Current through Register Vol. 24-06, March 15, 2024
A floor and/or liner need not be installed directly under a
storage container having a capacity of one hundred thousand gallons or more
which has been constructed on site and put into use prior to March 1, 1994:
Provided, That one of the following alternative procedures are
complied with, certified to in writing by an official of the company which owns
the storage container, and the certificate is filed with the department:
(1) Alternative 1 is as follows:
(a) A second bottom made of steel shall be
constructed for the storage container. The second bottom shall be placed over
the original bottom and separated from the original bottom by a support medium
designed to provide for leak detection between the two bottoms and properly
support the new bottom. This support layer may consist of gravel, sand,
concrete (grooved to provide leak detection), steel or other grillage, wire
mesh, etc. as dictated by good engineering practice.
(b) The original bottom of the storage
container shall be tested for leaks before the support layer and second bottom
are installed. A record of the test shall be kept on file at the permanent
storage facility or at the nearest local office from which the permanent
storage facility is administered.
(c) The newly constructed bottom shall be
tested for leaks before any liquid fertilizer is stored on the newly
constructed bottom. A record of the test shall be kept on file at the permanent
storage facility or at the nearest local office from which the permanent
storage facility is administered.
(d) There shall be a system to readily detect
leaks through the newly constructed bottom into the support layer. Leak tests
should be conducted at not more than six-month intervals with a record of such
tests to be kept at the permanent storage facility or at the nearest local
office from which the permanent storage facility is administered.
(2) Alternative 2 is as follows:
(a) The storage container shall be emptied,
cleaned, and tested for leaks. The walls and floor of the storage container
shall be tested to assure that welds and thickness of steel plates are sound
and adequate to contain the fertilizers. A record of the inspection, test
results, and of any repairs made shall be submitted to the department and
maintained by the owner or operator.
(b) The interior floor and twelve inches up
the wall of the storage container shall be coated with a liner to inhibit
corrosion. A record of this procedure shall be submitted to the department and
maintained by the owner or operator.
(c) A test for leaks and liner deterioration
or metal corrosion shall be conducted every five years thereafter. A record of
the test findings and of indicated repairs and maintenance shall be maintained
by the owner or operator.
(3) Alternative 3 is as follows:
(a) Monitoring devices shall be installed in
angled borings under each storage container. These monitoring devices shall
constitute a leak detection system for each storage container in advance of the
point at which any leak would reach groundwater.
(b) The number, length, and depth of each
boring shall be determined on the basis of site characteristics. The array of
monitoring devices under each storage container shall constitute the best
practical early warning detection system for storage container
leakage.
(c) Each monitoring plan
under alternative 3 shall be implemented only upon review and written approval
of the department and shall include inspection/monitoring schedules.
Statutory Authority:
RCW
15.54.800. 00-23-075, § 16-201-031,
filed 11/17/00, effective 12/18/00.