Section 136-18-060 - Construction by county forces project records
Current through Register Vol. 24-18, September 15, 2024
All construction by county forces project cost records shall be kept in the manner prescribed by the BARS manual. Records of quantities shall be kept in a manner consistent with original project estimates. The project records shall contain, but shall not be limited to, the following:
(1) Dated authorizing resolution;
(2) Vicinity map showing project location and limits;
(3) County engineer's estimate;
(4) Affidavit of preconstruction publication required by RCW 36.77.070;
(5) Documentation of start and end of construction dates;
(6) Affidavit of post-construction publication showing true and complete project cost as required by RCW 36.77.070.
Statutory Authority: Chapter 36.78 RCW. 09-23-044, § 136-18-060, filed 11/9/09, effective 12/10/09. Statutory Authority: Chapter 36.79 RCW. 99-01-021, § 136-18-060, filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, § 136-18-060, filed 8/12/96, effective 9/12/96. Statutory Authority: Chapter 36.78 RCW. 79-01-098 (Order 35), § 136-18-060, filed 1/3/79; Order 27, § 136-18-060, filed 1/27/76.