Washington Administrative Code
Title 136 - County Road Administration Board
Chapter 136-170 - Execution of a CRAB/county contract
Section 136-170-050 - Combining of RATA funded project with non-RATA funded project

Universal Citation: WA Admin Code 136-170-050
Current through Register Vol. 24-18, September 15, 2024

In those cases when a county desires to combine a RATA funded project with one or more adjacent non-RATA funded projects, the county, prior to advertising for the construction contract, or prior to commencing construction should any of the projects be scheduled for completion by county forces, shall notify the county road administration board in writing of its plans to combine the projects into a single construction project, assuring in writing that the work items assigned to the RATA funded section will remain distinct and separate through the bid documents and contract plans.

Upon verification that the request is submitted in a timely manner, that the combined project will meet the conditions of the CRAB/county contract and prospectus requirements, and that RATA funded items of work will be sufficiently separated from other work, the CRAB director will respond in writing, to grant the combination. Projects shall be considered adjacent if they have a common terminus.

Statutory Authority: Chapter 36.78 RCW. 09-23-044, § 136-170-050, filed 11/9/09, effective 12/10/09. Statutory Authority: Chapter 36.79 RCW. 08-16-044, § 136-170-050, filed 7/29/08, effective 8/29/08.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.