Washington Administrative Code
Title 136 - County Road Administration Board
Chapter 136-163 - Allocation of RATA funds to emergent projects
Section 136-163-050 - Limitations and conditions

Universal Citation: WA Admin Code 136-163-050

Current through Register Vol. 24-18, September 15, 2024

All projects for which rural arterial program funding is being requested under this chapter are subject to the following:

(1) The requesting county has the sole burden of making a clear and conclusive showing that the project is emergent as described in this chapter; and

(2) The requesting county shall clearly demonstrate that the need for the project was unable to be anticipated at the time the current six-year transportation program was developed; and

(3) The requesting county agrees to a reduction in the next funding period's maximum RATA eligibility to the county equal to the RATA that may be awarded. Should that region not have a maximum RATA eligibility for each county, the requesting county agrees to withdraw, amend or delay an existing approved project or portion thereof in an amount equal to the RATA that may be provided for the project.

Statutory Authority: Chapter 36.79 RCW. 01-05-009, § 136-163-050, filed 2/8/01, effective 3/11/01; 99-01-021, § 136-163-050, filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.79.060. 96-17-014, § 136-163-050, filed 8/12/96, effective 9/12/96.

Disclaimer: These regulations may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.