Section 173-145-060 - FCAAP project application process
Current through Register Vol. 24-06, March 15, 2024
The project application process for the eligible municipal corporations' applications includes the following in the general sequence given.
(1) The applicant shall prepare the project application to comply with the provisions of chapter 86.26 RCW and this chapter. The application must be made on a form furnished by ecology. A complete application shall include the following:
(2) The applicant shall review the preliminary project proposal with the county engineer, the Washington department of fish and wildlife and the department of natural resources and any affected Indian tribes.
(3) The applicant shall submit a prioritized list of project applications to the county engineer.
(4) The county engineer shall submit a prioritized list of all project applications within the county to ecology.
(5) The county engineer shall furnish evidence to ecology that the comprehensive flood control management plan described in WAC 173-145-040 is being prepared or is completed and adopted by the appropriate local authority and the flood plain management activities described in WAC 173-145-050 are being implemented.
Statutory Authority: RCW 86.26.105. 01-02-006 (Order 00-13), § 173-145-060, filed 12/21/00, effective 1/21/01. Statutory Authority: Chapter 86.26 RCW. 87-04-022 (Order 86-36), § 173-145-060, filed 1/28/87; 85-14-002 (Order DE 85-10), § 173-145-060, filed 6/21/85.