Section 173-220-140 - Schedules of compliance
Current through Register Vol. 24-06, March 15, 2024
(1) The department shall establish schedules and permit conditions as follows to achieve compliance with applicable effluent standards and limitations, water quality standards, and other legally applicable requirements:
Any legally applicable schedule of compliance contained in:
(2) In any case where the period of time for compliance specified in subsection (1)(a) of this section exceeds one year, a schedule of compliance shall be specified in the permit which will set forth interim requirements and the dates for their achievement; however, in no event shall more than one year elapse between interim dates. If the time necessary for completion of the interim requirement (such as construction of a treatment facility) is more than one year and is not readily divided into stages of completion, interim dates shall be specified for the submission of reports of progress toward completion of the interim requirement.
(3) Either before or up to fourteen days following each interim date and the final date of compliance, the permittee shall provide the department with written notice of the permittee's compliance or noncompliance with the interim or final requirement.
(4) On the last day of the months of February, May, August, and November, the department shall transmit to the regional administrator a list of all instances in the previous ninety days of failure or refusal of a major permittee to comply with an interim or final requirement. Such list shall be available to the public for inspection and copying and shall contain at least the following information on each instance of noncompliance:
(5) If a permittee fails or refuses to comply with an interim or final requirement in a permit, such noncompliance shall constitute a violation of the permit for which the department may modify or revoke the permit or take direct enforcement action.
Statutory Authority: RCW 90.54.020 and chapter 90.48 RCW. 88-22-059 (Order 88-9), § 173-220-140, filed 11/1/88. Statutory Authority: RCW 90.48.035 and 90.48.260. 82-24-078 (Order DE 82-39), § 173-220-140, filed 12/1/82; Order DE 74-1, § 173-220-140, filed 2/15/74.