Washington Administrative Code
Title 173 - Ecology, Department of (See also Titles 197, 317, 372, and 508)
Chapter 173-306 - Special incinerator ash management standards
Section 173-306-345 - Construction quality assurance plan
Universal Citation: WA Admin Code 173-306-345
Current through Register Vol. 24-06, March 15, 2024
(1) Before construction or modification, a detailed plan that shows how adequate and competent construction inspection will be provided to insure compliance with the requirements of this chapter and the approved engineering documents must be submitted to and approved by the department. The plan must be submitted according to a schedule specified in the permit.
(2) The construction quality assurance plan shall include:
(a) A
construction schedule summarizing planned construction activities, noting
sequence interrelationships, durations, and terminations;
(b) A description of construction management,
organization management procedures, lines of communication, and
responsibility;
(c) A description
of anticipated quality control testing, including type of test, frequency, and
who will perform the tests;
(d) A
description of the construction inspection program including inspection
responsibilities, anticipated inspection frequency, deficiency resolution, and
inspector qualifications; and
(e)
For monofills, a description of how WAC
173-306-440(4)(d)
is to be met.
Statutory Authority: Chapter 70.138 RCW. 00-19-018 (Order 00-17), § 173-306-345, filed 9/8/00, effective 10/9/00; 90-10-047, § 173-306-345, filed 4/30/90, effective 5/31/90.
Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.