requirements of this subsection. Engineering plans, reports, specifications, programs, and manuals submitted to the jurisdictional health department or the department must be prepared and certified by an individual licensed to practice engineering in the state of Washington, in engineering disciplines associated with landfill design and construction or with experience in landfill design and construction and to practice engineering.
Note: |
All horizontal locations must be based upon a control station related to a horizontal datum specified in chapter 58.20 RCW and chapter 332-130 WAC (NAD.83). |
information (such as stratigraphic sections, geophysical and geochemical surveys, and water quality analyses);
(6) Construction quality assurance and construction quality control plans.
The construction quality assurance (QA) and construction quality control (QC) plan must address the construction of the MSWLF unit according to the designs set forth in chapter 173-351 WAC. (Construction QA and construction QC are defined in WAC 173-351-100.) The owner or operator may submit separate construction QA plans and construction QC plans. For each phase of construction, these plans must include:
Note: |
It is intended that owners or operators will select and pay for the independent third party construction quality assurance firm, who will report to the owner or operator. |
(7) Signature and verification of applications.
Statutory Authority: RCW 70.95.020(3), 70.95.060(1), and 70.95.260(1), (6). 12-23-009 (Order 07-15), § 173-351-730, filed 11/8/12, effective 12/9/12. Statutory Authority: Chapter 70.95 RCW and 40 CFR 258. 93-22-016, § 173-351-730, filed 10/26/93, effective 11/26/93.